Chap 2 Long-Term Investment
Chap 2 Long-Term Investment
INVESTMENT
Advanced Financial
Management
Te n k i r S e i f u , P h D 2/1/20XX 1
Chapter objectives
1 2 3 4 5
© 2012 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted in a
license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
Net Present Value
(continued)
Information:
A detailed market study revealed expected annual revenues of
$300,000 for new earphones. Equipment to produce the earphones
will cost $320,000. After five years, the equipment can be sold for
$40,000. In addition to equipment, working capital is expected to
increase by $40,000 because of increases in inventories and
receivables. The firm expects to recover the investment in working
capital at the end of the project’s life. Annual cash operating
expenses are estimated at $180,000. The required rate of return is
12 percent.
Required:
Estimate the annual cash flows and calculate the NPV. Ignore tax.
Example: Solution
Example: solution …
►Some basic points that
must be understood in
relation to NPV are
▪ Relevant cash flows
Some basic NPV ▪ Discounting
concepts ▪ Impact of inflation
▪ Impact of taxation
Relevant costs and
revenues
The IRR provides a decision rule for investment appraisal, but also provides
information about the riskiness of a project – i.e. the sensitivity of its returns.
The project will only continue to have a positive NPV whilst the firm’s cost of
capital is lower than the IRR.
Internal Rate of return
►The steps in linear interpolation are:
1. Calculate two NPVs for the project at two different costs of capital.
2. Use the following formula to find the IRR
𝑁𝐿
𝐼𝑅𝑅 = 𝐿 + 𝑥 (𝐻 − 𝐿)
𝑁𝐿 −𝑁𝐻
where:
L = Lower rate of interest.
H = Higher rate of interest.
NL = NPV at lower rate of interest.
NH = NPV at higher rate of interest.
3. Compare the IRR with the company’s cost of borrowing.
If the IRR is higher than the cost of capital, the project should be accepted
Interpretation
of IRR
► A project with a positive NPV at
14% but an IRR of 15% for
example, is clearly sensitive to:
i. an increase in the cost of
finance
ii. an increase in investors’
perception of the potential
risks
iii. any alteration to the estimates
used in the NPV appraisal.
Example
Exercise
The modified IRR
(MIRR)
• The assumptions. The IRR only represents the return from the project if
funds can be reinvested at the IRR for the duration of the project
• The decision rule is not always clear cut. If a project has 2 IRRs, it is difficult
to interpret the rule which says, "accept the project if the IRR is higher than
the cost of capital".
• Choosing between projects. Since projects can have multiple IRRs (or none
at all) it is difficult to usefully compare projects using IRR.
Payback period measures the length of time it takes for the cash
returns from a project to cover the initial investment.
The main problem with traditional payback period is that it does not
take account of the time value of money
Discounted payback period measures the The shorter the discounted payback period, the
more attractive the project is.
length of time before the discounted cash
returns from a project cover the initial A long-discounted payback period indicates that
the project is a high-risk project
investment.
Macaulay duration
►Duration measures the average time to recover the present value
of the project (if cash flows are discounted at the cost of capital).
►Duration captures both the time value of money and the whole of
the cash flows of a project.
►Projects with higher durations carry more risk than projects with
lower durations.
►payback, discounted payback and duration are three techniques
that measure the return to liquidity offered by a capital project
Macaulay duration
►Duration measures: either the average time
► to recover the initial investment (if discounted at the project’s
internal rate of return) of a project, or
► to recover the present value of the project (if discounted at the cost
of capital).
►Duration captures both the time value of money and the
whole of the cash flows of a project.
►It is also a measure which can be used across projects to
indicate when most of the project value will be captured.
Macaulay Duration Formula
Illustration – Macaulay duration
Test your
Understanding
Modified
Duration
► Macaulay Duration is the name given to the
weighted average time until cash flows are
received and it is measured in years.
► Modified Duration refers to the price sensitivity
and is the percentage change in price for a unit
change in yield.
► Macaulay Duration and Modified Duration differ
slightly, and there is a simple relationship
between the two (assuming that cash flows are
discounted annually), namely:
𝑀𝑎𝑐𝑎𝑢𝑙𝑎𝑦 𝐷𝑢𝑟𝑎𝑡𝑖𝑜𝑛
𝑀𝑜𝑑𝑖𝑓𝑖𝑒𝑑 𝐷𝑢𝑟𝑎𝑡𝑖𝑜𝑛 =
(1 + 𝑐𝑜𝑠𝑡 𝑜𝑓 𝑐𝑎𝑝𝑖𝑡𝑎𝑙)
Capital rationing
► Shareholder wealth is maximised if a
company undertakes all possible positive
NPV projects.
► Capital rationing is where there are
insufficient funds to do so.
► This shortage of funds may be for:
► a single period only – dealt with analysis by
calculating profitability indexes (PIs)
► PI = NPV/PV of capital invested more than one
period
► extending over a number of years or
even indefinitely.
Profitability Index
► When choosing between projects, what counts are the total dollars
earned—the absolute profits—not the relative profits.
► Accordingly, NPV, not IRR, should be used for choosing among
competing, mutually exclusive projects or competing projects when
capital funds are limited.
Net Present Value
for Mutually Exclusive Projects
►There are three steps in selecting the best project
(with the largest NPV) from several competing
projects:
►Step 1: Assess the cash flow pattern for each project.
►Step 2: Compute the NPV for each project.
►Step 3: Identify the project with the greatest NPV.
Mutually exclusive projects: Example
Example; Solution ….
Test Your
Understanding
Postaudit of Capital Projects
►A key element in the capital investment
process is a follow-up analysis of a capital
project once it is implemented.
►A post-audit compares the actual benefits with
the estimated benefits and actual operating
costs with estimated operating costs.
►It evaluates the overall outcome of the
investment and proposes corrective action if
needed.
Postaudit Benefits
►Firms that perform post-audits of capital projects
experience a number of benefits, including the
following:
►Resource Allocation: By evaluating profitability, post-audits
ensure that resources are used wisely.
►Positive Impact on Managers’ Behavior: If managers are
held accountable for the results of a capital investment
decision, they are more likely to make such decisions in the
best interests of the firm.
►Independent Perspective: Post-audit by an independent
party ensures more objective results.
THANK YOU