WORKPLAN

The document outlines a construction project schedule for various tasks from March to October 2025, detailing the duration and start dates for each task. Key phases include substructure work, upper floor construction, roof installation, and finishing tasks. The timeline includes specific tasks such as site clearance, concrete work, and installation of doors and windows, with a total of 51 tasks listed.

Uploaded by

judexnams1on1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views1 page

WORKPLAN

The document outlines a construction project schedule for various tasks from March to October 2025, detailing the duration and start dates for each task. Key phases include substructure work, upper floor construction, roof installation, and finishing tasks. The timeline includes specific tasks such as site clearance, concrete work, and installation of doors and windows, with a total of 51 tasks listed.

Uploaded by

judexnams1on1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task

Task Name Duration Start


Mode
Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025
Mar Apr May Jun Jul Aug Sep Oct
1 SUBSTRUCTURE 22 days Mon 03/03/25
2 Site Clearance 1 day Mon 03/03/25
3 Topsoil for Excavation 1 day Tue 04/03/25
4 Setting out 1 day Wed 05/03/25
5 Excavation of trenches and Pits 2 days Thu 06/03/25
6 Earthwork Support 1 day Mon 10/03/25
7 Surface Treatment: Antitermite, level 1 day Tue 11/03/25
and compact
8 Concrete work: blinding, foundation 1 day Wed 12/03/25
Footings and Column Bases
9 Mansory Block work in foundation 2 days Thu 13/03/25
10 Filling to excavations 1 day Mon 17/03/25
11 Disposal 1 day Tue 18/03/25
12 Reinforcement to column bases and 1 day Wed 19/03/25
column starters
13 Formwork: Column Bases and Columns1 day Thu 20/03/25
14 Concrete work, Columns starters 2 days Fri 21/03/25
15 Filling to make up levels and Hardcore 1 day Tue 25/03/25
filling
16 BRC Fabric Mesh 1 day Wed 26/03/25
17 Damp proof Membrance 1 day Thu 27/03/25
18 Formwork: Oversite Concrete 1 day Fri 28/03/25
19 Concrete work: Oversite Concrete 2 days Mon 31/03/25
20 FRAMES 14 days Wed 02/04/25
21 Formwork: Columns, Beams and 2 days Wed 09/04/25
Lintels
22 Reinforcement to column , beams and 5 days Wed 02/04/25
Lintel
23 Concrete work in column, beams 7 days Fri 11/04/25
24 UPPER FLOOR 36 days Wed 23/04/25
25 Formwork: Roof Floor Beam and 8 days Wed 23/04/25
Suspended floor
26 Reinforcement to column , beams and 8 days Mon 05/05/25
Lintel
27 Concrete work in Roof Floor Beam 19 days Fri 16/05/25
and Suspended floor
28 STAIR CASE 17 days Fri 09/05/25
29 Formwork: Stair case 2 days Fri 09/05/25
30 Reinforcement to stair case 5 days Tue 13/05/25
31 Concrete work in Stair case 10 days Tue 20/05/25
32 MANSORY BLOCK WORK 38 days Fri 02/05/25
33 ROOF AND ROOF COVERING 24 days Tue 24/06/25
34 Formwork: roof beam 2 days Tue 24/06/25
35 Reinforcement to beam 4 days Thu 26/06/25
36 Concrete work in roof beam 7 days Wed 02/07/25
37 Works associated with wood members7 days Fri 11/07/25
38 Roof covering 4 days Tue 22/07/25
39 FABRICATION/INSTALLATION OF DOORS51 days Tue 20/05/25
40 FABRICATION/INSTALLATION OF 51 days Tue 20/05/25
WINDOWS
41 WALL FINISHING 18 days Mon 28/07/25
42 Rendering Inluding Screeding 11 days Mon 28/07/25
43 Tiling 7 days Tue 12/08/25
44 FLOOR FINISHING. TILING INCLUDING 14 days Fri 22/08/25
STAIR CASE
45 CEILING FINISHING 16 days Thu 11/09/25
46 Rendering Suspended slab and Pop 9 days Thu 11/09/25
screeding
47 Supply and install pvc ceiling strip 5 days Fri 26/09/25
48 PIPING WORK AND INSTALLATION OF 56 days Mon 04/03/24
SANITARY WARES, FITTINGS AND
ACCESSORIES
49 PIPING WORK AND INSTALLATION OF 56 days Mon 04/03/24
ELECTRICAL FITTINGS
50 PAINTING AND DECORATION 14 days Thu 11/09/25
51 EXTERNAL WORKS 10 days Wed 01/10/25

4 - BEDROOM TERRACE Wed 05/02/25


Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

DUPLEXEX WITH Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

A PENT FLOOR

Page 1