00_WindPowerFinancePractical_293_v0
00_WindPowerFinancePractical_293_v0
118
138 m (Enercon E-82, 2 MW
116 generator, 5281 m2 swept
114 rotor area)
112
20% higher AEP from 61,5 m
110 to 111,5 m (Nordex N77, 1.5
108 MW generator, 4657 m2
106 swept rotor area)
104 AEP calculation according to
102 FGW technical standard 5
100
60 80 100 120 140
Hub height (m)
Source: AGORA energiewende „Vergutung von
Windenergieanlagen an Land uber das
Referenzertragsmodell”, Tabelle1, 2014
Average hub height of wind turbines built in Germany in 2013: 117 m
19
Power curves of different wind turbines
Power output as share of rated power of
Turbine A
Turbine B
500
400
300
200
100
0
1000 5000 8000
Rated power of generator (W)
25
Exercise: specific power of wind turbines
Exercise: Calculate the rotor blade length of different wind turbines
Source: Molly, 2011, „Rated Power of Wind Turbines: What is Best?“
Profile above area with low Profile above area with high
roughness (sea, low grass) roughness (forest, town)
Revenues in Wind Power
Free, gross and net AEP (annual energy production)
Energy yield calculations are based on relevant topographic, meteorological,
and technical input data and on the mathematical methods applied to them
Aim of a wind resource assessment is to derive the: expected Annual Energy
Production (AEP)
Free AEP = annual energy production without any losses
Farm AEP or gross AEP = free AEP minus wake loss
Net AEP = gross AEP minus all other energy losses
Source: RENAC, 2016
Thursday, June 07, 2018 53
Revenues in Wind Power
Benchmark data for losses on AEP
Shading losses in the wind farm (wake effect) [%], approx. 3% - 15% or larger
Internal grid losses [%]: approx. 1.5% - 3%
Technical availability losses [%]: approx. 3%
Availability of grid connection [%]: approx. 0.5%
Sector Management [%]: depends on regulations / no rule of thumb
Blade Degradation [%]: approx. 0% - 0.5%
Icing [%]: depends on climate at site / no rule of thumb
Curtailments [%]: depends on regulations and permits / no rule of thumb
NOTE: Possible losses are depending on turbine size and number
NOTE: All indications are highly project specific and can be higher or lower.
Web links [1] [2] [3] Source: RENAC, 2016
Thursday, June 07, 2018 54
Exercise: free, gross (farm) and net AEP
Task: Answer the following questions and note results.
1. What is the difference between free, farm (gross) and net AEP?
2. Calculate the gross and the net AEP for a wind farm with 10 wind turbines
Free AEP of a single wind turbine: 12,0 GWh / WTG
Farm efficiency of 90% (wake effect)
Losses for
availability of 3%,
in- & external grid of 3%,
curtailments of 2% and
all other losses of 2%.
3. Which additional impacts might change the result of the AEP?
Source: RENAC, 2016
Thursday, June 07, 2018 55
Annual energy production estimation with capacity factor
and full load hours
Capacity factor
Definition: capacity factor is the ratio of the actual energy produced in a given
period, to the hypothetical maximum possible, i.e. running full time at rated
power.
Wh
Annual energy production a
Capacity factor %
Rated power of wind turbine W !"#$ #% &' "#( )/
Data source:
Annual energy production (Wh/a) has to be measured for a project
Rated power of wind turbine (W) is know from the turbine fact sheet
Duration of period is usually one year = 8760 h/a
57
Annual energy production estimation with capacity factor
and full load hours
Full load hours
Definition: Full load hours are calculated by dividing the turbine’s average
annual energy production by its rated power
Wh
h Annual energy production a
Full load hours
a Rated power of wind turbine W
Data source:
Annual energy production (Wh/a) has to be measured for a project
Rated power of wind turbine (W) is know from the turbine fact sheet
Full load hours can also be calculated by multiplying the capacity factor by the
duration of the period of operation (usually one year with 8760 h/a)
58
Annual energy production estimation with capacity factor
and full load hours
Typical full load hours and capacity factors for wind farms and
wind turbines
Site Capacity Full load
factor (%) hours (h)
Onshore at coast line in Germany,
~ 0.35 ~ 3050
hub height 100m
Onshore average in Germany (all
~ 0.2 ~1750
turbines)
Small wind turbines, 0.15 – 0.2 or higher at
1300 - 1750
good sited good sites
Small wind turbines,
< 0.05 < 450
bad sited
Offshore wind farm in German
0.4 – 0.5 3500 - 4000
North Sea
59
Exercise: Annual energy production estimation with
capacity factor and full load hours
Task: Calculate the capacity factor and full load hours
Input data turbine A:
300 kW rated power of wind turbine
811 MWh/a generated energy during one year
Input data turbine B:
Wind turbine with 2500 kW rated power
8442 MWh/a (MWh generated energy during one year)
Results:
Capacity factor Full load hours / year
Turbine A
Turbine B
60
Exercise: annual energy production estimation with
capacity factor and full load hours
Task: Calculate the annual energy output of turbine A and B
Wind turbine A:
2300 kW rated power and 4150 full load hours
Calculate the annual energy production and the capacity factor
Wind turbine B:
2300 kW rated power and 0,415 capacity factor
Calculate the annual energy production and the full load hours
Results: Rated power Annual energy Full load hours Capacity
(kW) generation (kWh/a) (h/a) factor
Turbine A 2300 4150
Turbine B 2300 0,415
62
Exercise: Estimate the annual energy generation for a
25 km2 wind farm
Assume you have an area of 25 km2 for your wind farm
Assume a capacity factor of 0.35
Assume the distance between wind turbines standing in main wind direction is 7
rotor diameter; and standing in in rarely occurring perpendicular wind direction is
5 times the rotor diameter
Calculate the following parameters for every wind turbine:
Number of turbines in the area
Installed wind power capacity (MW)
Annual energy production (GWh/a
Wind turbine input data:
Turbine A Turbine B
Specific turbine power (rated power per swept rotor area (W/m2)) 196 568
Rated power of wind turbine, MW 2 3
Rotor diameter of wind turbine, m 114 82
64
Exercise: Estimate the annual energy generation for a
25 km2 wind farm
Table for results
Turbine A Turbine B
Specific power (rated power per swept rotor area, W/m2) 196 568
Rated power of wind turbine, MW 2 3
Rotor diameter of wind turbine, m 114 82
Number of turbines in the area
Installed wind power capacity, MW
Annual energy production with capacity factor of 0.35, GWh/a
65
Exercise: Estimate the annual energy generation for a
25 km2 wind farm, wind turbine A
Main wind direction
Area for the wind farm:
5 km x 5 km
Rotor diameter
turbine A = 114 m
Rarely occurring
wind direction
66
Exercise: Estimate the annual energy generation for a
25 km2 wind farm, wind turbine B
Main wind direction
Area for the wind farm:
5 km x 5 km
Rotor diameter
turbine B = 82 m
Rarely occurring
wind direction
67
Exercise: Capacity factor and full load hours
Task: Answer the following questions and note results.
