0% found this document useful (0 votes)
3 views

Weekly status THE NORTH FACE report - 10-08-2024

The weekly status report for the project dated 10-08-2024 outlines the project team, local authority inspections, and health and safety updates, noting no accidents this week. It details ongoing manpower and MEP works, including various tasks related to fire-fighting, HVAC, fire alarm, lighting, and small power installations, with many tasks still pending. The report also highlights upcoming civil works and MEP tasks planned for the following week.

Uploaded by

Mohammed Idris
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views

Weekly status THE NORTH FACE report - 10-08-2024

The weekly status report for the project dated 10-08-2024 outlines the project team, local authority inspections, and health and safety updates, noting no accidents this week. It details ongoing manpower and MEP works, including various tasks related to fire-fighting, HVAC, fire alarm, lighting, and small power installations, with many tasks still pending. The report also highlights upcoming civil works and MEP tasks planned for the following week.

Uploaded by

Mohammed Idris
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 10

THE NORTH

WEEKLY STATUS REPORT FACE

Date: 10-08-2024

Item 1.0 Project team

Project Mr. Zabiulla Khan (PM – Japan Interiors) [JI]


Team: Mr. Ashique Ibrahim (PE – Japan Interiors W.L.L) [JI]
Mr. Mohammed Idris (PE&C – Japan Interiors W.L.L) [JI]

Client:

Item 3.0 – Local authority/Utility inspection

SL no. DESCRIPTION ACTION

1.0

2.0

Item 4.0 – HSE

No accidents report this week.

1
Item 5.0 – Weekly Manpower

Supervisors – 4 No. s
Carpenters – 14 No. s
Painters – 8 No. s
Welder – 2 No. s
Electrician – 10 No. s
Plumbing and HVAC – 14 No. s
Helpers – 15 No. s
Mason – 3 no.s

Item 6.0 – Information and site works

MEP WORKS

WORK
PROGRESS
Scope of works 4 51 52

1 Fire-Fighting

a Sprinkler Pipe Fixing Not started Pending In progress.

b Sprinkler Pipe Not started Pending In progress.


Dropping

c Pipe Painting Not started Pending In progress.

d Zone Control Valve No started Pending In progress.


Installation

e FHR No started Pending In progress.

2
2 HVAC No started Pending In progress.

a VAV Relocation

b New VAV Installation

c Thermostats &
Controller

d FCU Units

e FCU Thermostats

f Ducting

g Chilled water pipe

h Chilled water Valves

i Chilled water insulation

3
j Air Terminals &
Dampers

k Sound Attenuators

3 Fire Alarm

a Ceiling cabling

b Cable Pulling from


other floors
c Installation of
detectors.

d Installation of void
detectors

e Installation of
Speakers

4 Lighting

a Lighting conduiting

b Lighting wiring &


cabling

4
c Sensor - LCP CAT6
cabling

d Installation of light
fixtures

e DB Modifications

5 Small Power (works


including cabling)

a Relocation of floor
boxes

b Installation of new
floor boxes

c Relocation of
switches

d Installation of
switches

e Relocation of
sockets

f Installation of
sockets

g Relocation of data
sockets

5
h Installation of data
sockets

i Relocation of
thermostats

j Installation of
thermostats

i FCU unit cabling

6 ELV (works including


cabling)

a Relocation of floor
boxes

b Installation of new
floor boxes

c Relocation of data
sockets

d Installation of data
sockets

e Installation of patch
cords

f Installation of patch
panels

6
j Fluke Testing &
Commissioning

i Wi-Fi

SITE PHOTOGRAPHS

7
Civil works -

 Gypsum partition works marking done, Partition working progress

 Gypsum ceiling marking done plan for next week.

 60x60 grid ceiling framing support work ongoing.

 Flooring works in progress.

8
 Rolling shutter marking done.

Item 7.0 – Building nominated vendors

Item 8.0 – One week look ahead

Civil works

 Complition of gypsum dry wall partition.


 Floor screed activity completion.
 Rolling shutter support work completion

MEP works

Item 10.0 – Drawing/Finishes

4th floor collab area TV panel cladding drawing.

52nd floor VIP lounge.

51st floor planter at collab area.

Item 11.0 – Procurement

Item 12.0 – Risks

Item 13.0 – Contract/documents

Item 14.0 – Financial

9
Item 15.0 – Variations

Item 16.0 – Quality

Item 17.0 – Next progress meeting

10

You might also like