Yirgalem to Hawassa 230 kv line setting notes
Yirgalem to Hawassa 230 kv line setting notes
2 Relay Settings
since only three forward Zones are required settings on the relay can be performed in primary or secondary quantities
and impedance can be in polar or rectangular quantities (menu selectable)
for our case we use Secondary setting value and impedance rectangular since P443 can support rectangular(quad).
Since relay line angle setting is -900 to 900 in one degree steps , therefore select line angle the nearest round number.
Therefore setting line impedance and line angle is ZL = 12.22 58.00 deg
Page 1
2.1) Zone 1 Phase reach setting
Required zone 1 setting is to be 80% of the line impedance between C &E and KOKA substations.
Therefore :
required Z1 reach = 0.8*0.47 = 9.78 58.00 deg
Required zone 2 setting is to be the line impedance e of C&E -KOKA ss line plus 50% of the shortest
adjacent line impedance or can be set as 120 % of the line impedance if the transmision line is a radial system,
there fore :
Zone 2 phase reach impedance = (C&E -KOKA)ZL + 0.5*(ZL of KOKA -Wonji tap)
13.90 58.00 deg
Therefore taking grading time of 400 ms, the zone 2 time setting with 400 ms will have proper selectivity with the
remote end protection relays.
Z2 setting time : 400ms
therefore Z3 phase reach=( (NazeretC& E -koka )ZL + (ZL of koka -Yesu line))*1.25
Z3 phase reach = 45.44 58.00 deg
The zone 3 time delay must be set in order to grade with the time delay of zone 2 of remote substation
protection:-
We assume that the zone 2 time setting at of remote substation will have time delay 400 ms.
Therefore taking grading time of 400 ms, the zone 3 time setting with 800 ms will have proper selectivity with the
remote end protection relays zone 2 setting.
The zone 4 elements would typically provide back-up protection for the local busbar,
where the offset reach is set to 25% of the zone 1 reach of the relay for short lines
(<30km) or 10% of the zone 1 reach for long lines.
therefore :
Setting Zone 4 phase reach = 2.44 58.00 Ω deg in secondary value
Page 2
3 Residual compensation for earth Fault
The residual compensation factor can be applied for all zones because the transmission line impedance does not
change through sections. So for all zones the same KZO residual comp. And angle KZO angle will be applied.
Setting for Residual compensation Kz1, Kz2, Kz3and KZ4 = 0.55 14.00 Ω deg in secondary value
RPh >/= Ra
Where:
If = Minimum expected phase-phase fault current (A);
L = Maximum phase conductor spacing (m);
Ra = Arc resistance, calculated from the van Warrington formula .
taking the minimum expected phase to phase fault for the transmission line 2.21kA(from short c and maximum phase conductor
space for 132kv transmission line 2.5m we can calculate the arc resistance as follows:;
The maximum expected fault arc resistance for phase 1.36 Ω in secondary value
to phase faults is: Rarc-ph = 1.36 Ω in secondary value
The maximum phase fault resistive reach must be limited to avoid load encroachment trips.
Thus, R3Ph and other phase fault resistive reach settings must be set to avoid the heaviest
allowable loading on the feeder. where the worst case loading has been determined as point “Z”, calculated from:
Taking the maximum loading power of C&E -koka) transmission line 82MVA
considering overload conditions factor 120%.
Zload minimum = Zr 193.17 Ω in secondary value
Page 3
Considering the worst power factor = 0.5 angle becomes 60o
Resistive reach of start-up resistance limit for phase - phase faults:R lim-ph = 60% Zr = 0.6 x Zr
a) The phase - phase fault resistance limit for zone 3 and zone 4
Rarc-ph < R3 & 4 < minimum of (Rlim-ph, 10 x Z3, 80% Zr -∆R)
Rlim-ph = 115.90 Ω in secondary value
II) Calculation of maximum fault arc resistance for phase - ground faults:-
Resistive reach of start-up resistance limit for phase - ground faults:-
Rlim-g = 80% Zr = 154.54 Ω in secondary value
Typically, arc resistances are calculated using the van Warrington formula, which is:
Rarc-g = ( 28700*Lg/If-g1.4 )+ Rtower
Page 4
Lg = maximum length of insulator (m)
If-g = minimum phase to ground fault current (A) at remote end of the line
If-g= , which is the minimum phase - ground fault current at the remote end of the line provided by EEP/EEU
If-g = 2652 A
Rtower = 10 Ω
The maximum expected fault arc resistance for phase to ground faults is:Rarc-g 9.93 Ω secondary value
a) The phase - ground fault resistance limit for zone 3 and zone 4
Rarc-g < R3 & 4-g < minimum of (Rlim-g, 10 x Z3)
R2-g Resistive reach for ground fault setting = 123.63 Ω in secondary value
R1-g Resistive reach for ground fault setting = 97.78 Ω in secondary value
Page 5
Zone 1 extension scheme = disabled
Loss of Load(LOL)scheme = disabled
a) Aided scheme 1
Select : POR (Permissive Over Reach teleprotection scheme)
Select : 0 sec
d) Aided scheme 2
Select : Disable
e) Aided 2 DEF
Select : Enabled
Select : phase and ground
Aided scheme 1 DEF delay
Select : 0 sec
Switch-on-to-fault (SOFT) is provided for high speed clearance of any detected fault immediately
following manual closing of the circuit breaker.