1. Which effects might influence the capacity factor and full load hour of a
wind farm?
2. Can capacity factors and full load hours be used for a bankable wind farm
report and an investment decision?
69
Annual Energy Production:
Calculation with Wind Speed
Distribution and Wind Turbine
Power Curves
Annual energy production with power curves and
measured wind speed data
Methodology
With wind speed distributions and wind turbine
Ei in kWh
power curves:
vi = wind speed class i [m/s]
hi = relative frequency of wind speed class in
%
Pi = power output of wind turbine at wind
speed class vi [kW]
Ei= energy yield of wind speed class i [kWh]
Pi in kW
vi in m/s
Power curve of a
hi in % specific wind turbine
vi in m/s
© RENAC 2014
Wind speed distribution
vi in m/s for a specific site
Thursday, June 07, 2018 72
Annual energy production with power curves and
measured wind speed data
Methodoloy
Ei = Pi x ti
Ei = energy yield of wind class, i = 1, 2, 3 …n
[Wh, watthours]
ti = duration of wind speeds at wind class
[h/a, hours/year]
Pi = power of wind class vi of wind turbine power curve
[Watt, joule per second]
EΣ = E1 + E2 +…+ En
EΣ = energy yield over one year [Wh/a, watthours / year]
Source: RENAC, 2016
Thursday, June 07, 2018 73
Annual energy production with power curves and
measured wind speed data
Example: combination of wind speed distribution and power curve
vi vi
(m/s Time ti Power curve Energy Ei (m/s Time ti Power curve Energy Ei
) (h/a) P (kW)
i (kWh/a) ) (h/a) Pi (kW) (kWh/a)
1.0 20.2 0 0 9.0 1,162.6 1180 1,371,891
2.0 113.3 3 340 10.0 796.4 1612 1,283,808
3.0 305.0 25 7,624 11.0 443.4 1890 838,036
4.0 593.4 82 48,661 12.0 196.0 2000 391,938
5.0 938.3 174 163,265 13.0 67.0 2050 137,333
6.0 1,256.0 321 403,163 14.0 17.2 2050 35,312
7.0 1,439.5 532 765,811 15.0 3.2 2050 6,630
8.0 1,408.3 815 1,147,750 16.0 0.4 2050 881
Example: @ vi=7.0 m/s the annual energy production is
1,439.5 h/a x 532 kW = 765,811 kWh/a
The calculation ends at 16 m/s because higher wind speeds
contribute very little to the total energy output
Source: RENAC, 2016
Thursday, June 07, 2018 74
Annual energy production with power curves and
measured wind speed data
Example: summation over all wind speed classes
vi Time Power curve Energy
(m/s) ti (h/a) Pi (kW) Ei (kWh/a)
1.0 20.2 0 0
2.0 113.3 3 340
3.0 305.0 25 7,624
4.0 593.4 82 48,661 Summation over all wind
5.0 938.3 174 163,265 speed classes = annual
6.0
7.0
1,256.0
1,439.5
321
532
403,163
765,811
∑ energy production = 6.603
8.0 1,408.3 815 1,147,750 MWh/a (for a specific
9.0 1,162.6 1180 1,371,891 wind turbine at a specific
10.0 796.4 1612 1,283,808 site)
11.0 443.4 1890 838,036
12.0 196.0 2000 391,938
13.0 67.0 2050 137,333
14.0 17.2 2050 35,312
15.0 3.2 2050 6,630
16.0 0.4 2050 881
17.0 0.04 2050 80
Source: RENAC, 2016
Thursday, June 07, 2018 75
Exercise: Annual energy production with power curves and
measured wind speed data
Task: Calculate and compare the revenues of wind farm A and B
Available data:
Turbine A power curve (data see next slide), rated power 3300 kW,
115 m hub height, 250 W/m2 specific WT power
Turbine B power curve (data see next slide), rated power 3450 kW,
117 m hub height, 280 W/m2 specific WT power
One year side specific measured wind speed data (data see next slide)
Assumptions
technical availability of 98% for the entire wind farm
Assume a wake effect of 7% for the entire wind farm
Assume a tariff of 78 $/MWh, 20 year of operation and 10 wind turbines
76
Exercise: Annual energy production with power curves and
measured wind speed data, turbine A
Turbine A: Wind speed distribution and power curve
vi vi
(m/s Time ti Power curve Energy Ei (m/s Time ti Power curve Energy Ei
) (h/a) (kWh/a)
Pi (kW) ) (h/a) Pi (kW) (kWh/a)
0.50- 8.50- 2,576.9
1.50 83 0.0 9.50 928
1.50- 9.50- 3,111.4
2.50 259 0.0 10.50 686
2.50- 10.50- 3,273.9
3.50 510 41.4 11.50 452
3.50- 11.50- 3,297.3
4.50 785 179.1 12.50 265
4.50- 12.50- 3,299.9
5.50 1,029 410.2 13.50 137
5.50- 13.50- 3,300.0
6.50 1,186 756.8 14.50 62
6.50- 14.50- 3,300.0
7.50 1,219 1,235.8 15.50 25
7.50- 15.50- 3,300.0
8.50 1,123 1,856.2 16.50 9
Source: RENAC, 2016
Thursday, June 07, 2018 77
Exercise: Annual energy production with power curves and
measured wind speed data, turbine B
Turbine B: Wind speed distribution and power curve
vi vi
(m/s Time ti Power curve Energy Ei (m/s Time ti Power curve Energy Ei
) (h/a) (kWh/a)
Pi (kW) ) (h/a) Pi (kW) (kWh/a)
0.50- 8.50-
1.50 83 0 9.50 928 2,471.70
1.50- 9.50-
2.50 259 0 10.50 686 3,201.90
2.50- 10.50-
3.50 510 24.3 11.50 452 3,449.70
3.50- 11.50-
4.50 785 172.8 12.50 265 3,450.00
4.50- 12.50-
5.50 1,029 391.7 13.50 137 3,450.00
5.50- 13.50-
6.50 1,186 712.3 14.50 62 3,450.00
6.50- 14.50-
7.50 1,219 1,158.30 15.50 25 3,450.00
7.50- 15.50-
8.50 1,123 1,740.60 16.50 9 3,450.00
Source: RENAC, 2016
Thursday, June 07, 2018 78
Annual energy production with power curves and
measured wind speed data
Exercise: Comparison of wind farm A and B during 20 years
Gross Gross AEP Revenues,
Installed Free AEP Revenues
(farm) AEP during 78 $/MWh
capacity 1 year differences
1 year 20 years Tariff
Mio. $ / Mio. $ /
MW MWh/a MWh/a MWh/a
20a 20a
Turbine A
Turbine B
Thursday, June 07, 2018 79
Exercise: full load hours and the capacity factor
Task: Answer the following question and note results.
