A-simulation-based-approach-for-plant-layout-design-and-production-planning
A-simulation-based-approach-for-plant-layout-design-and-production-planning
net/publication/322708812
CITATIONS READS
72 3,529
5 authors, including:
All content following this page was uploaded by Zhinan Zhang on 27 January 2022.
ORIGINAL RESEARCH
Received: 7 October 2017 / Accepted: 19 January 2018 / Published online: 25 January 2018
© Springer-Verlag GmbH Germany, part of Springer Nature 2018
Abstract
Facing the new trend of Industry 4.0, manufacturing factories are required to have a more flexible structure to finish produc-
ing customized products within the limited time and at a reasonable cost. Although virtual factory technology is believed
to be helpful for plant layout design and production planning, there still lacks a general framework and algorithms of sim-
ulation-based approach to design an optimized plant layout and the production process. This paper proposes a framework
of simulation-based approach and develops a procedure for the implementation of the proposed framework. The paper also
integrates mathematical algorithms and heuristic methods when applying simulation to balance the operation performance
and the planning cost. An illustrative case demonstrates that the proposed approach can achieve the goal of better plant
layout design and production planning.
Keywords Industrial 4.0 · Plant simulation · Smart manufacturing · Layout planning · Virtual factory
13
Vol.:(0123456789)
1218 Z. Zhang et al.
13
A simulation-based approach for plant layout design and production planning 1219
it somehow fails to take other essential factors beyond simulation. Unfortunately, the factory layout design was not
the five factors into account, for instance, the fabrication within the scope of their research. Ducloux (2014) enlarged
process. Furthermore, VSM is not especially effective the scope of simulation for the entire manufacturing pro-
to evaluate, compare, and select the best option among cess to predict the properties of individual components. The
multiple alternative plans with respect to the estimated emphasis hinges on improving the life span prediction of
cost and schedule. Pahl et al. (2007) proposed a system- individual parts, instead of analyzing overall performance of
atic approach of layout drawing. Although 2D drawing the entire production line. Lindskog et al. (2016) proposed a
is effective to make the layout of a floor area visible, it method to improve the design of the manufacturing system
cannot effectively illustrate the deviations in the vertical through the visualization support. In this paper, they got
space. Moreover, it is extremely difficult, if not impossible, an accurate virtual representation of the current area and
to obtain the operational details simply from the layout would combine the representation with some models. Simu-
drawing, making it very difficult to follow the approach to lation was employed to identify the potential risks, while we
guide the implementation. hope to improve the overall design in terms of efficiency.
The substantial potentials of leveraging the simulation- Al-Ahmari et al. (2016) proposed a virtual reality environ-
related technologies and methods to enhance factory design ment, which was intended to train the frontline works who
have been suggested by many previous studies. For instance, operate assembly lines and to evaluate the assembly deci-
Mourtzis et al. (2014) reviewed those major milestones in sions. This environment only addressed a limited number of
the evolution history of simulation technologies, based on operations instead of operating the overall performance of
which, they projected the knowledge gap, future develop- a plant. Yap et al. (2014) put forward a method to facilitate
ment, and potential challenges of simulation in manufactur- the layout planning from the standpoint of virtual reality.
ing. Liu et al. (2013) also reviewed the development and The method emphasized on the human-robot interface and
application of simulation in manufacturing, with respect the layout planning for robot-centered work cells, with the
to, for example, the advantage, disadvantages, and further aim of overcoming the safety issues and the lack of trained
improvement of various simulation technologies. However, personnel.
