M & R Civil
M & R Civil
ANNEXURE NO.1 B
Remodelling of UMRALA ZONE WATER SUPPLY SCHEME
Statement Showing Annual Maintanance and Repairs Cost
Sr. Net cost incl.
Particulars Av. M&R Amount for M & R Re marks
No. contigency
1 2 3 4 5 6
A-Proposed Work
1 WTP at Umarala & Magariya H/W 68,458,300.0 1% 684583.00
2 Rising main pipeline 26,640,100.0 0.25% 66600.25
3 Gravity Main Non Metalic Pipe 342,824,100.0 0.25% 857060.25
4 RCC ESR 21,979,700.0 0.50% 109898.50
5 RCC HGLR 49,846,100.0 0.50% 249230.50
6 Pump house 4,150,700.0 0.50% 20753.50
7 Chlorination Arrangement 555,700.0 2.50% 13892.50
Total Rs. 2002018.50
(2) Vallabhipur to Umrala MHW 500 MM Dia DI Rising Main 22030000.00 0.25% 55075.00
(3 )Piprali Group: RM from Umrala HW to Piparali 250 mm PVC 10935000.00 0.25% 27337.50
(1) Piprali group : Well 6.00 Mtr. Dia. & 20.00 mtr. Depth 1.0 No. 600000.00 0.50% 3000.00
Total Rs. 3000.00