Standard General Conditions of the Construction Contract
Standard General Conditions of the Construction Contract
respect to its use or modification. This document should be adapted to the particular circumstances of
the contemplated Project and the controlling Laws and Regulations.
Prepared By
Endorsed By
The copyright for this EJCDC document is owned jointly by the three sponsoring organizations listed
above. The National Society of Professional Engineers is the Copyright Administrator for the EJCDC
documents; please direct all inquiries regarding EJCDC copyrights to NSPE.
NOTE: EJCDC publications may be purchased at www.ejcdc.org, or from any of the sponsoring
organizations above.
EJCDC® C-700, Standard General Conditions of the Construction Contract (2018), is the foundation
document for the EJCDC Construction Series. The General Conditions define the basic rights,
responsibilities, risk allocations, and contractual relationship of the Owner and Contractor, and establish
how the Contract is to be administered.
EJCDC documents are intended to be used as a system and changes in one EJCDC document may require
a corresponding change in other documents. Other EJCDC documents may also serve as a reference to
provide insight or guidance for the preparation of this document.
These General Conditions have been prepared for use with either EJCDC® C-520, Agreement Between
Owner and Contractor for Construction Contract (Stipulated Price), or EJCDC® C-525, Agreement
Between Owner and Contractor for Construction Contract (Cost-Plus-Fee) (2018 Editions). The
provisions of the General Conditions and the Agreement are interrelated, and a change in one may
necessitate a change in the other.
To prepare supplementary conditions that are coordinated with the General Conditions, use
EJCDC® C-800, Supplementary Conditions of the Construction Contract (2018).
The full EJCDC Construction series of documents is discussed in the EJCDC® C-001, Commentary on the
2018 EJCDC Construction Documents (2018).
All parties involved in a construction project benefit significantly from a standardized approach in the
location of subject matter throughout the documents. Experience confirms the danger of addressing the
same subject matter in more than one location; doing so frequently leads to confusion and
unanticipated legal consequences. Careful attention should be given to the guidance provided in
EJCDC® N-122/AIA® A521, Uniform Location of Subject Matter (2012 Edition) when preparing
documents. EJCDC® N-122/AIA® A521 is available at no charge from the EJCDC website, www.ejcdc.org,
and from the websites of EJCDC’s sponsoring organizations.
If CSI MasterFormat™ is used for organizing the Project Manual, consult CSI MasterFormat™ for the
appropriate document number (e.g., under 00 11 00, Advertisements and Invitations), and accordingly
number the document and its pages.
Remove these Guidelines for Use. Some users may also prefer to remove the two cover pages.
Although it is permissible to revise the Standard EJCDC Text of C-700 (the content beginning at page 1
and continuing to the end), it is common practice to leave the Standard EJCDC Text of C-700 intact and
unaltered, with modifications and supplementation of C-700’s provisions set forth in EJCDC® C-800,
Supplementary Conditions of the Construction Contract (2018). If the Standard Text itself is revised, the
EJCDC® C-700, Standard General Conditions of the Construction Contract.
©
Copyright 2018 National Society of Professional Engineers, American Council of Engineering Companies,
and American Society of Civil Engineers. All rights reserved.
Guidelines Page 1 of 2
user must comply with the terms of the License Agreement, Paragraph 4.0, Document-Specific
Provisions, concerning the tracking or highlighting of revisions. The following is a summary of the
relevant License Agreement provisions:
1. The term “Standard EJCDC Text” for C-700 refers to all text prepared by EJCDC in the main body
of the document. Document covers, logos, footers, instructions, or copyright notices are not
Standard EJCDC Text for this purpose.
2. During the drafting or negotiating process for C-700, it is important that the two contracting
parties are both aware of any changes that have been made to the Standard EJCDC Text. Thus, if
a draft or version of C-700 purports to be or appears to be an EJCDC document, the user must
plainly show all changes to the Standard EJCDC Text, using “Track Changes” (redline/strikeout),
highlighting, or other means of clearly indicating additions and deletions.
3. If C-700 has been revised or altered and is subsequently presented to third parties (such as
potential bidders, grant agencies, lenders, or sureties) as an EJCDC document, then the changes
to the Standard EJCDC Text must be shown, or the third parties must receive access to a version
that shows the changes.
4. Once the document is ready to be finalized (and if applicable executed by the contracting
parties), it is no longer necessary to continue to show changes to the Standard EJCDC Text. The
user may produce a final version of the document in a format in which all changes are accepted,
and the document at that point does not need to include any “Track Changes,”
redline/strikeout, highlighting, or other indication of additions and deletions to the Standard
EJCDC Text.
This document is subject to the terms and conditions of the License Agreement, 2018 EJCDC®
Construction Series Documents. A copy of the License Agreement was furnished at the time of purchase
of this document, and is available for review at www.ejcdc.org and the websites of EJCDC’s sponsoring
organizations.
TABLE OF CONTENTS
Page
Article 1—Definitions and Terminology........................................................................................................ 1
1.01 Defined Terms ............................................................................................................................... 1
1.02 Terminology .................................................................................................................................. 6
Article 2—Preliminary Matters ..................................................................................................................... 7
2.01 Delivery of Performance and Payment Bonds; Evidence of Insurance......................................... 7
2.02 Copies of Documents .................................................................................................................... 7
2.03 Before Starting Construction ........................................................................................................ 8
2.04 Preconstruction Conference; Designation of Authorized Representatives .................................. 8
2.05 Acceptance of Schedules .............................................................................................................. 8
2.06 Electronic Transmittals ................................................................................................................. 9
Article 3—Contract Documents: Intent, Requirements, Reuse .................................................................... 9
3.01 Intent............................................................................................................................................. 9
3.02 Reference Standards ................................................................................................................... 10
3.03 Reporting and Resolving Discrepancies ...................................................................................... 10
3.04 Requirements of the Contract Documents ................................................................................. 11
3.05 Reuse of Documents ................................................................................................................... 11
Article 4—Commencement and Progress of the Work .............................................................................. 12
4.01 Commencement of Contract Times; Notice to Proceed ............................................................. 12
4.02 Starting the Work ........................................................................................................................ 12
4.03 Reference Points ......................................................................................................................... 12
4.04 Progress Schedule ....................................................................................................................... 12
4.05 Delays in Contractor’s Progress .................................................................................................. 12
Article 5—Site; Subsurface and Physical Conditions; Hazardous Environmental Conditions .................... 14
5.01 Availability of Lands .................................................................................................................... 14
5.02 Use of Site and Other Areas ........................................................................................................ 14
5.03 Subsurface and Physical Conditions............................................................................................ 15
5.04 Differing Subsurface or Physical Conditions ............................................................................... 16
3.01 Intent
A. The Contract Documents are complementary; what is required by one Contract Document is
as binding as if required by all.
B. It is the intent of the Contract Documents to describe a functionally complete Project (or
part thereof) to be constructed in accordance with the Contract Documents.
C. Unless otherwise stated in the Contract Documents, if there is a discrepancy between the
electronic versions of the Contract Documents (including any printed copies derived from
such electronic versions) and the printed record version, the printed record version will
govern.
D. The Contract supersedes prior negotiations, representations, and agreements, whether
written or oral.
E. Engineer will issue clarifications and interpretations of the Contract Documents as provided
herein.
F. Any provision or part of the Contract Documents held to be void or unenforceable under
any Law or Regulation will be deemed stricken, and all remaining provisions will continue to
be valid and binding upon Owner and Contractor, which agree that the Contract Documents
will be reformed to replace such stricken provision or part thereof with a valid and
enforceable provision that comes as close as possible to expressing the intention of the
stricken provision.
G. Nothing in the Contract Documents creates:
1. any contractual relationship between Owner or Engineer and any Subcontractor,
Supplier, or other individual or entity performing or furnishing any of the Work, for the
benefit of such Subcontractor, Supplier, or other individual or entity; or
2. any obligation on the part of Owner or Engineer to pay or to see to the payment of any
money due any such Subcontractor, Supplier, or other individual or entity, except as
may otherwise be required by Laws and Regulations.
ARTICLE 12—CLAIMS
12.01 Claims
A. Claims Process: The following disputes between Owner and Contractor are subject to the
Claims process set forth in this article:
1. Appeals by Owner or Contractor of Engineer’s decisions regarding Change Proposals;
2. Owner demands for adjustments in the Contract Price or Contract Times, or other relief
under the Contract Documents;
3. Disputes that Engineer has been unable to address because they do not involve the
design (as set forth in the Drawings, Specifications, or otherwise), the acceptability of
the Work, or other engineering or technical matters; and
4. Subject to the waiver provisions of Paragraph 15.07, any dispute arising after Engineer
has issued a written recommendation of final payment pursuant to Paragraph 15.06.B.
B. Submittal of Claim: The party submitting a Claim shall deliver it directly to the other party to
the Contract promptly (but in no event later than 30 days) after the start of the event giving
rise thereto; in the case of appeals regarding Change Proposals within 30 days of the
decision under appeal. The party submitting the Claim shall also furnish a copy to the
Engineer, for its information only. The responsibility to substantiate a Claim rests with the
party making the Claim. In the case of a Claim by Contractor seeking an increase in the
Contract Times or Contract Price, Contractor shall certify that the Claim is made in good
faith, that the supporting data are accurate and complete, and that to the best of
Contractor’s knowledge and belief the amount of time or money requested accurately
reflects the full amount to which Contractor is entitled.
C. Review and Resolution: The party receiving a Claim shall review it thoroughly, giving full
consideration to its merits. The two parties shall seek to resolve the Claim through the
exchange of information and direct negotiations. The parties may extend the time for
resolving the Claim by mutual agreement. All actions taken on a Claim will be stated in
writing and submitted to the other party, with a copy to Engineer.
D. Mediation
1. At any time after initiation of a Claim, Owner and Contractor may mutually agree to
mediation of the underlying dispute. The agreement to mediate will stay the Claim
submittal and response process.
2. If Owner and Contractor agree to mediation, then after 60 days from such agreement,
either Owner or Contractor may unilaterally terminate the mediation process, and the
Claim submittal and decision process will resume as of the date of the termination. If
the mediation proceeds but is unsuccessful in resolving the dispute, the Claim submittal
EJCDC® C-700, Standard General Conditions of the Construction Contract.
©
Copyright 2018 National Society of Professional Engineers, American Council of Engineering Companies,
and American Society of Civil Engineers. All rights reserved.
Page 51 of 71
and decision process will resume as of the date of the conclusion of the mediation, as
determined by the mediator.
3. Owner and Contractor shall each pay one-half of the mediator’s fees and costs.
E. Partial Approval: If the party receiving a Claim approves the Claim in part and denies it in
part, such action will be final and binding unless within 30 days of such action the other
party invokes the procedure set forth in Article 17 for final resolution of disputes.
F. Denial of Claim: If efforts to resolve a Claim are not successful, the party receiving the Claim
may deny it by giving written notice of denial to the other party. If the receiving party does
not take action on the Claim within 90 days, then either Owner or Contractor may at any
time thereafter submit a letter to the other party indicating that as a result of the inaction,
the Claim is deemed denied, thereby commencing the time for appeal of the denial. A denial
of the Claim will be final and binding unless within 30 days of the denial the other party
invokes the procedure set forth in Article 17 for the final resolution of disputes.
G. Final and Binding Results: If the parties reach a mutual agreement regarding a Claim,
whether through approval of the Claim, direct negotiations, mediation, or otherwise; or if a
Claim is approved in part and denied in part, or denied in full, and such actions become final
and binding; then the results of the agreement or action on the Claim will be incorporated in
a Change Order or other written document to the extent they affect the Contract, including
the Work, the Contract Times, or the Contract Price.
ARTICLE 18—MISCELLANEOUS