Assignment ID 3423427
Assignment ID 3423427
Students Name
Department of Study
Course Number
Professor Name
Date
2
Question 1
a. cost variance
= $20,000 - $20,000
= $0
b. schedule variance
= $20,000 - $23,000
= -$3,000
Cost performance index (CPI) = Earned Value (EV)/ Actual Cost (AC)
= $20,000/$20,000
= 1.0
= 10%
Schedule performance index (SPI) = Earned Value (EV)/ Planned Value (PV)
= $20,000/$23,000
= 0.8696
= 86.96%
Question 2
a. Cost Variance (CV) is $0: The project is within budget; costs are according to plan.
b. Schedule Variance (SV) is -$3,000: The projectile delay as it only generated $ 3,000 less
c. Cost Performance Index (CPI) is 1.0: The project is meeting the cost expectations.
d. Schedule Performance Index (SPI) is approximately 0.87: The pace of the project has
In summary, the project is within budget although it is past schedule. The team needs to work on
Question 3
EAC = BAC/CPI
= $120,000/1
= $120,000
4
Cost-wise, the project is proceeding according to plan because the EAC is in line with the initial
budget. As of right now, there are neither savings nor cost overruns, and the project is on
Question 4
Using the Schedule Performance Index (SPI), you can calculate how long the project will take to
1−SPI
= Estimated Time to Completion (ETC) = ∗Original Duration
SPI
Assuming that the project was initially intended to last a year and that the SPI is roughly 0.87,
1−0.87
(ETC) = ∗Original Duration
0.87
0.13
= ∗1
0.87
= 0.149 years
It is projected that the project will take 0.149 years, or 1.79 months, to complete. Thus, if the
current schedule performance continues, the project should be completed in about 1.79 months.
5
Question 5
The Planned Value (PV), Earned Value (EV), and Actual Cost (AC) lines in the sketch closely
correspond, suggesting a favorable financial outcome for the project. The PV line shows the
projected cost over time, while the EV points, which show the actual value realized in
accordance with the project plan, follow the PV line closely. The AC line, which represents the
This sketch illustrates the project's budget, which indicates that actual financial outlays are
consistent with the projected costs. The intimate connection between PV, EV, and AC points to
efficient cost control. It is difficult to tell if a project is ahead of schedule, behind schedule, or
not without knowledge about the project timeline. However, the near alignment of these lines
6
suggests a sound financial performance; therefore, keeping an eye on this trend will be essential