1. What are the full load hours and the capacity factor of turbine A and
turbine B taking into account the 7% wake effect and 98% technical
availability?
Gross AEP (including 7%
Installed wind Capacity Full load
wake effect + 98% techn.
farm capacity factor hours
availability)
MW MWh/a % h/a
Turbine A 33
Turbine B 34.5
83
Wind direction
Wind direction
in % for each
sector
5% 10%
85
Example: Gross annual wind farm energy production,
wind direction analysis
Wind study results for 16x Siemens SWT-3.3-130
Free Annual Energy Production (AEP) = gross AEP + wake loss = net AEP + all losses
The uncertainty associated to this result quantifies possible deviations.
Free AEP
Wake losses
Gross AEP
Free AEP
Wake losses
Gross AEP
LI: „wind resource assessment for wind farm project , Sout Korea“, Annex E, 2016
Thursday, June 07, 2018 86
Annual Energy Production:
synthetic wind speed distribution
Annual energy production: estimation with wind atlas data
Synthetic wind speed distributions (Weibull equation)
Wind speed distribution data (m/s)
can be described with a mathematical
equation. The most common
equation is the Weibull-curve.
hw(v) = Wind speed distribution (h/a or percentage)
k = shape parameter; It specifies the shape or from of a wind speed
k = 2 (Rayleigh distribution)
89
Annual energy production: estimation with wind atlas data
Source:, http://www.windatlas.ca/en/maps.php?field=E1&height=80&season=ANU
Weibull data examples
Typical k factors ranges
1.2 < k < 1.7 Mountains
1.8 < k < 2.5 Typical North America and Europe
2.5 < k < 3.0 Where topography increases wind speeds
Canadian wind atlas, latitude = 50.853, longitude = -57.007 at 50m height
Weibull shape Weibull scale
Period
parameter (k) parameter (A)
Annual 1.81 10.37 m/s
Winter (DJF) 1.94 11.76 m/s
Spring (MAM) 1.85 10.16 m/s
Summer (JJA) 1.96 8.87 m/s
Fall (SON) 1.94 10.65 m/s
90
Annual energy production: estimation with wind atlas data
Errors in Weibull wind speed distributions
A synthetic Weibull wind speed distribution approximates a measured wind
speed distribution. underestimation
It can over- or
underestimate
hw(v)
certain wind
speed classes.
overestimation
Recommendation: use measured wind speed data instead of synthetic data for
investment decisions because the measured data are more precise and the
uncertainty will be smaller
91
Exercise: k and A values of a Weibull wind speed distribution
Task answer the questions:
1. Which of the graphs has a k-factor of 15, 2 and 3.5?
2. What would be the A factor of the three graphs (they have all the same A factor)?
1,400
1,200
Frequency (h/a)
1,000
800
600
400
© RENAC
200
0
0 5 10 15 20 25
Wind speed (m/s)
92
Annual Energy Production:
unexpected losses
Power curve certification according to IEC 61400-12,
test report extract for Vestas V90
Source: BWE „Wind Energy Market 2010/2011“
Report No. Riso-I-2201-1, 23.6.2004
Guideline IEC 61400-12
Test laboratory Risö National Lab, Roskilde, DK
95
Annual energy production with power curves and
measured wind speed data
Exercise: How would the revenues change in case the wind farm A has more
losses due to bad power curve certification or bad quality of wind data.
Assumptions:
Case A-O: same data as in the previous exercise
Case A-I: 2% of additional losses
Case A-II: 4% of additional losses
Tasks:
Calculate the revenues of wind farm cases A-I and A-II.
Compare the revenues of wind farm B with wind farm cases
A-0, A-I and A-II
96
Exercise: Annual energy production with power curves and
measured wind speed data
Table for results: Compare annual energy production and revenues of wind farm
A (case 0, case I and case II) and wind farm B
Revenue
AEP without AEP including AEP during Revenues, differences
Wind farm Installed
losses during 1 losses during 20 years 90 $/MWh compared
case capacity
year 1 year operation Tariff to wind
farm B
MW MWh/a MWh/a MWh/a Mio. $ / 20a Mio. $ / 20a
A-0 33
A-I 33
A-II 33
B-0 34.5 reference
Thursday, June 07, 2018 97
Exercise: Annual energy production with power curves and
measured wind speed data
Exercise 4: full load hours and the capacity factor
Task: What are the full load hours and the capacity factor of turbine A and
turbine B taking into account the 7% wake effect and 98% technical
availability?
Installed wind farm
Wind farm case AEP including losses Capacity factor Full load hours
capacity
MW MWh/a % h/a
A-0 33
A-I 33
A-II 33
B-0 34.5
99
Wind Power Laboratory
Learning objectives
A participant who has met the objectives of the course will be able
to explain
how to calculate the power output of a wind turbine with voltage
and current data
the effect of rotor blade design, the pitch angle and the rotor blade
number on the wind turbine power output
the maximum power output of a wind turbine
the power coefficient and the tip speed ratio
yawing losses and wake effect losses and
measure a power curve of a laboratory wind turbine
Thursday, June 07, 2018 102
Calibrate wind blower
1. Change knob position of blower and measure wind
speed
2. Plot data
Blower Anemometer
103
Wind speed data of blower
Table for blower calibration Knob Measured
position wind speed (m/s)
1
2
3
4
5
6
7
8
9
10
104
Plot graph with measured wind speed data
16
15
14
13
12
11
wind speed (m/s)
10
9
8
7
6
5
4
3
2
1
0
0 1 2 3 4 5 6 7 8 9 10
Blower knob position
105
Wind Power Laboratory: Wind
Power Mini Grid and Power
Measurement
106
Volt / ampere meter
A = display
B = Selection of measurement F
range
C, D and E = Cable input
F = Direct current (DC) –
voltage measurement
G = Direct current (DC) – G
current measurement
107
Wind turbine without rotor blades
A = Rotor hub
B = Hole to insert rotor blades
C = Socket for cables to the minigrid
D = Screws to fix a rotor blade
108
Wind turbine with rotor blades
F
A
CF
A = Rotor blades; Note: wind
turbines rotate clockwise
B = Rotor hub with screws
C = Socket with cables from
wind turbine to the load
D = Screw driver B
E = Cover for wind turbine
operation to avoid that rotor C
blades can fly around in the
room (must be used as a
protection during operation)
F = Rosette to measure the D
pitch angle (printed on the
protection cover) E
109
Cabling for a mini-grid with wind turbine, load,
voltmeter and amperemeter
Put the load to position
number 5.