a) SOFT selection
Select: Enabled
b) SOFT delay
c) SOFT tripping
Trip-on-reclose (TOR) is provided for high speed clearance of any detected immediately following
autoreclosue of the circuit breaker.
a) TOR selection
Select: Enabled
b) TOR tripping
Trip-on-close (TOC) is provided that the SOTF and TOR to remain in service for the duration of TOC
reset delay time once the line is energized.
Page 6
Line capacity base on limit of conductor = Imax = 430A
As the thermal limit of the conductor is limits the natural power of the line, we propose that the phase current
factor to be as below:
The threshold (I>) is set directional to see only the faults on the protected line.
Setting I>=
I> = 0.5 In *where In = rated current of the CT, 600A primary and 1A
secondary
Curve type: IEC S Inverse
we recommend TMS = 0.100 to improve selectivity with the zone 2 time setting of Distance relay of Remote end
substation and transformer back up protections tripping time.
High set overcurrent threshold must be set in order to respect selectivity requirement:- it must be higher than maximum through fault
current and the maximum inrush current of opposite substation
transformer. Considering the value of 3-phase short circuit current is not less than Iph-f =2 kA
The angular displacement quadrature connection in the relay (Ubc / Ia, Uca / Ib, Uab / Ic) is :-
φ C = 900
Angle setting =φ S = φ C - φ f = 90 - 60 = 30
o 0 o
During the VTs pick-up, I> element is forced to have non-directional operation.
VTS Block :- when the relevant bit is set to 0, the associated stage will revert to non-directional upon
Page 7
CT ratio factor 1200
Select : f f = - 60 deg (this is typical setting for solidly earthed transmission system
c) Polarization
During the VTs pick-up, IN> element is forced to have non-directional operation.
VTS Block :- when the relevant bit is set to 0, the associated stage will revert to non-directional upon operation
of the voltage transformer supervision.
In this application, stage IN>1, IN >2, IN >3 and IN >4 will revert to non-directional.
Select :-
IN > VNpol set = 3% of VN = 0.03 x 57.7 = 2 volt (typical setting is 1% to 4% of VN, where VN is phase to
ground voltage)
∆R = ∆X = 0.032 x ∆f x Zload-min
∆R = ∆X = 0.032 x ∆f x Zload-min
∆R =∆X = 30.91 Ω in secondary value
In case of power swing detection, the distance relay is blocked during 5 ms (settable value).
c) Unblocking (Removal) of Power swings to allow tripping for prolonged power swings:-
It is possible to limit the time for which blocking of any distance protection zones is applied. Power swing
Page 8
blocking is automatically removed after the unblocking delay with typical settings:-
PSB Unblocking :- Enabled
Unblocking delay : select td = 2 sec.
PSB reset delay: 200 ms
10 VOLTAGE PROTECTION
Setting : disabled
Ku = VT ratio = 132kv/0.1kv
The timer of the breaker failure is initiated by the protection internal trip order or by external
protection trip order (in this case a dedicated input of the MiCOM P443 must be used).
a) CB fail 1 setting
Page 9
I = 5 x In = 5A
VTS I>inhibit = 5A
e) Negative sequence current (I2) and zero sequence current (I0) threshold detection
f) CT Supervision (CTS)
WI Inhibit: Disable
13 SYNCHROCHEK FUNCTION
This function is set in order to get permissive order for CB autoreclosing order. The synchrocheck function is
used to enable the 3-phase autoreclosing.
Page 10