Project Progress Report 21.10.2024
Project Progress Report 21.10.2024
Project : Kalyani Expressway To 4/6 Lane Configuration From Muragacha (Ch. 4+565 KM) To Kampa (Ch. 35+340 KM) Including Elevated
Connector with Proposed Mogra-Kampa-Barajaguli Road Corridor In West Bengal
B
Location A
Muragachha, Panihati at Ch. 4+565
Location B
Camp Location, Madrail at Ch. 26+600
Location C
Kampa More, Kachrapara at Ch. 34+000
Employer Contractor
Authority Engineer Design Consultant
West Bengal Highway Dineshchandra R. Agrawal
LEA Associates South Asia Asc Infrastructure Private
Development Infracon Pvt. Ltd.
Private Limited Limited
Corporation Ltd.
Salient Features of The Project
** DBM Length has shown including the Structure Portion Length, Toll Plaza, Segment D, which are are .750, .800 and .936 respectively
Physical Progress (Structure)
1 5+122 Culvert at Service Road (LHS/RHS) Pending, Centre Done, BHS work is in Progress
2 7+712 17 Meter Pending (RHS), 10 Meter Raft Done and Wall is in Progress (COS)
3 9+500 2 meter Box Pending at RHS due to Electric Cable
4 13+400 0.500 m (LHS) Pending
5 13+877 Full Culvert Pending, Excavation has been started
6 15+550 2.5 meter box pending RHS (COS)
Total Scope and Progress of Drain and Obstruction as on Date
** 3,276 meter Drain has to be Constructed on the both sides of RE/RS Wall as additionally proposed
Miscellaneous Work Progress
Thank You