110
Wind Power Laboratory: Effect
of Blade Design on Wind
Turbine Power Output
111
Pitch angle measurement
A = Cover for protection and pitch angele
measurement
B = pitch angle measurement 90°
C = Magnets to connect cover with the ground
plate
45°
0°
112
Vane and working position of wind turbine blades
Real wind turbines operate the rotor blades close to 0°. To stop the wind
turbine the rotor blades are moved towards 90°.
Wind
90° 90°
45° 45°
0° 0°
Working position = 0°
Vane position= 90°
113
How to determine the 45° pitch angle
45°
90°
Wind Rotor blade
45°
0°
114
How to determine the 30° pitch angle
30°
90°
Wind Rotor blade
45°
0°
115
How to determine the 15° pitch angle
15°
90°
Wind Rotor blade
45°
0°
116
Effect of blade design on power output of a wind turbine
1. Change the blade design and measure the power output at
different wind speeds and at a pitch angle of 15°.
= flat
= curved
= optimised
2. Measure Voltage and Current
3. Calculate the power output (P = U x I )
4. Compare the power output of different rotor blade
designs.
117
Effect of blade design on power output of a wind turbine
1. Measure the power output of a three different blade designs at
the following wind speeds. The pitch angle is 15°.
Blade design wind speed Voltage Current Power
m/s V mA mW
low
flat 7 m/s
12 m/s
low
curved 7 m/s
12 m/s
low
optimised 7 m/s
12 /s
118
Effect of blade design on power output of a wind turbine
1. Which is the highest power output of the three different rotor blades?
Flat Curved Optimised
mW mW mW
at low
at 7 m/s mW mW mW
at 12 m/s mW mW mW
119
Wind Power Laboratory: Effect
of Rotor Blade Number on Wind
Turbine Power Output
120
Effect of rotor blade number on power output of a
wind turbine
1. Change the number of rotor blades and measure the power
output at different wind speeds and at a pitch angle of 15°.
Use curved rotor blades.
2 blades
3 blades
4 blades
2. Measure Voltage and Current.
3. Calculate the power output (P = U x I ).
4. Compare the power output of different rotor blade numbers.
121
Effect of rotor blade number on power output of a wind
turbine
1. Measure the power output of rotor blade numbers at the following
wind speeds. The pitch angle is 15°.
Blade
number wind speed Voltage Current Power
m/s V mA mW
low
2 blades 7 m/s
12 m/s
low
3 blades 7 m/s
12 m/s
low
4 blades 7 m/s
12 /s
122
Effect of rotor blade number on power output of a
wind turbine
1. Which is the highest power output of the three different rotor blades?
2 blades 3 blades 4 blades
at low mW mW mW
at 7 m/s mW mW mW
at 12 m/s mW mW mW
123
Wind Power Laboratory:
Theoretical Maximum and
measured Power Output
124
Maximal wind power density, Betz limit and power
curves of real wind turbines
1000
Wind power density of Efficiency losses
Power density [W / m2]
nR
Source: Robert Gasch, Jochen Twele, Wind Power Plants, Heidelberg (2012), S. 401
Rot. speed
85°
Pitch angle
65°
25°
0° wind speed
Idling Pitch Pitch variable Idling / Stop
const.
Vcut-in VR Vcut-out
149
Effective wind speed on the rotor blade
The next four slides explain the effective wind speed on the rotor blade. The
picture below shows the positions on the rotor blade that the four slides take
into account.
Slide 4 Slide 3 Slide 2 Slide 1
Fotos: Steil Kranarbeiten, Stefan Dürr; RENAC, A. Tiedemann
150
Effective wind speed on the rotor blade
The effective velocity v´ (i.e. the
wind speed indicated by a
hypothetical measuring device
400
v = wind speed [m/s]
cP = power coefficient Pitch
200
Real turbinecontrolled
PWPD, Turbine= cP * ½ * ρ * v3
0
0 2 4 6 8 10 12 14 16 18 20
Wind speed [m/s]
157
Wind Power Laboratory: Power
Coefficient Calculation
158
Power of wind in front of a wind turbine
Pw = ½ x ρ x A x v3
PW = power of wind [watt; joule per second]
ρ = air density [kg/m3; kilogram per cubic meter]
A = area = π * (½ D) ² [m2; square meter]
D = rotor diameter [m]
v = wind speed [m/s; meter per second]
Definition of power coefficient
The power coefficient (Cp) of a wind turbine is a measurement of how
efficiently the wind turbine converts the power in the wind into electric power
or
The power coefficient (Cp) is the ratio of power extracted by the wind turbine
(PT) to the total power contained in the wind resource in front of the wind
turbine PW).
Cp = PT/PW
160
Power coefficient curve and power curve
400 0.6
350
0.5
300
Power [kW]
Power coefficient cP
Source: http://www.mstudioblackboard.tu
150 m/s; due to noise protection
larger than 15 m/s not realized
Tip speed ratio is the most
important criteria for rotor blade
dimensioning of large and small
machines. Maximum value
determines the rotor blade loading.
171
The power coefficient (Cp) is not a constant, but a function
of the tip speed ratio λ and pitch angle β
Pitch angle, beta
Source: Lucas-Nuelle, Course number: SO2800-3D Version 1.0,
Power coefficent
Source: www.peaktech.de
2. Never point the laser at people or animals
3. Never look directly into the laser beam, since
it can cause serious eye damage.
4. Avoid the use of lasers at eye level.
5. Avoid possible reflections off reflective surfaces
such as glass and polished metal.
