Rainfall_runoff_simulation_using_MIKE11_NAM
Rainfall_runoff_simulation_using_MIKE11_NAM
net/publication/46480595
CITATIONS READS
46 2,740
2 authors:
All content following this page was uploaded by Supiah Shamsudin on 05 January 2014.
ABSTRACT
INTRODUCTION
Various model have been developed to solve the rainfall runoff relationship in
engineering research and practices. The widely known rainfall runoff models
identified are the Rational Method (McPherson, 1969), Soil Conservation
Service-Curve Number Method (Maidment, 1993), and Green and Ampt Method
(Green, 1911). The more complex models which should provide better runoff
estimation are continuously being researched and developed. Some of the
complex models identified are Genetic Danish MIKE11 NAM (1972). The
choice and validity of the model depends on the type of problem, the data
availability and the decision to be made.
The objective of this study is to estimate the rainfall runoff discharges of Sungai
Layang watershed using MIKE11 NAM model. The long term simulation (1988-
2000) was carried out based on the available rainfall and evaporation data. The
calibration and validation procedures of the model were carried out to provide a
satisfactory estimation. This rainfall runoff study is vital for the purpose of
Layang reservoir water quality amelioration.
Site Descriptions
There are two reservoirs within the Layang catchment area; Upper Layang
reservoir and Lower Layang reservoir. Upper Layang resevoir is in Masai, 40km
north east of Johor Bahru City. The reservoir is situated in the undulating area
and surrounded by hills. The maximum altitude is 160m and minimum altitude is
30m above mean sea level. The Upper Layang catchment is located
approximately within the coordinates of 1o30’N and 1o36’N latitudes and
103o50’E and 104o00’E longitudes with an average catchment slope of 1.6%. It
constitutes the south-western part of the State of Johor. Upper Layang catchment
is one of the major hydrological sources that produce runoff for the reservoir.
Sungai Layang is the main river that drains into the reservoir.
Lower Layang Reservoir is on the eastern part of the Upper Layang Reservoir.
The drainage basin for Hilir Layang Reservoir is 20.5 km2. The total drainage
basins for both reservoirs is 50.0 km2. Water outflow from both catchment is
about 40 MFD. At the present time, the outflow rate of water from the intake
tower to the water treatment plant is 28.5 MGD. These areas are shown in Figure
1.
The surrounding tributaries and their activities around the catchment area are
summarized in Table 1.
2
JURNAL KEJURUTERAAN AWAM (JOURNAL OF CIVIL ENGINEERING) Vol. 15 No. 2 2002
3
JURNAL KEJURUTERAAN AWAM (JOURNAL OF CIVIL ENGINEERING) Vol. 15 No. 2 2002
Mike11 NAM
MIKE11 NAM model was applied primarily because of its ability to simulate the
watershade physical processes in more detail. MIKE11 NAM model is a
watershed lumped-parameter model which are highly relevant with this particular
watershed under study and the long term flow simulation desired. In addition, it
is a complete and effective modeling software with the adds-on module which
allows flexibility for future investigation. The MIKE11 was applied because of
its availability in the Hydraulic and Hydrology Department, Universiti Teknologi
Malaysia.
The reliability of the MIKE11 NAM was evaluated based on the Efficiency Index
(EI) as described by Nash and Sutcliffe (1970). There were several related
studies available for model performance evaluation such as by Aitken (1973) and
Fleming (1975). The procedure by Nash and Sutcliffe (1970) had been widely
used for the detection of systematic errors with respect to long term simulation.
The EI was developed to evaluate the percentage of accuracy or goodness of the
simulated values with respect to their observed values. The EI as described by
Nash and Sutcliffe (1970) are as follows :
4
JURNAL KEJURUTERAAN AWAM (JOURNAL OF CIVIL ENGINEERING) Vol. 15 No. 2 2002
The Efficiency Index (EI) equal to 1 indicates the best (perfect) performance of
the model.
