Sample Quotation of Combined Cycle Power Plant

The document outlines the installation and commissioning activities for two packages, A and B, which include various equipment such as gas turbines, condensers, pumps, and piping systems. Each package specifies the tasks involved, including placement, alignment, installation of auxiliary equipment, and the need for skilled manpower for pre-commissioning and testing. Additionally, it covers miscellaneous works like painting, insulation, and support structures.

Uploaded by

rafiqdumkt
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views7 pages

Sample Quotation of Combined Cycle Power Plant

The document outlines the installation and commissioning activities for two packages, A and B, which include various equipment such as gas turbines, condensers, pumps, and piping systems. Each package specifies the tasks involved, including placement, alignment, installation of auxiliary equipment, and the need for skilled manpower for pre-commissioning and testing. Additionally, it covers miscellaneous works like painting, insulation, and support structures.

Uploaded by

rafiqdumkt
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Sr.

Description (Package A)
No
1 Gas Turbine, Steam Turbine, Generator and Auxiliaries(IP and LP bypass valve
included) including interconnected piping (OEM Scope)

1. Placement of equipment of foundation , Allignment of equipmenet , grouting.


2. Installtion of the Main equipmnet like GT , ST and Generator .
3. Installation of the Auxiliary Equipments like lube Oil Skid , Power Control cabinet, Air
Intake Filters , Exhaust Diffuser etc
4. Installation of the Interconnection Piping
5. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package

2 Condenser Package

1. Placement on foundation and installation of the Hot Well , Condenser lower half and upper
half
2. Installation of the Expansion Joint
3. Connection with the Condenser and Air evacuation system
4. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package

3 Vacuum Pumps

1. Placement of equipment of foundation , Allignment of equipmenet , grouting.


2. Installtion of the interconnected piping system.
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package

4 Bypass Stack 50 M

1. Placement of the equipment on the Foundation


2. Instalation of the Diverter Damper with the Seal Air System
3. Installtion of the connection piece with the GT and with the HRSG
4. Installtion of the Guilotine Damper with Motor
5. Installation of the Stack with transition pieces and silencers

5 HRSG Horizontal with Main Stack-50M (HRSG)


1. Installation of the HRSG structure
2. Instalation of the HRSG modules
3. Installation of the Drums
4. Installation of the Piping Spools and Supports
5. Installation of the Stack
6. Support for the Pre-Commisioing , Commissioing and Testing including Cleaning ,
Flushing , Restoration , Steam Blowing of HRSG
6 ST- HP Bypass Valve

1. Installation of the Bypass valave with Actuator


2. Installation of Water shut off valve and Spray valve
3. Installtion of the Piping connection
4. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
7 Onload tube cleaning system (OLTCS)

1. Installation of the Ball Collection System


2. Installation of the interconnection piping
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
8 TG Hall- GTG Main EOT Crane
1. Installation of the Rails , Double Gilder Bridge , cabin , Erectrical Systems etc.
2. Pre-Commisioing , Commisioing and Testing activities related to the package

9 TG Hall- ST EOT Crane


1. Installation of the Rails , Double Gilder Bridge , cabin , Erectrical Systems etc.
2. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package

10 Boiler Feed Pump (BFP)


1. Inatalltion of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package

11 Condensate Extraction Pumps (CEP)


1. Inatalltion of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
12 Main Plant Piping + Valves (Power Cycle) and fabricated & prefabricated
Supports + includes alloy steel impulse piping
1. Erection and Installation of the Pipe Spool Pieces at Site along with the supports and
insulation and cladding.
2. Pre-Commisioing , Commisioing and Testing activities related to the package like Hydro
test , NDT , steam blowing.
13 LP Piping for CEP, Vacuum Pumps with supports
1. Erection and Installation of the Pipe Spool Pieces at Site along with the supports and
insulation and cladding.
2. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
14 Lube Oil & GT-ST Interconnecting Piping (L&T Scope)
1. Erection and Installation of the Pipe Spool Pieces at Site along with the supports and
insulation and cladding.
2. Pre-Commisioing , Commisioing and Testing activities related to the package
15 Miscellaneous Works - Steam Blowing fabrication, erection, dismantling,
silencers, Supports etc.
1. Fabrication of Temporaray pipe spooling for the Steam Blowing activity.
2. Erection and dismatling of the temporray pipe spools , silencers and support.
16 Painting
17 Painting work (As per specification)-pipe supplied as raw with out painting
including its support

18 Painting work on primer painted piping spools---Condensate, Condenser air


evacuation piping, GT interconnection piping , piping on other packages.