Thursday, June 07, 2018 176
How to use the meter.
1. Follow the safety instructions.
2. Press MEAS button to start the
measurement.
3. The display shows the actual
rotational speed
Source foto: www.peaktech.de
Phase Ownership /
Phase
Investment
Value Added
Administrative Services
O&M
Source: ENERTRAG Structured Finance
Construction
Financing, Structuring & Marketing
Development (Siting, Permitting, Procurement of Land Rights)
Phases of the Project Life Cycle
Thursday, June 07, 2018 197
Costs in Wind Power
Investment cost of wind turbine generator (WTG)
Onshore Wind Farm
Components of a wind
turbine and their share
of the overall turbine
cost. Cost of turn-key
ready wind turbines are
about 1,700 – 2,450 USD
/ kWi.
Source: IRENA (2012)
Thursday, June 07, 2018 198
Costs in Wind Power
Capital expenditures (CapEx) of wind power
Generator
Grid Connection Transformer
Power Converter
Turbine cost breakdown
Foundation Gearbox
17%
Rotor blade
Tower
Planning &
miscellaneous
9% Source: IRENA 2015
Wind Turbine Other
63%
Wind Turbine Planning & miscellaneous Foundation Grid Connection
Thursday, June 07, 2018 201
Costs in Wind Power
Break down of investment cost in wind power
Thursday, June 07, 2018 202
Costs in Wind Power
Cost of debt for a euro area onshore project
Costs of debt
change daily
Source: New Energy Finance/Bloomberg; Data as of 15 January 2011
and together
with it does
the project
value
Thursday, June 07, 2018 203
Costs in Wind Power
Costs of capital or yield expectations of investors, Euro-Area2017
Indicative figures illustrate the rising yield expectation for increasing risk
Uncertainty Yield Expectation
15% -12% USD\EUR
Wind Risk P50 [%] Equity Debt
Output in MWh
ECF = Equity
Cash flow
Probability of Exceedance
that is exceeded with the 70%
60%
following probability taking
50%
into account long term
40%
average production & its 30%
overall uncertainty. 20%
Probability of exceedance: 10%
50% 0%
21.000 26.000 31.000 36.000
21000 26000 31000 36000
75% Wind Farm Energy Yield [MWh/a]
Net AEP ( MWh/a)
90%
Thursday, June 07, 2018 218
Uncertainty analysis of AEP (wind speed and energy)
The methodology to determine all uncertainties of the project influence the
annual energy production is as followed?
A) split the uncertainty evaluation into a wind speed and energy related
field; Important: wind speed related uncertainties in m/s have to be
translated into energy related uncertainties in MWh/a
B) In case uncertainties are stochastically in depended: Calculate the root of
the squared sum
-!#! . -1 0 1 -2 0 1 -3 0 1 ⋯ 1 - 5 0
With:
Utotal = total uncertainty in absolute values (MWh/a) or in % of AEP
U1, to UN = single uncertainties
Thursday, June 07, 2018 220
Sonic / light detection and ranging (SODAR/LIDAR)
Device emits sound up and Measuring towers Measurements
measures the sound/light that is with height up to up to 200 m
110
105
100
95
90
85
80
1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009
Wind speed related uncertainties
Exampel: Measurement and data processing uncertainties
1. Measurement uncertainty (cup anemometer, wind vane and mounting)
Deviations of the mast setup from the recommended practice of the IEC
61400-12 standard
Influences to the measurements from the mast itself, from the booms and
mounting clamps.
Quality, calibration and configuration of measurement system equipment
2. Data processing (data integrity, data analysis and long term correlation)
Data integrity (quality of technical information and documentation)
Data analysis (duration of the measurement campaign, data coverage,
measurement consistency, data synthesis)
Long term correlation (representatively of the reference data, the correlation
between site data and reference data)
Measurement and data processing Uncertainty Uncertainty
uncertainties (% of m/s) (% AEP)
Range 4–8% 6 – 12%
Example data from wind study Korea 5.0 % 7.9 %
Thursday, June 07, 2018 224
Energy related uncertainties
Power curve uncertainties: Uncertainties of power curve measurement
(deviation from IEC 61400-12 standard procedure)
Power curve uncertainty Value (%)
Range 5 – 12%
Example data from wind study Korea 6.2 %**)
Wake effect losses: The wind speed behind a wind turbine is reduced and
the wind has turbulences (wake effect). The wind turbine model has
limitations to take this into account.
Wake effect uncertainty Value (%)
Range 2–6%
Example data from wind study Korea 3.8 %**)
Thursday, June 07, 2018 225
Energy related uncertainties
Flow modelling
Transferring the wind speed data from the meteorological mast to the
wind turbine locations
Using the model specific horizontal and vertical wind speed
extrapolations.
uncertainties resulting from the surface roughness description, orography
(topographical description) as well as general limitations of the model.
Flow modelling Uncertainty (%)
Range 6 – 10 %
Example data from wind study Korea 7.8 %
Thursday, June 07, 2018 226
Exercise: Uncertainty analysis of annual energy production
Task: caluclate the total uncertainty for the example 1, 2 and 3
with the follwing data
With:
-!#! . -10 1 -20 1 -30 1 ⋯ 1 -5 0 Utotal = total uncertainty
U1, to UN = single uncertainties
Uncertainties in % related to annual energy
AEP change due to uncertainty of production (AEPP50)
Case 1 (%) Case 2 (%) Case 3 (%)
measurement and data processing 6.0 8.0 10.0
prediction horizon (1 year) 3.0 4.0 6.0
modelling 5.0 7.0 9.0
power curve 5.0 6.0 9.0
losses (wake losses) 2.5 3.5 5.0
Total uncertainty
Thursday, June 07, 2018 227
Uncertainty analysis of annual energy production,
Excel tool, table “1b.P.Case”
Thursday, June 07, 2018 229
P50, P75 and P90 depend on overall uncertainty
P9015% = 110 GWh/a
P9012% = 120 GWh/a
Source: Enertrag, 2010a
Exercise: Uncertainty analysis of annual energy production
Task: Calculate annual energy production P75 and the P95 of the wind farm A-0 and
B-0 (see exercise in previous chapter for P50) for different uncertainties
Assume Net-AEP-P50 of wind farm A-0 and B-0 as given below
Assume a total uncertainty of annual energy production of
10.1%, 13.3% and 18.0% (relative standard deviation, rSD)
Use the Excel tool (previous slide) to create the probability
density equation and to calculate the P-cases P75 and the P95
P-Case Annual energy production P-Case Annual energy production
of wind farm case A-0 (GWh) of wind farm case B-0 (GWh)
10.1% 13.3% 18.0% 10.1% 13.3% 18.0%
P50 115,982 115,982 115,982 P50 114,250 114,250 114,250
P75 P75
P95 P95
Source: RENAC, 2018
Thursday, June 07, 2018 231
Exercise: Uncertainty analysis of annual energy production
Task: Calculate the revenues of the wind farm A-0 and wind farm B-0 for
different uncertainties
Assume the uncertainties and the results for annual energy production at P50,
P75 and P90 of the previous exercise (Assume an tariff of 90$ / MWh, 100
turbines and 20 years of operation)
P-Case Wind farm A-0, revenues P-Case Wind farm B-0, revenues
during 20 years (Mio. $) during 20 years (Mio. $)
9.2% 13.3% 18.0% 9.2% 13.3% 18.0%
P50 P50
P75 P75
P95 P95
Source: RENAC, 2018
Thursday, June 07, 2018 233
Cash Flow Valuation
Financial valuation of annualized cash flows (in 9 steps)
Annualized (constant) cash flows are assumed to simplify cash flow modelling
Note: the present value (PV) at a constant discount rate of regular payments of a
constant cash flow(cCF) results by multiplying the cash flow times annuity factor.