Root Mean Square Error (RMSE) method used by Fleming (1975) was another
method applied to evaluate the reliability of MIKE11 during this study. This
method can be regarded as a measure of absolute error between the computed
and observed flows. RMSE values tend to be zero for perfect agreement between
observed and simulated values. RMSE is defined as follows :-
5
JURNAL KEJURUTERAAN AWAM (JOURNAL OF CIVIL ENGINEERING) Vol. 15 No. 2 2002
Input Data
The rainfall and evaporation data were monitored and gathered by the relevant
authorities in Malaysia. The rainfall data applied for MIKE11 was obtained from
Drainage and Irrigation Department (DID) Ampang, Kuala Lumpur, while the
evaporation data was obtained from the Malaysia Meterological Service (MMS),
Petaling Jaya, Selangor. Daily rainfall data for 12-year period 1988 – 2000 for
Layang Watershed obtained from DID Station No. 1539301 was applied. There
were some missing rainfall and evaporation data observed during this study. The
missing data values was treated by applying the Arithmetic Mean Method
(Maidment, 1993). The rainfall data from Lim Lim Station, Plentong Station and
Tiram Stations were utilized for the missing value estimation using the method
above. The related rainfall station used for the study are shown in Table 2 :
The reliability of the rainfall data was tested by double mass curve method
(Gupta, 1989) as shown in Figure 2. The straight line graph obtained indicated
that the data is consistent. Non straight line graph would appear if the data have
been subjected to various changes such as changes in recoding station or shift in
observation practices.
6
JURNAL KEJURUTERAAN AWAM (JOURNAL OF CIVIL ENGINEERING) Vol. 15 No. 2 2002
The areal precipitation or the representative precipitation over a defined area was
required for the MIKE11 NAM computation. The areal precipitation was
computed from point precipitation by Thiessen polygon method (Gupta, 1989).
The point precipitation was obtained from the record of a group of rainfall
gauges within the area. The percentage weight to denote the degree of influenced
of the individual rainfall station over the watershed rainfall was calculated. The
percentage weights were obtained by considering the proportion of its
representative area.
The area obtained for the total Layang watershed area was 33.89 km2. the
Layang River sub-watershed area was 4.036 km2. The areal precipitation was
computed by multiplying the precipitation at each station and their calculated
percentage weight. The percentage weights were used for the Mean Areal
Rainfall (MAR) input, in the MIKE11 model. The percentage weights input into
the MIKE11 model are shown in Table 3.
A weir with a 90o V-notch was constructed for flow measurement for the purpose
of model calibration. The weir was constructed according to the British Standard
BS 3680: Part 4A: 1981. (Methods of measurement of Liquid Flow – Part 4A.
Thin-plate weirs). The site selected for the weir installation (as stated in the BS
3680: Part 4A: 1981) must have a uniform and steady approach channel. The
weir was constructed with the crest level height of 0.35m above datum. The weir
was constructed from a 10 mm Perspex sheet, put in position with a 7.5 mm
diameter, PVC pipe filled with cement. An asphalt sheen was screwed to the
bottom part of the weir and laid down in the upstream direction of the river to
ensure a acomplete volume of discharges flowing through the weir. The weir
was calibrated at the Hydraulics and Hydrology Laboratory to determine the
coefficient of discharge (Cd) value which was 0.61. The twelve (12) months
(October 1999 – September 2000), flow data observed from the constructed weir
was used for the calibration procedure in the MIKE11 NAM model. The daily
water level was monitored using the water level recorder SPOHR QP1 of
7
JURNAL KEJURUTERAAN AWAM (JOURNAL OF CIVIL ENGINEERING) Vol. 15 No. 2 2002
Mestechnik, Germany. The water level recorder was established at the stream
site, which enables continuous observation of water level. The stage height was
set up for the purpose of recording the height of the water surface in a stream
above a fix datum. The fornightly check-up is required for the water level
recorder.
The application of MIKE 11 model for rainfall runoff estimation can be divided
into two (2) stages. The first stage is the calibration process to determine an
optimum values of the model parameters. The second stage is the streamflow
simulation using the estimated model parameter during the calibration process.
