1-Bx Changaly
1-Bx Changaly
I GENERAL EXPENSES
1.1 Site installation and folding Fft 1
This package takes into account all the construction site costs related to installations, possible displacements and withdrawal in
the area relating to the Lot.
- the layout of floor surfaces for storage of materials, parking of machines and vehicles, construction of offices or construction
buildings,
- the development or construction of access roads to the base and their maintenance,
- the folding of installations and equipment at the end of the construction site,
- Restoration of the sites by reforestation with fast-growing species including supply and transport of plants, as well as the
development of quarry sites.
This price does not include the installation or services due to the Mission of Control of the Engineer.
This lump sum price, may in no case exceed 15% of the amount of the Offer and includes, the redevelopment of sites and
reforestation with fast-growing species, all sujétions and aléas, will be paid to the Contractor under the following conditions:
- 70% on the basis of an engineer’s certificate stating the eXstence of equipment and materials on site.
30% on provisional acceptance after the Contractor is prepared all borrowing sites with fast growing forest species
It pays for the cleaning and sweeping of the right-of-way of construction work, canals, dykes and preparation of cofferdams, diversion, pumping and flattening of water for the execution of works, the pickling and the implantation of
It also includes the costs of topographical surveys (complementary or detailed) for the establishment and production of execution
plans.
it includes:
- preparatory work (piping, implantation....);
- the design and establishment of access roads and circulation areas necessary for access during construction, access to the
loading and unloading zones, site facilities and in general for the completion of the works;
- The execution of all necessary additional geotechnical surveys;
- The necessary additional surveys;
- the preparation of calculation notes;
- the preparation of reinforcement plans;
- the establishment of harvest plans;
- the edition of the plans and calculation notes in a number of contract copies;
- Assembly of execution files including all attachments.
The package will be paid per file in triplicate and on digital key in a usable and editable format
Earthworks will be carried out at all depths and in all types of soil, including rock and water drainage if necessary. It includes the
use of spikes and sledgehammers, breakers or other equipment if necessary, and shoring or dewatering. If necessary, the raising
of the walls and bottoms of the excavations, the widening with elephant's feet, all shovelling, loading, transport, unloading,
straddling, spreading and compacting on the parts to be backfilled in the right-of-way of the worksite, the surplus spoil can be
used as shimming backfill and backfill for the construction of dykes and embankments. The parts of the excavations not occupied
by the foundation works will be rammed in layers 0.20 m thick, at the contractor's expense.
Earthworks carried out by hand or with mechanical equipment on all types of ground, including rocky ground or ground containing
a water table, to open trenches for pipes and standard structures, including all the necessary steps.
This price includes: staking out the pipe, opening the trench to the required width and depth, lining the excavated soil along the
trench, shoring if necessary, making the extra widths or depths required to create any recesses or projections at the joints, and all
other incidentals.
In addition, it includes all the difficulties of meeting electrical or telephone cables, masonry, forestry, any shielding of excavations,
etc., and all other difficulties.
The width of the trench must be at least 0.60 m for pipes smaller than 125 mm. For larger diameters, the width must be increased
by 0.10 m on each side. The depth must be increased by 0.10 m for the laying bed if necessary. The work must be carried out in
accordance with the longitudinal and marking profiles approved by the project manager. No changes to the route will be made
without the prior approval of the authorities.
The price also covers earthworks for standard pipework.
It will take account of all the difficulties associated with this type of work, in particular all safety measures, shoring, as well as the
III.2.1 m3 1467
adjustment and possible transport at public expense of excess excavated material.
Backfilling the trench by hand or with mechanical equipment above the bedding backfill with the excavated spoil, including the
straddling of this spoil at all distances, including all conditions, in particular tamping in the case of road crossings or built-up areas
III.2.2 m3 868.9307
and the repair of gravel or tuff pavements, not including the bedding backfill counted with the laying of the pipes. The backfill will
be compacted 20 cm above the upper generatrix of the pipe laid.