1. PVcCF =cCF *AF, with AF =((1-(1+r)-t)/r, and AF for debt(AFd) =((1-(1+rd)-td)/rd
2. Annual Energy Production in P50= AEPP50= Quantity(Q) over project life time(t)
3. AEP-risk =standard deviation of AEP relative to AEPP50 =SDAEP/AEPP50 =rSDAEP
4. Tariff =Price(P), variable Costs(vC), fixed Costs(fC), rt=tax rate, I=CapEx+Devl
5. Capital-conditions: capital rate(rd), tenor(td), P-Case and coverage ratio (DSCR)
…see next slide for steps 6. to 9. (for a risk-sensitive reduction of revenue)
Source: RENAC, 2016
Thursday, June 07, 2018 235
Cash Flow Valuation
Financial valuation of annualized cash flows (in 9 steps)
Annualized (constant) cash flows are assumed to simplify cash flow modelling
Note: the present value (PV) at a constant discount rate of regular payments of a
constant cash flow(cCF) results by multiplying the cash flow times annuity factor.
6. P-Case is the probability to exceed a given case or scenario i.e. for debt = P-Cased
7. The P-Case is an exceedance-probability and equals 1 less short fall probability
8. The term Ninv(Pexceed)=Ninv(1-Pshortfall) and is equal to (AEPPxx-AEPP50)/SDAEP
9. Safety-reduction of AEPP50 for debt is given by: Ninv(1-P.cased)*rSDAEP
…see next slide for the formalization of the 9 steps described above
Source: RENAC, 2016
Thursday, June 07, 2018 236
Debt Cash Flow Valuation
Formalizing and simplifying debtconditions and its volume
A single-line equation for a rough first “guesstimation” (for debt volume):
AF=Annuity Factor, rd=debt rate, td= debt tenor, DSCR=debt service coverage ratio, I=Investment, rt=tax rate,
D=I/t= linear depreciation, t= project life time, P=price=tariff, vC=variable costs, fC=fixed costs, Q=AEPP50,
rSDAEP= Standard Deviation relative to AEP, N(1-P.case)=inverse normal distributed, P.cased=debt probability
1. Debt: D =DS*AFd with AFd =((1-(1+rd)-td)/rd
2. Debt service: DS =(FCFd)/DSCR with DSCR > 1
3. Free Cash to Firm: FCFd =CFd -txd with txd=(CFd -D)*rt => CFd*(1-rt)+D*rt
4. CF before tax: CFd =(Qd*(P-vC)-fC) =(Qd*P -Qd*vC –fC)
5. reduced Quantity: Qd =Q*(1+S) with Q=AEPP50 and S=Safety reduction
6. Saftey-reductionAEP: S =rSD*N(1-P.cased) with Safety-reduction S<0
D=((Q*(1+rSD*N(1-P.cased))*(P-vC)-fC)*(1-rt)+D*rt)/DCSR*((1-(1+rd)-td)/rd)
Source: RENAC, 2016
Thursday, June 07, 2018 237
Equity Cash Flow Valuation: FCF x AFe –DS x AFe
Formalizing and simplifying equity conditions and its volume
Using the simple Annuity approach to evaluate non-uniforn equity cash flow (ECF)
REMEMBER: Cash Flows of the different types of Capital:
ENTITY: Entity CF= FCF (uniform)
DEBT: Debt CF= DS (uniform)
EQUITY: Equity CF= ECF (non-uniform => L-shaped, compare CF-Model)
WITH: FCF –DS= ECF
GENERAL: Capital Value= Capital-CF at Capital Cost over Capital lifetime =CF x AF
ENTITY: Entity Value= FCF at Entity Cost (rev) over Entity lifetime (tev) =FCF x AFev
DEBT: Debt Value= DS at Debt Cost (rd) over Debt lifetime (td) =DS x AFd
EQUITY: Equity Value= ECF at Equity Cost (re) over Equity lifetime (te) non-uniform!
REPLACEMENT of non-uniform ECF by uniform FCF and uniform DS (maintaining equity discounting)
ECF= FCF –DS=> EQUITY= (FCF –DS) at Equity Cost (re) over Equity lifetime = FCF x AFe –DS x AFe
EQUITY: = +FCF at Equity Cost (re) over Equity lifetime (+FCF x AFe )
–DS at Equity Cost (re) over Equity lifetime (–DS x AFe )
Source: RENAC, 2016
Thursday, June 07, 2018 238
Cash Flow Valuation
Formulas for Entity Value(EV), Debt(D)- and Equity(E)-Volume
The same formula adjusted for entity-, debt-, equity-value in an overiew
EV= ((Q*(1+rSD*N(1-Probev))*(P-vC)-fC)*(1-rt)+I/t*rt)/DCSR*((1-(1+rev)-t)/rev)
D = ((Q*(1+rSD*N(1-P.case))*(P-vC)-fC)*(1-rt)+I/t*rt)/DCSR*((1-(1+rd)-td)/rd)
E = ((Q*(1+rSD*N(1-Probe))*(P-vC)-fC)*(1-rt)+I/t*rt)/DCSR*((1-(1+re)-te)/re)
-((Q*(1+rSD*N(1-Probd))*(P-vC)-fC)*(1-rt)+I/t*rt)/DCSR*((1-(1+re)-te)/re
Q=P50-AEP, SD=AEP-Risk, rSD=SD/AEP P.case=banking probability, P=tariff, vC=variable costs, fC=fixed costs,
rt=tax rate, rd=debt rate, td=tenor of debt, I=CapEx, t= project life time, DSCR= debt service coverage ratio
Lookup Table: Nr P-CASE P95 P90 P85 P80 P75 P70 P65 P60 P55 P50
Row 4. schows 1. Prob.ShortFall 5% 10% 15% 20% 25% 30% 35% 40% 45% 50%
2. Prob. Exceedance 95% 90% 85% 80% 75% 70% 65% 60% 55% 50%
An example for
3. N(1-Prob. Exc.) -1,64 -1,28 -1,04 -0,84 -0,67 -0,52 -0,39 -0,25 -0,13 0,00
rSD = 15 % 4. 3. x 15% (=rSD) -0,25 -0,19 -0,16 -0,13 -0,10 -0,08 -0,06 -0,04 -0,02 0,00
NOTE: In the P50-Case, the term N(1-Probev) is =0 therefore the term (1+SD*N(1-Probev)) is =1 !
