ABC NETWORK INFRASTRUCTURE

The document outlines the hardware and software specifications for an ABC Network Infrastructure project, including detailed item descriptions, quantities, and costs. The total estimated cost for the hardware is 1,167,900 and for the software is 3,300, leading to a total project cost of 1,181,200. It also includes an implementation plan detailing phases, activities, duration, manpower, and responsibilities.

Uploaded by

tolasaamana25
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views

ABC NETWORK INFRASTRUCTURE

The document outlines the hardware and software specifications for an ABC Network Infrastructure project, including detailed item descriptions, quantities, and costs. The total estimated cost for the hardware is 1,167,900 and for the software is 3,300, leading to a total project cost of 1,181,200. It also includes an implementation plan detailing phases, activities, duration, manpower, and responsibilities.

Uploaded by

tolasaamana25
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

ABC NETWORK INFRASTRUCTURE

Hardware specification
no Item Specification Quantity Estimated unit cost price

1 server Model-IBM 770,64GB RAM,8GHz proc, 4 90000 360000


HDD 10TB

2 Pc Dell 7020,RAM 2GB, 3.12 GHz proc, HDD 64 12000 768000


50GB

3 Distribution switch D-link port 8 2 1200 2400

4 Access switch D-link port 16 8 1500 12000


5 Core switch D-link port 24 1 2000 2000
6 Network media UTP cat6e 2 roll 5000 10000
7 Network media Fiber optics 100m 3000 3000
8 Network connector RJ-45 500pcs 4 2000

9 Modem DSL 1 2500 2500


10 Router 16 port 1 3000 3000
11 firewall 1 3000 3000
Total price 1167900
Software specification
no Item Specification Quantity Estimated unit cost price

1 Microsoft window server 2008 enterprise edition 2 250 500

2 Windows OS Window 7 5 100 500

3 Network driver Driver solution 5 100 500

4 Utility software Antivirus(avast) 5 100 500

5 Application software Office 2010 or2007 5 100 500

6 Browser software Mozilla ,fire fox, Google, chrome 2 100 100

7 Microsoft SQL 2014 2 100 200

8 Email exchange software 2 250 500

Total price 3300


Cont………
• Task3: Calculate the total cost of the project
including hardware and software
• Hardware requirement =1167900
• Software requirement =3300
• Total cost =1181200
• Internet connectivity = broadband connection
=10000 per month for 10Mb/s speed per month
Cont…
Implementation plane
Phases Activities to be performed Duration manpower Responsibility

Planning Study/survey original business 2 day 3 Manager


requirement Supervisor
Allocate required budget for the project Network technical

Identify required infrastructure


Design Select appropriate topology 1 day 4 Network technical DBA
Design network model admin
Design logical diagram for the network Network admin
supervisor
implementation Install network media 2 day 4 Network technical DBA
Install required hardware and software admin
Network admin
Configure each network components supervisor

Configure security required.


Test Test server and client 1 day 3 Network technical DBA
Test security admin
Test network media and device Network admin
Maintain Troubleshoot hardware and software 2 day 3 Network technical DBA
admin
Troubleshoot network problem Network admin
Staff/user training