they stayed on the theoretical level still. Neither have they Based on the above discussion, it is obvious that there
pointed out a systematic method to utilize simulation to is a knowledge gap. Some previous methodologies includ-
reinvent the manufacturing process. Mujber et al. (2004) ing different algorithms did not deal well with the dynamic
pointed out the potentials of employing Virtual Reality to manufacturing process, with the industry becoming more
enhance operation management and manufacturing process, and more highly collaborative, customer-oriented, eco-
based on the augmented virtual interactions between users efficient and knowledge-intensive. Although some people
and machines. Despite the obvious contributions of these interpreted the applications of simulation in the manufactur-
past studies to deepen the theoretical understandings, these ing industry, they left on the theoretical shelf and have not
review-oriented works are lack of details and specifics to elucidated a practical application procedure, which provides
guide the practical execution. a reference to enterprises. Some scholars had attempted to
There were indeed some experts attempting to apply the apply the simulation method to the factory practice, but they
simulation method into practice, but their focuses were lim- usually concentrated on a limited range of aspects, such as
ited to some sectors or different from us. For example, Siano assembly process, risk prevention, life prediction, etc. Few
et al. (2013) discussed the designing method and testing of the previous literature worked on optimizing the overall
method to present the simulation results and verify the effec- performance of a factory by means of simulation. Therefore,
tiveness. The methods are inspiring, but the model is mainly our study might be a significant point of reference to the
designed for electricity supply design and energy savings production activities in the future.
in smart homes, which cannot be applied to manufactur-
ing industry directly. For this shortage, recently, the new 2.2 Commercial plant simulation software
technology named digital twin was introduced in shop-floor,
e.g., Tao et al. (2017c) proposed the concept of digital twin Plant simulation software functions to facilitate managers
shop-floor in 2017, and the key is to realize the modeling and/or engineers to make more informed design decisions
and simulation of physical job-shop, and then realize the based on the visualization of operation or production. Some
integration and fusion between physical and cyber job-shop simulation software is developed by the industrial leading
(Tao and Zhang 2017). users. For example, Siemens, Dassault, and Applied Mate-
On the other hand, some researchers have endeavored rials have all developed their own plant simulation soft-
to apply simulation in practice. Grienitz et al. (2013) pro- ware (e.g., Siemens Tecnomatix Plant Simulation, Dassault
posed a method called GraFem to model and optimize the CATIA V6, and AutoMod) and provided a variety of ser-
manufacturing process, which is supported by the integrated vice packages to manufacturers. For instance, AutoMod can
13
1220 Z. Zhang et al.
help model operations at different levels, from the equipment changes, simulation can deal with more complex situation
level to the more complicated manufacturing, distribution, and approach closer to the reality. In addition to the static
automation and logistics levels. The users of ProModel do and discrete cases, simulation also handles some dynamic
not need to build models themselves and the software is and continuous information. Furthermore, by conducting
easy to learn. Furthermore, the simulation results can be simulation, different plans can be built, evaluated, tested,
generated in a relatively very short time (Promodel 2016). and eventually compared against different metrics. By doing
However, ProModel was only able to show 2D images. Users so, the optimal solution that yields the highest throughput at
could not simulate the 3D arrangement in the plant or get the the lowest cost can be identified. All the work could be com-
operation details accordingly. pleted before the factory is set up or transformed. In contrast,
Although the aforementioned plant simulation software the investment could be considerable given the company has
can provide nice functions for engineers to model and ana- to change the initial layout or modify the production process
lyze plant operations, these software or tools are different after the factory takes shape. Thus, it is of great significance
from each other and there still lacks a general approach for to perform simulation before building or transforming a fac-
engineers (especially the novice engineers) to gain an overall tory or a production line. A meta-model of simulation-based
cognitive understanding of how to perform plant simulation. approach is shown in Fig. 1, which consists of 5 key steps. A
