Daily Report Jan-28 2025

On January 28, 2025, construction activities included installing low voltage cables, AC ducts, and patching concrete, with no inspections conducted. The workforce comprised various teams including project managers, supervisors, electricians, and AC technicians, all working under sunny weather conditions. The workday began at 8:00 am and concluded at 6:01 pm, with all workers leaving the site afterward.

Uploaded by

Julio Quintero
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views

Daily Report Jan-28 2025

On January 28, 2025, construction activities included installing low voltage cables, AC ducts, and patching concrete, with no inspections conducted. The workforce comprised various teams including project managers, supervisors, electricians, and AC technicians, all working under sunny weather conditions. The workday began at 8:00 am and concluded at 6:01 pm, with all workers leaving the site afterward.

Uploaded by

Julio Quintero
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

Daily Report Tuesday 01/28/2025 by Julio Quintero “Site Construction Supervisor”

Working hours 8:00 am to 4:30 pm. 15-minute break at 10 o'clock and 30 minutes-lunch at 1:00 pm

Ritos Development: Ben Quality Projects:


1 Sr. Project Manager and 1 Supervisor 6 FrameTechnicians
Enrique Builders Choice:
Venext Air Conditioning: 2 Workers
2 AC-Technicians JOE’S EXCAVATOR. Concrete cutting
Complex Circuit. 2 Workers
4 Electricians Sids Low Voltage.
4 Electricians (+ 2 helpers)

The weather was a sunny day.

07:45 am to 8:00 am All the workers arrived at the construction site, they started at 8 o’clock

The gate was opened at 7:45 am

INSPECTIONS: No Inspection today

ACTIVITIES: Running low voltage cables; Installing the ceiling on the ground floor, in the bar area. Installing AC ducts on
the second floor. Patching on the concrete.
The framers continued with the ceiling on the ground floor.
Fixing the concrete slab on the Top roof
AC technicians installed more air ducts on the first floor

The plumbers were working on more conduits


Joe was working on the concrete cutting

The electricians installed some conduits on the second floor


Other framers were working on the AC return rooms
The low-voltage Technicians run cables on the second floor (TV, data, alarm, and camera cables)
Everybody left the site after 6:01 pm