imultaneous Operations (SIMOPS) Safe Work Practice
imultaneous Operations (SIMOPS) Safe Work Practice
WORK
PRACTICE
SIMULTANEOUS
OPERATIONS (SIMOPS)
Acknowledgments
The American Institute of Chemical Engineers (AIChE) and the Center for Chemical Process Safety (CCPS) express their
appreciation and gratitude to all members of the Safe Work Practices Project Committee and their member companies for
their generous efforts and technical contributions to the development of the Safe Work Practices. The volunteer team of
authors and reviewers who developed this SWP are listed below.
Authors and Reviewers:
Brian Farrell CCPS Consultant
Andrew Bartlett Sphera
Rajender Dahiya AIG
Cheryl Grounds CCPS Consultant
Jerry Keezer Bostik
Aamish Junaid Khan ADNOC Gas Processing
Siva Menedi Petroleum Development Oman
Andrew Moulder Inter Pipeline Ltd.
The Center for Chemical Process Safety was established by the American Institute of Chemical Engineers in 1985 to
focus on the engineering and management practices to prevent and mitigate major incidents involving the release of
hazardous chemicals and hydrocarbons. CCPS is active worldwide through its comprehensive publishing program,
annual technical conference, research, and instructional material for undergraduate engineering education. For more
information about CCPS, please call (+1) 646-495-1371, email [email protected], or visit www.aiche.org/ccps
This document is made available for use with no legal obligation or assumptions. Corrections, updates, additions, suggestions,
AND recommendations should be sent to Dr. Anil Gokhale, Sr. Director CCPS at [email protected]. If you are reading this offline,
you may not be reading the latest version. Please check on the CCPS web site for the current release.
https://www.aiche.org/ccps/publications/safe-work-practices
Need/Call to Action....................................................................................................................... 3
Incidents............................................................................................................................. 27
DuPont Yerkes SIMOPS Incident.................................................................................... 27
Formosa Plastics SIMOPS Incident................................................................................ 28
Reference Materials.......................................................................................................... 29
Appendix 1.......................................................................................................................... 30
PERSONNEL INJURY
An improperly managed SIMOPS situation may increase the consequence or severity of a hazardous material release,
resulting in personnel exposure to the released material, with the following consequences.
g Exposure to a fire due to the release of ignited flammable materials resulting in smoke inhalation or burns.
g Exposure to an explosion due to a release of ignited flammable or explosive materials causing blunt force trauma.
g Exposure to corrosive materials (acid or caustic) causing chemical burns.
g Exposure to toxic materials.
g Exposure to hot or cold materials causing thermal burns.
ENVIRONMENTAL/COMMUNITY IMPACT
SIMOPS activities that cause a release of hazardous material have the potential to escalate into an incident with
environmental and/or community impacts. Such an incident has far-reaching consequences for organizational
reputation and may affect a facility’s “license to operate.” The extent of on-site and off-site consequences is related to
material properties such as flammability and toxicity, the quantity of released material and dispersion properties. These
potential consequences include:
g Chemical release to the neighboring community.
g Contamination of land, potable water, and underground aquifers.
g Declaration of a “Shelter in Place” by local authorities
g Media coverage of the incident.
New or increased
Communicate plan EXECUTE IDENTIFY ADVERSE
hazards resulting
to all teams. THE PLAN INTERACTIONS
from interaction?
g Mechanical failure
• Loss of containment of hazardous material
• Failure of Safety Critical Device
• Failure of Isolation
g Unintended interconnection of process equipment or piping
g Mixing of incompatible chemicals
g Loss of Utility or Stored Energy
• Electric
• Steam
• Instrument Air
g Fire or explosion in the facility
g Uncontrolled vehicular traffic
g Loss of means of communication
g Crews from diverse backgrounds that speak different languages
g Lack of, or unclear, communication between work teams
g Human Factors
• Fatigue
• Staffing Levels
• Complexity of Manual Procedures
• Skill sets and competency level of workers
g Adverse weather conditions
g Single means of emergency egress
g Work Permits and Work Orders that do not identify SIMOPS
g Use of unapproved equipment for SIMOPS activities
MOST
EFFECTIVE
Physically remove
ELIMINATION the hazard
Replace the
SUBSTITUTION hazard
LEAST
EFFECTIVE
Elimination – when the hazard is physically removed or eliminated – is the most effective way to control the SIMOPS
hazard. By moving one of the operations to take place on a different day or time, there is no longer a simultaneous
operation. For example, consider the Evergreen Packaging Paper Mill incident described above. The simultaneous
operations involved two separate contractor work crews engaged in two separate maintenance activities which
occurred in a single large unit operation. This SIMOPS situation could have been eliminated by separating the two
maintenance activities so that they took place on different days. In this way, the activities of one work crew could not
have adversely affected the other work crew. Alternatively, the Blastco crew could have performed the work during the
warmer day shift, eliminating the need to heat the resin with a heat gun in the upflow tower.
