Weekly status THE NORTH FACE report - 10-08-2024
Weekly status THE NORTH FACE report - 10-08-2024
Date: 10-08-2024
Client:
1.0
2.0
1
Item 5.0 – Weekly Manpower
Supervisors – 4 No. s
Carpenters – 14 No. s
Painters – 8 No. s
Welder – 2 No. s
Electrician – 10 No. s
Plumbing and HVAC – 14 No. s
Helpers – 15 No. s
Mason – 3 no.s
MEP WORKS
WORK
PROGRESS
Scope of works 4 51 52
1 Fire-Fighting
2
2 HVAC No started Pending In progress.
a VAV Relocation
c Thermostats &
Controller
d FCU Units
e FCU Thermostats
f Ducting
3
j Air Terminals &
Dampers
k Sound Attenuators
3 Fire Alarm
a Ceiling cabling
d Installation of void
detectors
e Installation of
Speakers
4 Lighting
a Lighting conduiting
4
c Sensor - LCP CAT6
cabling
d Installation of light
fixtures
e DB Modifications
a Relocation of floor
boxes
b Installation of new
floor boxes
c Relocation of
switches
d Installation of
switches
e Relocation of
sockets
f Installation of
sockets
g Relocation of data
sockets
5
h Installation of data
sockets
i Relocation of
thermostats
j Installation of
thermostats
a Relocation of floor
boxes
b Installation of new
floor boxes
c Relocation of data
sockets
d Installation of data
sockets
e Installation of patch
cords
f Installation of patch
panels
6
j Fluke Testing &
Commissioning
i Wi-Fi
SITE PHOTOGRAPHS
7
Civil works -
8
Rolling shutter marking done.
Civil works
MEP works
9
Item 15.0 – Variations
10