Project Progress Report 12.11.2024
Project Progress Report 12.11.2024
2024)
Project : Kalyani Expressway To 4/6 Lane Configuration From Muragacha (Ch. 4+565 KM) To Kampa (Ch. 35+340 KM) Including Elevated
Connector with Proposed Mogra-Kampa-Barajaguli Road Corridor In West Bengal
B
Location A
Muragachha, Panihati at Ch. 4+565
Location B
Camp Location, Madrail at Ch. 26+600
Location C
Kampa More, Kachrapara at Ch. 34+000
Employer Contractor
Authority Engineer Design Consultant
West Bengal Highway Dineshchandra R. Agrawal
LEA Associates South Asia Asc Infrastructure Private
Development Infracon Pvt. Ltd.
Private Limited Limited
Corporation Ltd.
Review Meeting on 13.11.2024
1. Cost of Ground Improvement Chainage between 7+000 to 8+000 amounting 7.45 Cr. would be executed in COS-I, **
StrataWeb® Geocell SW356-150, StrataTex HSR™ 200 x 200, StrataWeb® Geocell 75mm thick.
2. Keutia More Modification work has been submitted cost amounting 0.13 Cr. of which would be executed from COS-II
4. IN Illumination work : 647 number of Poles erected out of 1256 as per Scheduled Scope
Regarding Scope of Drain
2 Descoped per the Direction of PWD Secretariat 1.100 at Km. 5 (Near Muragacha More)
2 14+875 14+895 RHS 20.00 Payment Released Conformation Awaited from Land Owner