The on site data acquisition problems are the accessibility for regular
maintenance and disturbance due to animals in the forest. The nature of rainfall
pattern is spatial resulting in an uneven rainfall distribution within the catchment
area. This factor directly affect the rainfall-runoff model calibration. The
unexpected flood surrounding the gauging site would certainly damage the data
acquisition system and reduce the accessibility for observation and maintenance.
Flood during March 2000 that occurred within the study site add more missing
data and create problem to the calibration process. The problem of missing data
was handled by the application of adjustment. The adjustment procedure employ
the interpolation and method of proportion in the rainfall-runoff relationship.
The flow series are simulated based on the daily rainfall for the 12-year period,
1988 to 2000. Figure 4 demonstrates the simulated daily flow for the Layang
Reservoir (1988 – 2000). The simulated peak flow occur in 1992 and 1994 with
approximate values are 20.94 m3/s and 18.93 m3/s respectively. The streamflow
validation curve from June 1998 to July 1998 is shown in Figure 5.
8
JURNAL KEJURUTERAAN AWAM (JOURNAL OF CIVIL ENGINEERING) Vol. 15 No. 2 2002
Zamri Mohd (2000) obtained maximum simulated runoff values of 30.05 m3/s
and 25.5 m3/s in 1992 and 1994 respectively. These values were different from
the values obtained during this study probably because their weir was constructed
further downstream and affected the watershed size used in MIKE 11
computation. Secondly their weir was located at the flood zone which was
experiencing the abrupt change of water level.
GROUNDWATER:
Ratio of groundwater catchment area to
topographical catchment 1.0
Root zone threshold value for groundwater recharge 0.1
Specific yield of groundwater reservoir 0.1
Time constant for routing baseflow 1000
Minimum groundwater depth 0.0
Maximum groundwater depth causing baseflow 12.0
Seasonal variation of this depth (Y/N) N
Groundwater depth for unit capillary flux 0.0
Change groundwater abstraction data (Y/N) N
9
JURNAL KEJURUTERAAN AWAM (JOURNAL OF CIVIL ENGINEERING) Vol. 15 No. 2 2002
More automatic rainfall stations should be made available within the Layang
watershen to give a better representation of the mean areal rainfall and so as to
achieve better results. At the moment there is only one rainfall station being
established at the Layang watershed. The computation for the mean areal rainfall
carried out during this study was based on the Tiram and Plentong rainfall
11
JURNAL KEJURUTERAAN AWAM (JOURNAL OF CIVIL ENGINEERING) Vol. 15 No. 2 2002
stations, the closest rainfall stations which are located outside the Layang
watershed. More rainfall stations will reflect more accurately the effects of
locality differences in the rainfall pattern. The Layang watershed normally
experienced an amount of the rainfall which differs with different locality within
the same period of time (Tarmizi et.al, 1997).
CONCLUSIONS
ACKNOWLEDGEMENTS
The authors appreciates all the helps obtained from everyone involved, especially
for the technicians of UTM-FKA Hydrology Laboratory, Encik Rahim hashim
and Encik Ismail Husin for working hard at the site. The authors are also
thankful to the Research Management Center (RMC) – Universiti Teknologi
Malaysia for the financial support under Vote 71327.
REFERENCES
Green, W.H., and G.A. Ampt (1911), “Studies On Soil Physics. 1. The Flow of
Air and Water Through Soils.” Journal of Agriculture Science, Vol 4,
pp. 1-24.
12
JURNAL KEJURUTERAAN AWAM (JOURNAL OF CIVIL ENGINEERING) Vol. 15 No. 2 2002
McPherson, M.B. (1969), “Some notes on the Rational Method of Storm Drain
Design”, Tech. Memo. No.6. ASCE, Water Resources Research
Program, Harvard University, Cambridge, MA.
Nash, J.E. and Sutcliffe, J.V. (1970). River Flow Forecasting Through
Conseptual Models, Part 1: A Discussion on Principals. Journal of
Hydrology, V10, p 282-290.
13