well-constructed simulation model based on the abstraction
of a real physical system and its operating logic is of utmost
3 Proposed framework for plant simulation importance to lean plant simulation.
Section 3 presents the general framework and the procedures 3.2 System architecture of plant simulation
to implement the proposed framework, and thus to realize
the efficient design of plant layout and production line based To obtain a better plant layout and production planning,
on simulation. First, it is necessary to introduce the concept the right input information and data should be efficiently
of lean plant simulation and to develop a systematic archi- transformed into the desired output. Figure 2 illustrates the
tecture of plant simulation. system architecture of how to perform a simulation-based
lean design of layout and production planning. The frame-
3.1 Concept of efficient plant simulation work is composed of five major components: input, output,
design tools, simulation resource repository, and simulation
Simulation facilitates engineers to “see” the manufacturing modeling. Each component consists of different elements
process, which can help imitate the possible manufactur- that are intended to perform different functions. The inputs
ing process to see the outcome, considering the dynamic of the framework include, for example, physical structure of
parameters. According to the German Association of Indus- manufacturing unit, manufacturing process flow, logistics
trial Engineers, simulation refers to imitation of a dynamic planning and optimization, production equipment tooling,
process within a model to arrive at a better result that can and CAD drawings. The outputs of the framework include,
be transferred to the physical system. Unlike some math- for instance, process analysis, and logistics display. The
ematical algorithms, which could only take the parameters core component of the framework is the simulation mod-
as determined figures but fail to consider the arbitrary eling, which can be decomposed into (1) layout modeling,
13
A simulation-based approach for plant layout design and production planning 1221
Fig. 2 System architecture of simulation based lean layout and production planning
simulation and optimization; (2) process modeling, simula- systems, and equipment failures can be identified later. The
tion and optimization; and (3) logistics modeling, simulation detailed procedure of building the 3D model is shown in
and optimization. The tools layer shows the tools that can the following.
be used in lean plant simulation. The knowledge of how to Step 1. Analysis of the manufacturing process flow Fig. 3
use the tools is stored in simulation resource repository. The illustrates the procedure for process flow analysis. The first
simulation resource repository allows a company to manage step to build a virtual model is to have some insight into the
its resource related to plant simulation and thus to support process flow of the production line. Experts are required to
design and re-design of their plant layout and production grasp an idea of the characteristics of the production line,
lines. including the stability of the performance, the efficiency of
the production rate, the degree of the automation, the con-
3.3 A structured process efficient plant simulation venience of maintenance and the quality of the products. In
addition, experts are also expected to get more acquainted
Based on the proposed architecture of simulation-based effi-
cient layout and production planning, several procedures are
developed to support plant layout and production planning
design.
13
1222 Z. Zhang et al.
with the products, including their categories, functions, Step 2. Design and modeling of production line Fig. 4
strengths and shortcomings. shows the procedure for the design and modeling of a pro-
The second step is to model the corresponding relations duction line, which follows the analysis of the manufacturing
between the products and production lines. It is required to process flow. During the process of building models, the
analyze which process flow should be prepared to merchan- corresponding standards that the models have to conform to
dise the products and what devices are demanded. Then, it need to be taken into account. Furthermore, tradeoff should
is possible to build the virtual models of these devices and be made when deciding the final quality of the models, since
attempt to put them in a certain sequence afterward. it takes high time cost and labor cost to build the models of
It is worthy of note that the scope to be studied needs high precision.
to be confirmed so as to avoid invalid work and a waste of Step 3. Model simplification During the process of build-
resources. Engineers are required to pinpoint the bottlenecks ing models, a moderate amount of simplification is regularly
and verify the influence of every segment on the production needed. The first type of models, of which complexity needs
capacity of this plant. to be reduced, are the facilities purchased from the outside
parties, because the engineers have no access to the struc-
ture and operation details of these facilities. Another type is
the facilities of which structures are quite complex, such as
some facilities with multiple degrees of freedom.
13
A simulation-based approach for plant layout design and production planning 1223
layout accordingly, which will be discussed in Sect. 3.3.3 the performance of the current system and ask “what-if”
in detail. questions accordingly. They will change the parameters of
As mentioned above, the major consideration is the the system and even modify the initial layout to test the pos-
restriction conditions in the first step. The first are the fac- sible effects of those changes on the system. In such way,
tors which have a great effect on the construction address of numerous simulation runs will be performed, and an optimal
this factory, including traffic, labor rates, labor skills, land, setting will be identified.
and closeness to raw materials. These factors may decide
the degree of automation needed, the possible cost, and the 3.3.3 Optimal design of the current plan
feeding strategy. The second restrictive condition is charac-
teristics of demand. For instance, if the annual demand vol- To obtain the optimal design of the whole plan based on
ume is high and the variability is relatively low, the factory the simulation, experts first need to have an idea how they
is suggested to consider improving the degree of automation should understand the output results of the simulation. Then,
and taking advantage of scale economy. What is more, the multiple trials, comparison and analysis from various angles
sophistication of the available equipment is also a signifi- are a must.