While Elimination is the most effective means of risk control, it is not always possible to eliminate a hazard. When it is
not possible to eliminate the hazard, consider substitution. In the Evergreen incident, if the Blastco crew had used resin
that hardened at a lower temperature, there would have been no need to use a heat gun, thereby removing the hazard
introduced by the heat gun.
A typical starting point for a SIMOPS HIRA is a compilation of the HIRAs that pertain to each of the individual SIMOPS
activities. A challenge when developing a SIMOPS HIRA starting from existing HIRAs is that the Risk Matrix inputs
(frequency and consequence) used in the original HIRAs may not apply for the SIMOPS HIRA. The potential adverse
interactions between SIMOPS activities may require changing either the frequency or consequence ratings for hazards
to different values. The SIMOPS HIRA should review and adjust the Risk Matrix inputs to arrive at a new Risk Rating
for existing hazards (those identified in the individual HIRAs) and for new hazards arising from SIMOPS. The new and
revised Risk Ratings can then be used to determine the adequacy of existing safeguards and/or the need for new or
improved safeguards to reduce risk to a tolerable level.
A partial list of additional safeguards and controls that may be necessary to control SIMOPS hazards is provided below.
g Controlling and restricting personnel access to areas where simultaneous activities are taking place
g Ensuring that ergonomic factors (such as small or cramped work areas, frequency of breaks) have been considered
and addressed
g Developing and implementing a communication plan so that all affected individuals and crews are kept informed as
the simultaneous activities proceed
g Adding a barrier between activities to maintain separation between work crews and their actions
g Installing additional isolation points using blinds, locked and tagged valves, or car seals
g Re-routing traffic flow within the facility during SIMOPS operations
g Ensuring alternate emergency egress and emergency response routes
g Removing inventory from equipment prior to overhead lifts
STEP 11 - AUDIT THE WORK PROCESS AND THE EXECUTION OF THE PLAN
The final step in the SIMOPS life cycle is to conduct an audit of the work process and the execution of the SIMOPS
plan to identify improvement opportunities. It is recommended that the audit be carried out by an independent party
not associated with the SIMOPS (e.g., the shift supervisor from another area of the facility). Participants should include
the SIMOPS Coordinator, and members of each work crew involved in the SIMOPS. Audit findings should be shared
with the facility management team and with the personnel who worked on the SIMOPS project. Further guidance and
recommended practices related to audits can be found in the CCPS book, Guidelines for Risk Based Process Safety [10].
The application of the SIMOPS HIRA process described in Steps 1 through 10 could have led to different outcomes for
the Wacker Chemical Release Incident and the Evergreen Paper Packaging Mill Hot Work Incident, as described next.
HIRA LEADER
Person with experience and expertise in Hazard Identification and Risk Analysis (HIRA) methods. Responsible for
leading the SIMOPS HIRA. This person is typically a Plant Process Engineer or Process Safety Engineer whose
responsibilities include:
g Working with the SIMOPS Coordinator to identify potential adverse interactions, hazards, and consequences arising
from SIMOPS.
g Identifying existing safeguards and developing new safeguards to manage the SIMOPS hazards.
g Leading the SIMOPS HIRA
g Obtaining required engineering and technical personnel to participate in the SIMOPS HIRA.
g Developing the SIMOPS plan to safely manage work activities related to the SIMOPS
g Participating in the SIMOPS audit.