Source: RENAC, 2016
Thursday, June 07, 2018 239
Cash Flow Valuation, Excel tool, table “CF-Valuation”
Form to calculate INPUTS Project A-0 Project 1b Project 1c Project B-0 Project 2b Project 2c
CAPEX 0 0 0 0
volume of: Balance of Plant (BOP) 0 0 0 0 0
Developlment (Dvlm) 0 0 0 0 0
• debt (D), Invest/WTG 0 0 0 0 0 0
• equity ( E),
Nr. of WTG 0 0 0 0 0
• entity value (EV) and MW/WTG 0.00 0.00 0.00 0.00
• project margin (M) Net AEP/WTG 0 0 0 0
Uncertainty 0.0% 0.0% 0.0%
Tariff USD/MWh 0 0 0 0 0
Var. Costs USD/MWh 0 0 0 0 0
Fix.Costs/WTG USD p.a. 0 0 0 0 0
Tax Rate % 0% 0% 0% 0% 0%
DSCR 0 0 0 0 0
Tenor debt 0 0 0 0 0
P.case 0% 0% 0% 0% 0%
Debt rate 0.00% 0.00% 0.00% 0.00% 0.00%
Project Life time 0 0 0 0 0
Equity rate 0.00% 0.00% 0.00% 0.00% 0.00%
Entity rate (COC) 0.00% 0.00% 0.00% 0.00% 0.00%
Source: RENAC, 2016
Thursday, June 07, 2018 240
Case study exercise of wind power valuation
Case study: assessing a project’s financial viability
Answer the following questions (group-wise):
Assume yourself in the position of a bank’s, shareholder’s or developer’s executive, who is
responsible for an investment of up to 100 M$ into a large wind power project and ask yourself
which risks can threat your success and payback of the project. Perform the following steps:
1. Make a rough checklist in bullet points
2. Make suggestions what actions will comfort your risk position sufficiently
3. Try to quantify roughly the expected return and the main risks (=question your inputs).
Using the simplifying formulas requires to explain why an application makes sense or is
maybe misleading. So argue why or where the simplifying approach makes sense or not.
4. Give a financial explanation, if, when, under which conditions and how much funds (debt
and equity) can be invested into the project (this requires the main calculations).
5. Discuss the investment offers of the class: try to identify the key drivers of the highest and
lowest offer and potential risk of the highest offer.
Source: RENAC, 2016
Thursday, June 07, 2018 241
Case Study: annualized financial valuation
Case study (simplified/annualized): project information
Calculate project values for different turbines
1. Project A-0: 10WTGs, Q=11,598 MWh/WTG, rSD=10,1\13.3\18%, P=78 $/MWh,
vC=12$/MWh, fC=0.06 M$/WTG , rt=20%, Pd=95%, rd=4%, td=15, DSCRd= 1.25, Pe=50%,
re=16%, te=20, DSCRe= 1.0, CapEx+BoP+Dvlm=I=5.3= 4.1+0.9+0.3 M$/WTG, rev=8.26%
2. Project B-0: 10WTGs, Q=11,425 MWh/WTG, rSD=10,1\13.3\18%, P=78 $/MWh,
vC=12$/MWh, fC=0.06 M$/WTG , rt=20%, Pd=95%, rd=4%, td=15, DSCRd= 1.25, Pe=50%,
re=16%, te=20, DSCRe= 1.0, CapEx+BoP+Dvlm=I= 5.5= 4.3+0.9+0.3 M$/WTG, rev=8.26%
Note: Changing the turbine usually changes the AEP, the AEP-uncertainty, the turbine price
(CAPEX) and regularly the O&M-cost (here same for simplicity).
Source: RENAC, 2016
Thursday, June 07, 2018 242
Case Study: valuation exercise
Case study, project 1: debt, equity, project value and margin
1. Project A-0: 10WTGs, Q=11,598 MWh/WTG, rSD=10,1\13.3\18%, P=78 $/MWh,
vC=12$/MWh, fC=0.06 M$/WTG , rt=20%, Pd=95%, rd=4%, td=15, DSCRd= 1.25, Pe=50%,
re=16%, te=20, DSCRe= 1.0, CapEx+BoP+Dvlm=I=5.3= 4.1+0.9+0.3 M$/WTG, rev=8.26%
Capital Volumes Wind farm A-0, revenues during 20 years (Mio. $)
with I = 53 M US$
10.1% 13.3% 18.0%
D
E
EV
M (D+E-I)
M (EV-I)
Source: RENAC, 2016
Note: further
Thursday, June 07,results
2018 are distributed at the end of workshop 243
Case Study: valuation exercise
Case study, project 1: debt, equity, project value and margin
2. Project B-0: 10WTGs, Q=11,425 MWh/WTG, rSD=10,1\13.3\18%, P=78 $/MWh,
vC=12$/MWh, fC=0.06 M$/WTG , rt=20%, Pd=95%, rd=4%, td=15, DSCRd= 1.25, Pe=50%,
re=16%, te=20, DSCRe= 1.0, CapEx+BoP+Dvlm=I=5.5= 4.3+0.9+0.3 M$/WTG, rev=8.26%
Capital Volumes Wind farm A-0, revenues during 20 years (Mio. $)
with I = 55 M US$
10.1% 13.3% 18.0%
D
E
EV
M (D+E-I)
M (EV-I)
Source: RENAC, 2016
Note: further
Thursday, June 07,results
2018 are distributed at the end of workshop 245
Project valuation checklist
Thursday, June 07, 2018
Project valuation checklist
Selected critical questions to ask I / II
NOTE: Questions intend to question the assumptions of the financial valuation
1. Are EPC, turbine supply, grid connection and O&M signed, binding & valid?
2. Is there an legally binding EPC and a turbine supply contract?
3. Are warranties in the EPC, turbine supply and O&M sufficient?
4. Are construction, delay and other risk mitigated or insured and are
liquidated damages sufficient in case major risks will occur?
