Sample Quotation of Combined Cycle Power Plant
Sample Quotation of Combined Cycle Power Plant
Description (Package A)
No
1 Gas Turbine, Steam Turbine, Generator and Auxiliaries(IP and LP bypass valve
included) including interconnected piping (OEM Scope)
2 Condenser Package
1. Placement on foundation and installation of the Hot Well , Condenser lower half and upper
half
2. Installation of the Expansion Joint
3. Connection with the Condenser and Air evacuation system
4. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
3 Vacuum Pumps
4 Bypass Stack 50 M
19 Insulation
21 Store management
Sr.
Description (Package B)
No
1 Gas Booster Compressors
1. Placement of equipment on foundation
2. Installation of the Compressor Skid along with the coolers and the N2 generation skid
3. Intallation of the interconnetting piping
4. Pre-Commisioing , Commisioing and Testing activities related to the package
5 Buffer Vessel
1. Installation of the Buffer Tank along with the Piping connections
2. Supply of skilled manpower for pre-commissioning, commissioning and testing as per
L&T requirement
6 Air conditioning and Ventilation system
1. Installation of the AC indor and outdoor units , Instllation of the Roof Top Units .
2. Installation of the supply and ventilation fans
3. Installation of the Ducting system
4. Supply of skilled manpower for pre-commissioning, commissioning and testing as per
L&T requirement
7 Hydrogen + CO2 + N2 Cylinders
8 CW Pump
1. Installation of the Pumps with Motor
2. Installation of the Piping connections along with alignment .
3. Skilled manpower with required tools for Pre-Commisioing , Commisioing and Testing
activities related to the package
27 LP Piping like Potable, Service, fire, HRSG fill, DM Transfer, effluent, WTP (Other
than vendor scope), CCW, DM Feed, Deep Borewell, Instrument Air, River water
intake piping, CW make up piping + Fire Fighting System Piping + valves +
Fabricated & Prefabricated supports, Miscellaneous piping, drains & vents etc
43 Painting work (As per specification) for pipe and structure, plates, chequred plates
etc
44 Painting work on primer painted piping spools
45 Insulation
46 Wrapping and Coating of Underground Piping : ACW/CW Piping Joints, Raw water,
Fire water and other misc. piping
OTHERS
47 CW/ACW/Intake Piping - GRP Piping
48 Site fabricated Tanks (DM Water Storage Tank -2 Nos + Raw Water & Fire water
storage tank- 1 No.) including mountings, support structure, staircase, access
platform, Internal nozzles with piping
49 Elevator (3 Nos.)
Final Coat / Touch Up painting for all equipment and piping as per the instructions
50
of L&T Engineer including Man Power and other Resources.