cant limiting factor. If some equipment’s capacity is insuf- To find the meaning of the output value, there are two
ficient so that it becomes the bottleneck of the production methods which help use samples to estimate the population
line. Then extra attention is needed to this processing sector. value, i.e. point estimate and interval estimate. Point esti-
Then, according to the limitations and availability of mate is used to calculate the mean and standard deviation
models, the technological flow can be confirmed. The factors of the population, while interval estimate is to give more
to consider consist of rationality, economic efficiency, oper- information about the accuracy of the output parameters
ability, controllability and environmental concerns. Above estimation.
all, the safety of staff and users are the most important. The Then, it is required to settle down the output of current
design of the process flow will directly affect the quality and experiments and conduct more alternative designs. Different
quantity of the end products. plans will possibly have different performance, such as the
The layout is dominated by the process flow. There are average throughput and WIP held in the system. Experts are
four basic types of layout in total, which are fixed-position required to ensure the different performance observed are the
layout, process layout, cellular layout and product layout results of different settings instead of statistical variations so
(Zhang et al. 2015). Each kind of layout has its own advan- that they can reflect actual differences of the physical sys-
tages. The basic layout is mainly determined by the fea- tems. In addition to thinking of the system from the points of
tures of the products and should be modified in accordance engineering capacity, experts from various spheres includ-
with the specific conditions. Fixed-position layout is mainly ing finance, economics and management should help make
for job shop production. The products are typically large some tradeoff from different angles. For example, if the
and heavy so that they are difficult to move. Process layout system gives a high yield every time, it can take advantage
provides a higher flexibility because equipment is arranged of economical scale and avoid some setup cost. However,
according to their functions. In cellular layout, there are the inventory carrying cost is raised consequently. Thus,
many cells, each of which is designed to produce a limited higher throughput does not necessarily mean higher profit.
variety of products. Product layout is for mass production. The comprehensive analysis is crucial to select the optimal
Multiple pieces of devices or workstations are arranged in plan. The procedure for optimal design of current plan is
sequence. The work in process (WIP) are all moved through shown in Fig. 6.
the sequence.
After the initial layout is confirmed, parameters need to
be set. The possible parameters can include arrival rate of
raw materials, processing time on WIP, idle time, the capac-
ity of buffers and the speed of conveyors. It is worth noting
that some parameters are not a deterministic value but a
random number. In this case, some discrete and continuous
probability distribution can be taken use of to simulate these
stochastic variables.
Following the above all preparation work, simulation can
be carried out. The virtual experiment will run for days,
weeks or even months of the system activity in a short
elapsed real time, giving an output representing the result
of the objective functions. Then, those experts will analyze Fig. 6 Procedure for optimal design of current plan
13
1224 Z. Zhang et al.
3.3.4 Integration of algorithms and heuristic methods these three machines. While, all parts will go through K,
L and M after being produced in any of A, B and C. These
It is noteworthy that when applying simulation to the lay- 6 machines will occupy the sites 1, 2, 3, 4, 5, and 6, all of
out plan, the designers should make a wise decision when which are 1 × 1 sq m. The expected quantities of material
choosing mathematical algorithms and heuristic methods. flow between the production machines and the polishing
It is true that mathematical algorithms can better lead to the machines, and that amongst the polishing machines have
optimized solution, but it usually takes a long time, espe- been estimated as shown in the flow-between charts. Assum-
cially when the scenario is complex. In contrast, heuristic ing all the material flow are rectilinear movements between
methods can help obtain a good result much more quickly, centroids, the experts are required to obtain an assignment
which is acceptable and perform better than most solutions. of facilities to minimize the total cost, or quantity-distance
When applying the simulation, our system will first make product Table 1.
