Commissioning Process A Step-by-Step Guide
Commissioning Process A Step-by-Step Guide
322Shares
Share
Share
Share
Share
Commissioning process helps to achieve the project goals. Have you ever
wondered how large complex projects are commissioned and started up?
There is a lot that goes on behind the scenes! Each project is different and
must have a unique plan to achieve the desired outcome. However, the
overall process to plan, commission, and startup a project is similar in each
case. Let’s review the steps for commissioning and startup. For additional
information, you can also check this article out to help you set your projects
up on success Project Mindset Lifecycle
Step 1 – Planning
There are several activities that take place off-site prior to the commissioning
team mobilizing to site during the design and construction phases of a
project. During design and construction, the schedule and sequence of
activities during commissioning are used to define the required construction
milestones, in order to plan the project schedule. The construction
milestones then define the required design milestones. From this sequence
of milestones, the project team is then aware of what activities need to be
compete and by when to ensure all the project components come together
as a final system for testing.
Any specialized test equipment or special tools are defined and procured
prior to commissioning. If the constructor is required to provide any
specialized equipment, this is defined as well.
And last but not least, safety management systems need to be established
prior to commencing any commissioning activities, learn more about safety
here Safety During Commissioning. The energy isolation procedures, also
known as Lock Out Tag Out (LOTO) process, needs to be established and
points of contact identified as responsible for the process.
During the design and procurement phase of the project, a critical step prior
to equipment delivery to site is Factory Acceptance Testing (FAT). FAT
verifies that the equipment is designed per specification before leaving the
factory, where any issues discovered are much easier and cheaper to fix,
rather than delaying testing until equipment is installed on-site.
Project Professionals
Commissioning Standards
Checklist Database
Beginner/Intermediate/Advanced Training
CxPM Certification
Mechanical process are slowly started, and piping is configured for the initial
operating scenarios. Flows are started and monitored to ensure correct
operation.
Automation is executed and fault scenarios are tested and verified. Read this
article to learn more about automation, watch the discussion video and learn
from Question and Answer portion The Correct Way to Commission
Automation Systems
The equipment undergoes analysis at each stage to ensure the plant process
is operating as specified. The Consultant SME and Owner reps are present to
verify correct operation of the plant process. The plant is not up and running
and functioning as a system – ready for fine-tuning to optimize the process.
Training is a key deliverable for the operating individuals to obtain from the
project. Contracts will typically define the training that the contractor is
required to provide. Training sessions should be arranged prior to
commissioning activities in order that operators have some experience with
the new systems prior to being asked to work with the new systems. Please
feel free to check our in-depth training here Commissioning Academy: Full
System Commissioning
Project Completion