PERT - CPM PPT
PERT - CPM PPT
PERT - CPM
PERT CPM
• Program Evaluation and Review • Critical Path Method
Technique
• Used when dealing with projects where • Scheduling and cost control for well-
activity durations are uncertain. defined tasks
• Uses three estimates (Optimistic, • Uses a single fixed time estimate per
Pessimistic, and Most Likely) task
• More flexible for uncertain durations • Less flexible, suited for structured
projects
• Ideal for projects with high variability • Ideal for projects with well-defined,
and research-based tasks sequential activities
INTEGRATIONS
PERT-CPM
The two methods are often integrated for
comprehensive project analysis.
Activity
A task or set of tasks required to complete a project. It consumes resources and time
Event (Node)
A specific point in time signifying the start or completion of one or more activities
Network Diagram
A graphical representation of a project’s activities and their sequence
Predecessor Activity
An activity that must be completed before another activity can start
Successor Activity
An activity that cannot start until another activity is completed
PERT-Specific Terminologies
Drag/Slack Time
The amount of time an activity can be delayed without affecting the overall project duration
CPM-Specific Terminologies
Critical Path
The longest path through the network diagram, determining the shortest possible project
duration. It has zero slack
Total Float
The total amount of time an activity can be delayed without affecting the project’s completion
date
TF = LS – ES
TF = LF – EF
Free Float
The amount of time an activity can be delayed without affecting the start of any successor
activities.
FF = ES of next activity – ES of current activity – Duration of current
FF = EF – ES of the next activity
PERT applies an
“Activity-on-Arrow”
network diagram,
CPM applies an
“Activity-on-Node”
network diagram.
Activity-on-Arrow
A B C D means the network diagram
S 1 2 3 E depicts each milestone event as
a node and shows the activity
information on the arrows
joining each milestone event.
Activity-on-Node
3 3 3 1 shows the activity information as
A B C D E a node, and links one activity to
the next, rather than linking one
milestone to the next.
PROCEED TO EXCEL
MSTCONNECT 2025 mstconnectph
Breakslides
Let’s Take a Break 15 Minutes!
MSTCONNECT 2025 @mstconnectph
CONTACT US