a forecast on the planning time needed by the implementa- The first method is to apply the mathematical algorithm
tion of the mathematical algorithm. Given it is within the to calculate the cost of every specific assignment to obtain
required time window, the mathematical algorithm will the global optimized solution. The model representing the
be applied. Otherwise, heuristic methods will be chosen total quantity-distance product should be
instead. An example on plant layout optimization will be
6 j=6
illustrated here to show how to choose from algorithms and 1 ∑∑
heuristics. We will use deterministic numbers here to facili-
TC(𝐚) = w d(a(i), a(j)) (1)
2 i=1 j=1 ij
tate our introduction, while for stochastic values, the simula-
tion methods can be applied. Where TC is the total cost, i.e. the quantity-distance prod-
Assuming that there are six manufacturing facilities in uct and a is the assignment vector of the 6 machines Table 2.
total, which are Production Machine A, B and C and Polish- There should be 6!/2 = 360 kinds of solutions to assign
ing Machine K, L and M. Since A, B and C are producing these facilities to the sites. Two example cases will be intro-
different parts of the products, the WIP will not flow among duced in detail.
Table 1 The layout of the sites (top), and the flow between the facili- Case 1 For A->1, B->2, C->3, K->4, L ->5,
ties (bottom) M->6, or assignment vector = (1,2,3,4,5,6). Then,
the total quantity-distance product for this lay-
1 3 5
out = 0(1) + 0(1) + 7(2) + 10(2) + 5(3) + 0(2) + 9(1) + 6(3)
2 4 6 + 6(2) + 4(1) + 8(1) + 9(2) + 4(2) + 3(1) + 6(1) = 135.
A B C K L M
K 7 9 4 K - 4 3 Case 2 For A->1, B->2, C->3, K->4, L ->6,
L 10 6 8 L - 6 M->5, or assignment vector = (1,2,3,4,6,5). Then,
M 5 6 9 M -
A – – – 7 10 5
B – – – 9 6 6
C – – – 4 8 9
K – – – – 4 3
L – – – – – 6
M – – – – – –
1 2 3 4 5 6
1 – 1 1 2 2 3
2 – – 2 1 3 2
3 – – – 1 1 2
4 – – – – 2 1
5 – – – – – 1
6 – – – – – –
13
A simulation-based approach for plant layout design and production planning 1225
the total quantity-distance product for this lay- only 6 times of calculation for the second heuristic method.
out = 0(1) + 0(1) + 7(2) + 10(3) + 5(2) + 0(2) + 9(1) + 6(2) Obviously, more calculation time and storage space are
+ 6(3) + 4(1) + 8(2) + 9(1) + 4(1) + 3(2) + 6(1) = 138. needed for the algorithm.
In this example, the deterministic weight is used for con-
Similarly, we can obtain the total costs for the remaining venience of calculation, while the weight can be a stochastic
358 assignments, and the minimum result is 135. value within a certain range following some distribution, in
The second method is the heuristic one to save time. The which case simulation is more applicable. Therefore, the
whole sites are divided into two parts, i.e. the production experts can set a planning time window first. Given the time
session and the polishing session. The production machines needed for algorithms is within the time limit, algorithm is
are allocated in Site 1, 2 and 3, while the polishing machines suggested to obtain the global optimum. Otherwise, if the
are assigned to Site 4, 5 and 6. We will consider the flow time goes beyond the time limit, heuristic method is recom-
within each session individually to confirm the allocation mended to save planning time.
in this department, while ignoring the flow across different
sessions. First, we consider the allocation within the pro-
duction session. Since there is no flow amongst the pro-
4 Application case
duction machines, we just assign them randomly. We can
just assign A to 1, B to 2 and C to 3. Then, we consider the
This section presents the implementation of the proposed
assignment within the polishing session. Assuming a is the
simulation-based approach, and briefly introduces an
assignment vector of the new departments, there should be
application case of the layout design and optimization of
3! = 6 kinds of assignments, which are a = (4,5,6), (4,6,5),
a workshop.
(5,4,6), (5,6,4), (6,4,5) and (6,5,4).
13
1226 Z. Zhang et al.
Therefore, there are almost no reliable guidelines for 4.2.2 The layout of the industrial robots and AGV
adjusting the layout of the workshop so that enterprise is not
able to correctly evaluate the manufacturing system layout The distance between the machine tools is only 1.73 m, so
and equipment configuration before the actual production. the smaller models of industrial robots are selected. Accord-
Due to the lack of three-dimensional dynamic simulation ing to the survey, three industrial robots of two series of
results, enterprises cannot make quantitative evaluation of FANUC can meet the demand. Taking the weight of the
the discrete manufacturing system. For example, it is not workpiece into account, FANUC M-16iB industrial robots
sure whether the systems which have been put into use have are adopted. To load and unload for two machines, an indus-
an adequate capacity to meet the production requirement trial robot is installed between two processing devices. It’s
in the face of new technology, new products, changes in needed to install a total of six industrial robots. The layout
production planning emergency and equipment maintenance is shown in Fig. 9.
status.
Thus, it is urgent to build a virtual working environ- 4.2.3 The path plans of AGV
ment of the whole workshop which can work as an effective
inspection tool for the new planning design. Based on the Forklift AGV path plans are shown in Fig. 10. There is a
above background, the proposed method is used to simulate total of nine stops, among which stop points cp1 to cp6 are
and optimize the layout of the workshop and the dynamic docking with the industrial robots. CpIn is the stop point
performance of the manufacturing system. docking with the shelves. CpWait is the waiting area where
AGV takes goods from the shelf, and cpOut is the stop point
4.2 The layout planning of warehouses during the downtime of forklift AGV. The operating path
of the forklift AGV is a bidirectional reversible path with a
4.2.1 The layout of the lathes turning radius of 1 m.
In the layout shown in Fig. 8, the width of the inter-device 4.2.4 The 3D plan of the whole warehouse
channel and the relative spacing between the two lathes is so
small that AGV and industrial robots cannot go through to The 3D digital model of the workshop is shown in Fig. 11,
complete the work. Considering movement space required including 12 machine tools, 6 FANUC industrial robots, a
by the forklift AGV and industrial robots, the adjustment forklift AGV, and a shelf. Figure 12 shows the relative posi-
of the location of the machine is needed. After calculation, tion of the industrial robot and the machining tools.
the forklift AGV flexible steering channel width should
not be less than 2.8 m. On this basis, the margin of 0.2 m 4.3 The simulation evaluation of production lines
can be added. The interval between the two sets of verti-
cal machines is adjusted to not less than 3 m. The interval The layout of the machines, the AGV path planning and
between the relatively-installed two machines is adjusted to the layout of the forklift truck in the workshop are shown
not less than 1.73 m, as shown in Fig. 8. in Figs. 9, 10, 11 and 12. On this basis, professionals can
13
A simulation-based approach for plant layout design and production planning 1227
simulate the operation of the workshop when they are given 4.3.1 Production efficiency
the production process and production planning.
The simulation runs for 12 h, and the output of the cam var-
ies with time is shown in Fig. 13. The output is regarded as
one set when completing every pallet with 6 cams in total.
Thus, the actual cam output is 6 times the output.
13
1228 Z. Zhang et al.
13
A simulation-based approach for plant layout design and production planning 1229
Table 3 The average utilization rate of devices achieve the objective of lean design of plant layout. Specifi-
Device category Serial number Utilization rate
cally, the paper suggests one way to judge whether math-
ematical algorithms or heuristic methods should be used,
Vertical machining tools Rmachine (1) 0.908 and the necessity has been proved. It can be speculated that
Rmachine (2) 0.907 this approach will have instructional significance to a slew
Rmachine (3) 0.902 of companies when they build or revamp a plant, arrange the
Rmachine (4) 0.902 facilities or staff and polish up the process flow. However,
Rmachine (5) 0.897 the available model library and the optimization method
Rmachine (6) 0.897 are not comprehensive for the time being. It’s suggested the
Rmachine (7) 0.894 future works make efforts to enrich these contents. And the
Rmachine (8) 0.894 way to achieve commercialization and synchronization will
Rmachine (9) 0.894 be discussed in the future work.
Rmachine (10) 0.894
Rmachine (11) 0.890 Acknowledgements This research is partially supported by the Minis-
Rmachine (12) 0.889 try of Industry and Information Technology of the People’s Republic of
China (2016ZXFM03002), the Shanghai Academy of Space Technol-
Industrial robots Rrobot(1) 0.049
ogy-Shanghai Jiao Tong University Joint Research Center of Advanced
Rrobot(2) 0.049 Aerospace Technology (USCAST2016-16) and National Key Technol-
Rrobot(3) 0.049 ogy Support Program (2015BAF18B02). Special thanks to Mr. Weimin
Rrobot(4) 0.048 Ding for the case study.
Rrobot(5) 0.048
Rrobot(6) 0.047
Forklift AGV Ragv 0.172 References
Alahmari A, Abidi MH, Ahmad A, Darmoul S (2016) Development of
a virtual manufacturing assembly simulation system. Adv Mech
factory will face the risk of confidential information leakage. Eng 8(3):1–13
Therefore, a company must make a comprehensive SWOT Automod (2017) http://www.appliedmaterials.com. Accessed 17 Dec
2017
analysis and compare the advantages and disadvantages to
CATIA V6 (2017) https: //www.3ds.com/produc ts-servic es/catia/ produ
make a wise decision. cts/v6/. Accessed 07 Oct 2017
Dasgupta D, Michalewicz Z (2013) Evolutionary algorithms in engi-
5.2 Limitations neering applications. Springer, Berlin
Ducloux R (2014) Improvement of part or tooling life prediction
through simulation of whole manufacturing process. Procedia
Although it has been pointed out that a wise decision Eng 81:504–509
between algorithms and heuristic methods is needed and Grienitz V, Hausicke M, Goerzel S, Dangelmaier W, Laroque C (2013)
an example has been given, this paper has not suggested the Systemic manufacturing process modelling and optimization with
integrated simulation. In: A. Klass (ed) Simulation in Produktion
most commonly-used algorithms or heuristic methods and
Und Logistk 2013, pp 99–108
has not discussed how to select from them. What is more, the Groover MP (2007) Fundamentals of modern manufacturing: materials
theoretical feasibilities have been proved, while the approach processes, and systems. Wiley, Hoboken
to set the time limit is not suggested as well. Therefore, more Kia R, Khaksarhaghani F, Javadian N, Tavakkolimoghaddam R (2014)
Solving a multi-floor layout design model of a dynamic cellular
work needs to be done before commercialization. Besides, manufacturing system by an efficient genetic algorithm. J Manuf
the paper mainly focuses the simulation in the stage of layout Syst 33(1):218–232
design before construction, while does not well discuss the Lenin N, Siva Kumar M, Islam MN, Ravindran D (2013) Multi-objec-
synchronization problem in the system operation process. tive optimization in single-row layout design using a genetic algo-
rithm. Int J Adv Manuf Technol 67(5–8):1777–1790
It should be better if our system can monitor the operation Li GQ, Zhao FQ, Guo C, Teng HF (2006) Parallel hybrid PSO-GA
within the production line in real time and help make adjust- algorithm and its application to layout design. In: International
ment from time to time. conference on natural computation. Springer, Berlin, Heidelberg,
749–758
Lin MH, Fu LC (2001) A virtual factory based approach to on-line
simulation and scheduling for an FMS and a case study. J Intell
6 Conclusions and future work Manuf 12(3):269–279
Lindskog E, Vallhagen J, Berglund J, Johansson B (2016) Improving
In this paper, we proposed a framework of simulation-base lean design of production systems by visualization support. Pro-
cedia CIRP 41:602–607
plant layout design and an operation procedure for plant sim- Liu XX, Liu QY, Wang W (2013) Development of virtual simulation
ulation. Case study showed that companies can refer to this in manufacturing industry. In: Applied mechanics and materials.