5. Are at least two independent wind studies available and your own one?
6. What is the basis for the tariff payment (governmental law or other?) and
which risks can lead to reduced prices or off taking of the produced energy?
Source: RENAC, 2016
Thursday, June 07, 2018 250
Project valuation checklist
Selected critical questions to ask II / II
NOTE: Questions intend to question the assumptions of the financial valuation
7. Are all construction permits and easements for each plot of land complete?
8. Are wind studies counter-checked from independent experts to verify it?
9. Conduct a post-mortem analysis (think about things that can go wrong)
10. What are possible reasons for delay of commissioning and operation?
11. What are the project’s very individual characteristics and which are critical?
12. What are two major “pros and cons" in a very short SWOT*- analysis?
*SWOT: strength, weakness, opportunities, threats
Source: RENAC, 2016
Thursday, June 07, 2018 251
Thank you
Albrecht Tiedemann
Felix Hulsch
Renewables Academy (RENAC) AG
Schönhauser Allee 10-11
D-10119 Berlin
Tel: +49 30 52 689 58-71
Fax: +49 30 52 689 58-99
www. renac.de
[email protected]
Thursday, June 07, 2018 252
Backup slides
Thursday, June 07, 2018 253
Levelized costs of wind energy
Thursday, June 07, 2018
LCOE in Wind Power
Content: Revenues and costs in wind power: Part II
1. Levelized costs of energy (LCOE): Definition
2. Pros and cons of Wind Power
3. LCOE of wind power in different regions
4. Sensitivities
Source: RENAC, 2016
Thursday, June 07, 2018 255
LCOE in Wind Power
The next slides answer the following practical questions:
1. What is the practical use for LCOE?
2. How to compare costs of generation even across technologies?
3. What are typical sensitivities?
Source: RENAC, 2016
Thursday, June 07, 2018 256
LCOE in Wind Power
1) Levelized Cost Of Electricity (LCOE)
LCOE is the effective cost or price per unit of electricity at which it has to be sold to cover
really all costs of its generation: development, CapEx, OpEx, CoC.
Approach: Present value of all costs divided by the present value of net power production.
The discount rate (i) takes the cost of capital (debt and equity) into account.
Formula has the input parameters:
LCOE: Levelized Cost of Electricity Generation in $/kWh (or $/MWh)
I 0: Investment costs: CapEx including development costs
At: Annual total operating costs including taxes in $ in each year t
Qel: Quantity of electricity generated each year (AEP) in kWh p.a. or (MWh p.a.)
i: Interest rate of capital including cost of debt and equity in % p.a.
n: Useful economic life in years
t: Current year during the useful life (1, 2, …n)
Source: RENAC, 2016
Thursday, June 07, 2018 257
LCOE in Wind Power
Pros and Cons of LCOE
Analytical tool allows comparing different technologies with
different scales of operation, investments or life time
PROS
One simple easy to understand monetary value
Break even benchmark, including all types of costs
Strongly depends on underlying assumptions i.e. interest rate
CONS
Assumptions (interest rate) difficult to derive from market
Interpretation needs understanding of present value concept
Only a cost measure, no accounting for revenues nor margin
Source: RENAC, 2016
Thursday, June 07, 2018 258
LCOE in Wind Power
Levelized costs of energy (LCOE) of wind power worldwide
Levelized cost of energy (LCOE) of wind energy is a function of wind speed
(full load hours) and capital and investment costs.
LCOE shows prices from 40 USD/MWh to 160 USD/MWh often with wide
spreads of 80 USD/MWh per region except China and India
Source: IRENA
Thursday, June 07, 2018 259
LCOE in Wind Power
Levelized costs of energy (LCOE) of wind power worldwide
Source: IRENA
Thursday, June 07, 2018 260
LCOE of Renewable Energy technologies and conventional
power plants in Germany, 2013
ELECTRICITY RENEWABLE ENERGY TECHNOLOGIES”, STUDY, NOVEMBER 2013
Source: FRAUNHOFER INSTITUT FOR SOLAR ENERGY SYSTEMS ISE: “LEVELIZED COST OF
250
200
LCOE € /MWh
150
100
50
0
GHI = Global horizontal irradiance [kWh/(m²a)], FLH = Full load hours [h/a]
261
External cost theory
Economic externalities represent the impact of production and consumption on
other entities other than those entities actual producing and consuming, which are
not reflected in prices
Externalities taken into account in an Ecofys-study (from 2014) for the European
Union are:
Impacts on human health
Effects on ecosystems and biodiversity
Resource depletion, primarily water, metals and fuels but also including crops,
buildings and other assets
Ecofys assessed external costs using the External-E tool. This calculation tool
integrates life cycle assessment (LCA), actual power production data and
monetisation methodologies to estimate and value total environmental impacts
262
External costs of energy - monetary values for climate
change for (EU28 average, in €2012/MWhe)
The blue bars indicate the
range of external costs found in the
sensitivity analysis. The green line
indicates the results for the
central assumption of 50
€2012/tCO2e.
263
External costs of energy - monetary values for climate
change for (EU28 average, in €2012/MWhe)
264
LCOE + external costs
Note: exact costs depend on local circumstances, LCOE for Germany and
external cost data for Europe
200 Min+Min, €/MWh Max+Max, €/MWh
150
100
50
0
Wind PV utility, PV small, Gas CC, Lignite, 6600 Wind Hard coal,
onshore, 1800-2000 1800-2000 3000- 4000 - 7600 FLH offshore, 5500 - 6500
1300 - 2700 GHI GHI FLH 2800 - 4000 FLH
FLH FLH
265
LCOE in Wind Power
LCOE sensitivity against full load hour and cost of capital
LCOE of wind energy in €Cents/kWh as a function of full load hours (x-axis)
at three different discount rates (of 5%, 7.5%, 10%) . Web links: [1]
with: