PAT Checklist_ Colocation_ 19-Jan-2025
PAT Checklist_ Colocation_ 19-Jan-2025
Acceptance Documents
As-Built Quantity
Project Name : Site Status Project Type
Others ( )
Unit Code Unit Description Unit Measurement Designed Quantity Actual Quantity
Initial
Design Office
Parties Implementation Contractor (…….........................) Design Office / Tawal Field Inspector (…….........................)
Name
Date
Signature
Contractor Logo
Acceptance Documents
Outstanding Items List ( OIL )
Project Name :
Site ID : PO #:
Region : WO#:
District: City:
10
All Outstanding Items noted above to be cleared in accordance with the Contract
Parties Implementation Contractor (…….........................) Design Office / Tawal Field Inspector (…….........................)
Name
Date
Signature
All Outstanding Items noted above have been cleared in accordance with the Contract
Parties Implementation Contractor (…….........................) Design Office / Tawal Field Inspector (…….........................)
Name
Date
Signature
SITE NAME:
TOWER HEIGHT:
Project Name
S.NO.
10
11
12
13
14
15
Name
Date
Signature
RAMBOLL REPRESENTATIVE
________________________
NAME
________________________
DATE
________________________
SIGN
INSPECTION ITEMS
Check Shelter /ODU model and serial number if any , Foundation , Installation
MDB / DCDP power connections, SCECO ( lugs, terminals, tightening,Installation , Breakers..) if any as per scope ,
Red-Line Drawings
Updating of all as-built drawings include reflecting of all active equipment and report for any deviation from approved FDE
_____
_____
_____
RESULT
SEVERITY
PASS N/A FAIL
MAJOR
MAJOR
MINOR
MAJOR
MAJOR
MAJOR
MAJOR
MINOR
MAJOR
MAJOR
MAJOR
MAJOR
MINOR
________________________
NAME
________________________
DATE
________________________
SIGN
3.1.4 Generator Signal / Control Cable is correctly connected to the Generator Controller & to the Controller unit
3.1.5 Check that the Coolant & Lube Oil levels are as per requirements
3.1.7 Where Commercial Grid is available, open the kWh meter panel Circuit Breaker - CHECK
3.1.8 Open the Circuit Breaker on the Alternator input to the ATS - CHECK
3.1.9 Manually Start the Generator (with the Remote Start / Stop disabled) - CHECK
Check Engine Parameters on the Generator Control Panel (Battery Volts, Oil Pressure & Coolant Temp) for norma
3.1.10
with no alarms
3.1.11 Check that the Alternator Parameters on the Generator Control Panel (Volts & Frequency each Phase) are within
3.1.12 Close the Circuit Breaker on the Alternator input to the ATS - - CHECK
Verity that the ATS correctly passes the Generator Power Source through to the distribution panel boxes and on
3.1.13
System (if installed)
3.1.14 Manually Stop the Generator and enable Remote Start / Stop functionality - CHECK
3.1.15 Close the Circuit Breaker on the kWh meter panel (if applicable) - CHECK
3.2 DISTRIBUTIONAL PANEL BOXES & SITE ELECTRICAL WORKS
3.2.1 Verify that Site Folder contains the Electrical Wiring Conformance Documentation. (FDED/As-Built)
3.2.2 Verify all Circuit Breakers are of the correct ratings.
3.2.3 Verify that distribution panel boxes & Site Electrical Works Cabling have been installed as per approved FDED
3.2.4 Verify the distribution panel boxes is connected to grounding system as per diagrams
3.2.5 Verify all Circuit Breakers are of the correct labelled correctly
3.2.6 Verify that indicators on the Surge Protective Device remain Green
3.2.7 Demonstrate Continuity between the Earth Link and the Neutral Link within the distribution panel boxes
Measure & record incoming AC supply Voltage from each of the Main Circuit Breaker Terminal Screws to the Neu
(expected: ~220V, however, values indicating correct wiring are required)
3.2.10
(whilst measuring, ensure that the voltage level does not decay over a 5 second period, which may indicate a Neu
low integrity which can damage equipment in 3 phase systems)
Measure & record the incoming AC supply Voltage between each of the Main Circuit Breaker Terminal Screws.
3.2.11
(expected: 0V / ~400V, however, values indicating correct wiring are required
Close the Circuit Breaker for the twin AC Service Outlet & verify both sockets function by plugging in an appliance
Charger)
3.2.12 NOTE: If Generator is used to provide AC input power to the distribution panel boxes , and the DC Power System
to undergo PAT, then return to the final 2 steps of the Generator PAT Process
3.3.7 Verify that each Cabinet is connected to the grounding system as per approved FDED
3.3.8 Verify all utilized DC Distribution Circuit Breakers are labelled correctly
Verify Continuity between the Earth Terminal and the Neutral Terminals within the incoming AC Mains connectio
3.3.9
Neutral integrity).
3.3.10 Verify that the temperature sensor is installed in the battery compartment (VRLA)
Demonstrate Continuity between the incoming AC Mains Earth Terminal and the Master Equipment Cabinet bod
3.3.11
subracks.
3.3.12 Demonstrate Continuity between the incoming AC Mains Earth Terminal and the Cabinet Grounding Bar.
Verify that the DC Common Bus is earthed in one location by visual inspection & Demonstrate Continuity of the D
3.3.13
the Equipment Grounding Bar
Using a Calibrated Digital Multi-Meter, measure & record the OCV of each Battery String in the Master Cabinet (if
3.3.14
points where the DC Power System Battery Cables connect to Battery Terminal (isolated by the Battery CBs one a
Verity that Rectifier Modules, Rectifier Controller & Site RMMS Controller are all powered up & active as indicate
3.3.16
Displays
Open the distribution panel boxes Circuit Breaker which feeds the DC Power System, and observe that the Batte
to the load. Close this Circuit Breaker again.
NOTE: If Generator is used in manual start / stop operation, to provide AC input power to the distribution panel
3.3.17
Power System, then return to the final 2 steps of the Generator PAT Process
NOTE: If Generator is used in manual start / stop operation, to provide AC input power to the distribution panel
Power System, then return to the final 2 steps of the Generator PAT Process
MAJOR = REJECTION
Name
Date
Signature
RAMBOLL REPRESENTATIVE
________________________
NAME
________________________
DATE
________________________
SIGN
RESULT
NSPECTION ITEMS
SEVERITY PASS
ESEL GENERATOR & DC POWER
NTS FOR DIESEL GENERATOR
MAJOR
SLD MAJOR
FDED MAJOR
ator MAJOR
U ~ M:
n each of the Main Circuit Breaker Terminal Screws.
MAJOR
wiring are required
____V
e distribution panel boxes , and the DC Power System is not yet required MAJOR
rator PAT Process
d correctly MINOR
ral Terminals within the incoming AC Mains connection area (indicating
MAJOR
Lower:
he OCV of each Battery String in the Master Cabinet (if applicable) at the
MAJOR
to Battery Terminal (isolated by the Battery CBs one at a time)
____V
MS Controller are all powered up & active as indicated by LED & LCD
MAJOR
eds the DC Power System, and observe that the Battery provides back-up
N/A FAIL
Mid: Lower:
____V ____V
M ~ L: L ~ U:
____V ____V
N/A FAIL
Upper:
Batteries to be installed before HO visit to avoid vandalism.
____V
________________________
NAME
________________________
DATE
________________________
SIGN