methodology and follow the above-mentioned framework to Trans Tech Publ, Switzerland
13
1230 Z. Zhang et al.
Molano JIR, Lovelle JMC, Montenegro CE, Granados JJR, Crespo RG Tao F, Guo H, Zhang L, Cheng Y (2012) Modelling of combinable rela-
(2017) Metamodel for integration of Internet of Things, Social tionship-based composition service network and theoretical proof
Networks, the Cloud and Industry 4.0. J Ambient Intell Humaniz of its scale-free characteristics. Enterp Inf Syst 6(4):373–404
Comput. https://doi.org/10.1007/s12652-017-0469-5 Tao F, Zuo Y, Xu LD, Zhang L (2014) IoT-based intelligent perception
Mourtzis D, Doukas M, Bernidaki D (2014) Simulation in manufactur- and access of manufacturing resource toward cloud manufactur-
ing: review and challenges. Procedia CIRP 25:213–229 ing. IEEE Trans Industr Inf 10(2):1547–1557
Mujber TS, Szecsi T, Hashmi MS (2004) Virtual reality applications Tao F, Cheng JF, Cheng Y, Gu SX, Zheng TY, Yang H (2017b)
in manufacturing process simulation. J Mater Process Technol SDMSim: a manufacturing service supply–demand matching
155:1834–1838 simulator under cloud environment. Robot Comput Integr Manuf
Pahl G, Beitz W, Feldhusen J, Grote KH (2007) Engineering design: a 45(6):34–46
systematic approach. Springer, Berlin Tao F, Cheng J, Qi Q (2017c) IIHub: an industrial internet-of-things
Plant Simulation (2017) https://www.plm.automation.siemens.com. hub towards smart manufacturing based on cyber-physical system.
Accessed 07 Oct 2017 IEEE Trans Industr Inf. https: //doi.org/10.1109/TII.2017.275917 8
Promodel (2016) Simulation Conversations with ProModel. 2016. https Tao F, Cheng J, Qi Q, Zhang M, Zhang H, Sui F (2017d) Digital
://blog.promodel.com. Accessed 07 Oct 2017 twin-driven product design, manufacturing and service with big
Promodel (2017) https://www.promodel.com/Products/ProModel. data. Int J Adv Manuf Technol. https://doi.org/10.1007/s0017
Accessed 07 Oct 2017 0-017-0233-1
Rong H (2011) Design of automatic block section signalling layout of Terkaj W, Tolio T, Urgo M (2015) A virtual factory approach for in situ
appling chaos embedded particle swarm optimization algorithm simulation to support production and maintenance planning. CIRP
based on skew tent map. Inf Control, Autom Robot 132:785–792 Ann Manuf Technol 64(1):451–454
(Lecture Notes in Electrical Engineering book series) Ullman DG (2017) The mechanical design process. McGraw-Hill, New
Siano P, Graditi G, Atrigna M, Piccolo A (2013) Designing and test- York
ing decision support and energy management systems for smart Yang T, Kuo Y, Su C, Hou C (2015) Lean production system design
homes. J Ambient Intell Humaniz Comput 4(6):651–661 for fishing net manufacturing using lean principles and simulation
Suh NP (2001) Axiomatic design: advances and applications. Oxford optimization. J Manuf Syst 34:66–73
University Press, Oxford Yap HJ, Taha Z, Dawal SZ, Chang S (2014) Virtual reality based sup-
Tao F, Qi Q (2017a) New IT driven service-oriented smart manufactur- port system for layout planning and programming of an industrial
ing: framework and characteristics. IEEE Trans Syst Man Cybern robotic work cell. PloS One 9(10):e109692
Syst. https://doi.org/10.1109/TSMC.2017.2723764 Yildiz AR (2013) A new hybrid artificial bee colony algorithm for
Tao F, Zhang M (2017e) Digital twin shop-floor: a new shop-floor para- robust optimal design and manufacturing. Appl Soft Comput
digm towards smart manufacturing. IEEE Access 5:20418–20427 13(5):2906–2912
Tao F, Zhao D, Hu Y, Zhou Z (2008) Resource service composition Zhang ZN, Liu G, Jiang ZC, Chen Y (2015) A cloud-based framework
and its optimal-selection based on particle swarm optimization in for lean maintenance, repair, and overhaul of complex equipment.
manufacturing grid system. IEEE Trans Industr Inf 4(4):315–327 J Manuf Sci Eng 137(4):040908
13