19 Insulation

20 Commissioning Assistance for Complete package -A

21 Store management
Sr.
Description (Package B)
No
1 Gas Booster Compressors
1. Placement of equipment on foundation
2. Installation of the Compressor Skid along with the coolers and the N2 generation skid
3. Intallation of the interconnetting piping
4. Pre-Commisioing , Commisioing and Testing activities related to the package

2 Induced Draft cooling tower (IDCT)


1. Pultruded FRP sub assembly and Frame assembly
2. Film Fills assembly
3. Fan stack & deck assembly
4. Fan, shaft & Motor Erection
5. Maintenance arraignment assembly
6. Riser pipe structure, riser pipe & REJ assembly
7. Supply of skilled manpower for pre-commissioning, commissioning and performance
guarantee test as per L&T requirement

3 PT + WTP Plant incl lab equipment


1. Installtion of the Dosing skids
2. Installtion of the Clarifier Mechanical Parts
3. Installation of the Demineralization Skids
4. Installation of the Pumps and Interconnecting Piping
5. Supply of skilled manpower for pre-commissioning, commissioning and Testing as per
L&T requirement
4 Gas Conditioning Skid + RMS
1. Installation of the ESD valve , KODs , Filter seperators , Buffer Tanks , Cold vent stack etc .
2. Installation of the Inteconnection Piping
3. Supply of skilled manpower for pre-commissioning, commissioning and testing
activities like N2 purging , cleaning , cardboard blasting etc as per L&T requirement

5 Buffer Vessel
1. Installation of the Buffer Tank along with the Piping connections
2. Supply of skilled manpower for pre-commissioning, commissioning and testing as per
L&T requirement
6 Air conditioning and Ventilation system
1. Installation of the AC indor and outdoor units , Instllation of the Roof Top Units .
2. Installation of the supply and ventilation fans
3. Installation of the Ducting system
4. Supply of skilled manpower for pre-commissioning, commissioning and testing as per
L&T requirement
7 Hydrogen + CO2 + N2 Cylinders
8 CW Pump
1. Installation of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package

9 CW screen & gate, RW Sluice gate & trash rack


1. Installation of the wetted and non wetted embedment parts
2. Installation of the Bar Screens in the Pump House
3. Installation of the Gates and Trash Rack in the Pump House
10 Fire fighting system
1. Installation of the Indoor and Outdoor Hydrant System
2. Installation of the Spray Water System and Sprinkler System
3. Installation of the CO2 Fire System
4. Installation of the Detection System and Fire Alarm Panel
5. Instllation of the Portable Fire Extinguishers
6. Installation of the Fire Piping system .
7. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
11 Workshop Machinary
1. Installation of the workshop machinery like Lathe , Grindinh machine, Drilling machine
and other tools as applicable in the Workshop building.

12 Plate Heat Exchangers


2. Installation of the Plate Heat Exchangers
3. Installation of the Interconnection Piping
4. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
13 Hydrogen Generation Plant
1. Installation of the Skid of the H2 generation plant
2. Installation of the Piping System
14 Waste water treatment Plant
1. Installtion of the Dosing skids and OWS Skid
2. Installation of the Pumps and Interconnecting Piping
3. Supply of skilled manpower for pre-commissioning, commissioning and Testing as per
L&T requirement
15 ACW pumps
1. Inatalltion of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
16 CW Chemical Dosing system
1. Instllation of the Dosing Tanks and Dosing Pumps
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
17 ACW Debris Filter
1. Intallation of the self cleaning filters at the discharge of the ACW Pumps along with piping
connections
18 Miscellaneous Pumps
DM Water Transfer Pumps, Cooling Tower Make up Pump, ,HRSG Fill Pumps,
Portable Water Pump
1. Inatalltion of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
19 Service Water Pump
1. Inatalltion of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
20 Fire water - Electrical motor driven pump
1. Inatalltion of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
21 Fire water -Diesel engine driven pump
1. Inatalltion of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
22 Fire water -Jockey pump
1. Inatalltion of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
23 River Water Pumps (3*600M3 )
1. Inatalltion of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
24 Sump pumps
1. Inatalltion of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
25 CCW Pumps
1. Inatalltion of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
26 Instrument Air compressor
1. Installation of the Compressors , Air Dryers and the Air receivers
2. Installation of the Interconnectiong Piping
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package

27 LP Piping like Potable, Service, fire, HRSG fill, DM Transfer, effluent, WTP (Other
than vendor scope), CCW, DM Feed, Deep Borewell, Instrument Air, River water
intake piping, CW make up piping + Fire Fighting System Piping + valves +
Fabricated & Prefabricated supports, Miscellaneous piping, drains & vents etc

28 Butterfly valves (large-dia above 450NB)


29 Rubber Expansion Joints
30 Metal Expansion joints
31 Gas Booster Compressors shed Crane
32 CW Pump House Crane
33 River Water Intake Pump House Crane
34 CW / ACW / CW
Butterfly valve Hoist
35 CW fore bay stop log gate Hoist & screen hoist
36 Air compressor area Hoist
37 Fire water pump house Hoist
38 Workshop building hoist
39 Other Area Misc. Crane & hoists, Chain blocks
40 Other Misc. work like support structure, pipe support etc--shall be supplied as raw
material
41 Shop Fabricated Tanks ( Atm. Flash Tank + CCW Expansion Tank)
42 Commissioning Assistance for Pacakge B

43 Painting work (As per specification) for pipe and structure, plates, chequred plates
etc
44 Painting work on primer painted piping spools
45 Insulation
46 Wrapping and Coating of Underground Piping : ACW/CW Piping Joints, Raw water,
Fire water and other misc. piping
OTHERS
47 CW/ACW/Intake Piping - GRP Piping
48 Site fabricated Tanks (DM Water Storage Tank -2 Nos + Raw Water & Fire water
storage tank- 1 No.) including mountings, support structure, staircase, access
platform, Internal nozzles with piping
49 Elevator (3 Nos.)
Final Coat / Touch Up painting for all equipment and piping as per the instructions
50
of L&T Engineer including Man Power and other Resources.