III.2.3 Supply, transport and laying of sand at the request of the project owner for clay, rock or tuff sections and the m3 122.32
IV CONSTRUCTION AND EQUIPPING OF STRUCTURES ON THE PRESSURE PIPE
The prices cover the complete construction of the current structures in reinforced concrete dosed at 350 kg/m3, 0.15 m thick with
a minimum 5 cm layer of clean concrete, in accordance with the details on the plans and the instructions of the authorities,
including painted steel rungs.
The reinforcement will be T8, spaced at 10 cm intervals in a single layer, on the inside wall of the manholes, including inverts and
slabs in accordance with the plans and any other special requirements not shown. Surfaces in contact with the ground will be
painted with three coats of bitumen. The external dimensions of the manholes are indicative and by no means restrictive and will
be executed in accordance with the administration's plans.
Equipment of standard structures:
Equipment of a suction cup structure on PEThd pipe, DE 400 mm -in accordance with the standard plan provided in
IV.1
the standard plans file. Each structure comprises
2 Welding collars with steel mobile flange DE 400/ DN 400
2 DN 400 cast iron flanged wall sleeves, L=1.00 m
1 Cast iron flanged tee 400/80/400
1 Gate valve with elastomer seal and DN80 direct passage
1 DN 80 suction cup unit 1
Installation of a drainage system on a PEThd pipe, OD 400 mm, in accordance with the standard plan provided in
IV.2
the standard plans file:
Welded collar with movable steel flange DE 400/400
Cast iron flanged sleeve DN 400, L=1.00 m
Cast iron flanged tee 400/80/400
DN 80 dismantling joint
Gate valve with elastomer seal and DN 80 direct passage
Cast iron flanged sleeve DN 80, L=1.00 m unit 1
V CONSTRUCTION OF THE DAMPING BASIN
The prices cover the complete construction of the damping basin in reinforced concrete dosed at 350 kg/m3, 0.15 m thick with a
minimum 10 cm layer of clean concrete, in accordance with the details on the plans and the instructions of the authorities.
The reinforcement will be T8, spaced at 20 cm intervals in a single layer, on the inside wall and invert side, in accordance with the
plans and all other specifications not shown. Surfaces in contact with the ground will be painted with three coats of bitumen. The
external dimensions of the manholes are indicative and in no way limiting and will be executed according to the administration's
plans.
Prices include in particular :
- All earthworks in All types of terrain.
- Site installation: topographical work.
- The supply and installation of the materials required to complete these works, including steels and the possible use of special
cements such as CPA 45 or equivalent.
- The supply and installation of a coat of bitumen for the surfaces in contact with the ground, and three coats of paint on the
outside.
- Supply and installation of backfill materials, including compaction.
- Supply of a wall crossing sleeve with sealing collar and welded collar for connection to the discharge pipe.
V.1 EARTH BACKFILL FROM EXCAVATIONS :
Backfill for shimming and protecting the walls from the excavations, soil judged to be sound and absolutely free of gypsum,
including transport, careful sieving, spreading, adjustment in layers up to 0.20 m thick, watering, ramming to refusal, measured at m3 42
the backfilled void.
V.2 CLEAN CONCRETE B1 :
Type B1 clean concrete dosed at 150 kg of CPI 32.5 cement per m3 of concrete, including supply, laying and all other
m3 1,48
requirements.
V.3 CONCRETE FOR REINFORCED CONCRETE
Cement concrete dosed at 350kg of CPI 32.5 cement per m3 of type B5/350 concrete to be reinforced. m3 3,49
V.4 DE 400/DN400 welding collar
This price covers the supply, transport and assembly of a DE400/400 welding collar. u 2
V.5 Feed-through sleeve
The price covers the supply, transport and assembly of a wall feed-through sleeve with sealing collar DN 400, L = 0.50 m. u 2
VI CONSTRUCTION OF CONCRETE IRRIGATION CHANNELS
The prices cover the complete construction of the main and tertiary irrigation canals in reinforced concrete dosed at 350 kg/m3,
0.15 m thick with a minimum 5 cm layer of clean concrete, in accordance with the details in the plans and the project owner's
instructions.
The reinforcement will be T8, spaced at 20 cm intervals in a single layer, on the inside wall and invert side, in accordance with the
plans and any other specifications not shown.
The prices include in particular :
- All earthworks in All types of terrain.