AUDITOR
Person responsible for auditing the SIMOPS work process and the application of the SIMOPS Plan after the SIMOPS is
complete. This person should have experience in the audit process. Responsibilities include:
g Auditing the SIMOPS work process and execution of the SIMOPS Plan to find areas for improvement.
g Ensuring the SIMOPS Coordinator and members of every work crew participate in the audit.
g Writing an audit report and sharing the report with facility management and the SIMOPS Coordinator.
Figure 5: Photo of atmospheric storage tank following the explosion. The top of the tank was almost completely blown
off due to the explosion, as can be seen in the left side of the photo. [12]
CONSTRUCTION ACTIVITIES
BREACH OF CONTAINMENT
CRANE OPERATIONS OVER
MAINTENANCE INVOLVING
EQUIPMENT
DRILLING N 6 HOT WORK
Y Y Y Y Y Y Y
INTRUSIVE MAINTENANCE Y 3 3 3 Y 3 Y 3 3
NON-INTRUSIVE
Y Y Y 3 Y Y Y Y Y
MAINTENANCE
CONSTRUCTION Y Y Y Y Y Y Y Y
HOT WORK 10 3 3 3 Y 3 3 Y
HEAVY LIFTS N Y Y 3 Y Y Y Y
RADIOGRAPHY 3 3 3 3 3 N
COLD FLARING N N N
LPG LOADING Y Y N N Y Y N Y Y
Table A-1: Example SIMOPS Matrix 1. See Table A-2 for color coding and numerical coding.
NUMBER REQUIREMENT
Permitted subject to PTW, including all necessary risk assessments, certificates and emergency arrangements.
Consider whether the following are required or applicable:
g Area is Suitably lit, using zone approved light
g Breach of containment assessment, including PPE requirements
g Hot Work Permit
g Gas Testing
3
g Confined Space Entry Certificate
g Isolations in place
g Dropped Object Exclusion Zones
g Lifting plans
g Method Statement
g Access restrictions
6 If construction works are within 50m of drilling rig, Rig PTW system is to be followed.
Permitted subject to hot work PTW on well pads. No hot work on well head permitted unless fully isolated. Area
10
Classification requirements addressed by PTW.
Table A-2: Example SIMOPS Matrix 1. Color Coding and Numerical Coding.
LIFTING OPERATIONS
WORKING AT HEIGHT
MANUAL HANDLING
EXCAVATION WORK
HOT WORK
BREAK CONTAINMENT - HC * A P R R A R R P P P R A R P R R P P
BREAK CONTAINMENT - NON HC A * R R R A R R R R R R A R R R R R P
CONFINED SPACE ACTIVITY P R * A R A R R R R R R A R R R R R P
CRANE AND VEHICLE OPERATIONS R R A * R A R R R R R A A R R R R R P
EXCAVATION WORK R R R R * A R R R R R R A R R R R R P
GENERAL COLD WORK A A A A A * A A A A A A A A A A A A A
HANDLING HAZARDOUS SUBSTANCES R R R R R A * R R R R R R R R R R R R
HANDLING RADIOACTIVE SOURCE R R R R R A R * R R R R R R R R R R R
HOT WORK P R R R R A R R * R R R R R R R R R P
HYDRO AND ABRASIVE BLASTING P R R R R A R R R * R R R R R R R R R
LEAK AND PRESSURE TESTING P R R R R A R R R R * R R R R R R R R
LIFTING OPERATIONS R R R A R A R R R R R * R R R R R R R
MANUAL HANDLING A A A A A A R R R R R R * R R R R R R
NON STANDARD ISOLATIONS R R R R R A R R R R R R R * R R R R R
SPARK POTENTIAL WORK P R R R R A R R R R R R R R * R R R R
WORKING AT HEIGHT R R R R R A R R R R R R R R R * R R R
WORKING ON ELECTRICAL SYSTEMS R R R R R A R R R R R R R R R R * R R
WORKING ON SAFETY SYSTEMS P R R R R A R R R R R R R R R R R * R
WORK ON PRESSURIZED EQUIPMENT P P P P P A R R P R R R R R R R R R *
A ALLOWED: The two operations can be carried out simultaneously following completion of a SIMOPS HIRA.
RESTRICTED: The two operations can be carried out simultaneously following completion of a SIMOPS HIRA,
R
implementation of additional hazard controls, and approval by the Operations Manager.