- Site layout: topographical work.
- The supply and installation of the materials required to complete these works, including steel, and the possible use of special
cements such as CPA 45 or equivalent.
- preparation of the smooth formwork for pouring the channel walls
- making expansion joints 2 cm wide every 10 m of the channel and filling the expansion joints with mastic-coated polystyrene.
- Supply and installation of backfill materials, including compaction.
VI.1 EARTH BACKFILL FROM EXCAVATIONS:
Backfill for shimming and protecting the walls from the excavations, earth judged to be sound and absolutely free of gypsum,
including transport, careful screening, spreading, adjustment in layers no thicker than 0.20 m, watering, ramming to refusal, m3 5804
measured at the backfilled void.
VI.2 CLEAN CONCRETE B1 :
Type B1 clean concrete dosed at 150 kg of CPI 32.5 cement per m3 of concrete, including supply, laying and all other handling. m3 1741.2
VI.3 CONCRETE FOR REINFORCED CONCRETE
Cement concrete dosed at 350 kg of cement CPI 32.5 per m3 of type B5/350 concrete to be reinforced, including the preparation
m3 2720.625
of expansion joints every 10 m.
VI.4 IRRIGATION INTAKE STRUCTURE
Construction of an irrigation intake structure in reinforced concrete dosed at 350kg of cement CPI 32.5 per m3 of type B5/350
concrete in accordance with the plan provided by the client. The work includes the construction of a metal guardrail including a
Unit 88
locking piece and a metal gate made of 3 mm thick sheet metal. The guardrail is made up of a metal frame consisting of a U-
shaped iron embedded in the concrete,
This price covers, in accordance with the execution project, the excavation of all types of soil at any depth and the profiling of drains
and collectors. The excavated material will then be used as backfill for the profiling of the canals, tracks, embankments and
embankments, and will therefore be temporarily stored and paid for in the backfill price. This price includes in particular:
- Necessary staking and establishment of longitudinal profiles;
- Preliminary cleaning of the site, excavation and stripping of topsoil to an average depth of 30 cm (thirty centimetres). Disposal of
all the products removed at a disposal site approved by the project owner.
- digging The excavation
- Profiling and adjusting the ditch bottoms and embankments in accordance with the cross-sections approved by the project owner.
- Protection against all types of water during excavation;
- Prior geotechnical reconnaissance of the excavated material;
- The use of mechanical or manual means for the excavation, including the supply and removal of equipment,
- All safety-related matters;
- It should be noted that The quantities of excavated material that can be reused as backfill will be determined on The basis of
contradictory topographical surveys and will be recorded in a report.
The company is required to provide the topographical plans and profiles necessary for the project owner to check that the work
complies with the specifications.
This price applies to the cubic metre of excavated material carried out in accordance with the longitudinal profiles of the project
and taken on the basis of contradictory attachments and recorded on the minutes and on the basis of the topographical plans m3
supplied by the company and approved by the project owner, with the unused quantities being evacuated to the landfill site
indicated by the project owner, regardless of the transport distance. 5857.44
VIII CONSTRUCTION OF RUNWAYS
VIII.1 Creation of crushed as-built tracks 5 m wide, 6 m platform, 20 cm sub-base (0/31.5) and 20 cm base (0/20): km
VIII.2 Creation of crushed as-built tracks 3 m wide, 4 m platform, 20 cm sub-base (0/31.5) and 20 cm base (0/20): km
VIII.3 Construction of culverts
Supply, transport and installation of culverts: This price includes the supply, installation and complete execution of culverts,
including headworks. In accordance with the plan supplied by the project owner, including all the necessary steps.
This price includes
- The supply of nozzles on site
-Excavation, whatever the nature of the soil, loading, transport of materials over any distance, unloading at the place of reuse or at
a final storage site approved by the project owner.
-Preparing The laying bed in accordance with The technical specifications.
Backfilling the trenches with selected materials and compacting them, as well as laying the sub-base and base courses of the
runway to be crossed
- construction of the reinforced concrete headworks (upstream and downstream works)
-All aspects of connecting the nozzles to the headworks Unit 4
Totat Rate (GMD)