Appendix B - Façade Projects
Appendix B - Façade Projects
Façade projects have a different inspection criterion related to the duties of the site
safety inspector. The primary or alternate site safety manager must perform the site
safety inspection per Table 10 whenever he or she is present onsite. At all times,
paragraph (1) of subdivision (e) of this section requires the presence of a qualified
person to do the inspection of Table 10 if the primary or alternative site safety manager
is not present.
Table 10
Façade project inspections
Minimum Schedule of
Requirement
Inspections
Prior to the commencement
Verify that the approved site safety plan is on
(1) of the project; and daily
site.
thereafter
Verify that required sidewalk sheds, fences,
pedestrian protection, roof and adjoining property Prior to the commencement
(2) protection, safety netting, guardrails, perimeter of the project; and daily
protection, and controlled access zones are in thereafter
accordance with the approved site safety plan.
Verify that all scaffolds, cranes, derricks, hoisting
machines, mast climbers, sidewalk sheds, and Prior to the commencement
fences possess a valid permit/certificate, and that of the project; as each
such information is recorded in the permit log. piece of equipment is
(3)
(Note: certain types of scaffolds and brought to the site; and at
cranes/derricks are exempt from permit/certificate the renewal or expiration of
requirements; see sections 3314.2 and 3319.3 of the permit/certificate
the building code for details.)
Verify that, where required, Department of
(4) Transportation permits for street or sidewalk Once per permit
closings are available at the site.
Verify that notice has been provided to the
(5) department prior to the installation or removal of Prior to each instance
a suspended scaffold or a mast climber.
Verify that plans for all scaffolds, cranes,
derricks, hoisting machines, mast climbers, Prior to the commencement
sidewalk sheds, and fences are available at the of the project; as each
(6) site. (Note: certain types of scaffolds and piece of equipment is
cranes/derricks are exempt from design brought to the site; and
requirements; see sections 3314.3 and 3319.3 of monthly thereafter
the building code for details.)
Verify that installation inspections have been
completed for all scaffolds, tower/climber cranes,
derricks, hoisting machines, mast climbers, and
sidewalk sheds, and that a record of such
inspection is available at the site. (Note, Following the installation of
(7)
installation inspections may also be required each piece of equipment
when equipment is moved to a new location at
the site, or when components are relocated - for
example, when decking and guardrails on a
supported scaffold are moved to a different level.)
Verify that daily/pre-shift inspections have been
completed for all scaffolds, cranes, derricks,
hoisting machines, mast climbers, and sidewalk
(8) sheds and that a record of such inspection is Daily
available at the site. (Note: certain types of
cranes do not require an inspection; see section
3319.3 of the building code for details.)
Verify that inspections have been completed
following an adjustment or repair to a scaffold, Following each adjustment
(9)
crane, derrick, hoisting machine, mast climber, or or repair
sidewalk shed.
Verify that the general contractor or sub-
contractors, as appropriate, are verifying that
workers have completed a course that is at least
ten hours in length and approved by the United
(10) Daily
States Department of Labor Occupational Safety
and Health Administration (OSHA) in construction
industry safety and health, or an equivalent
training, and that documentation of such
verification is maintained at the site by the
general contractor or sub-contractors.
Verify that the general contractor or sub-
contractors, as appropriate, are providing a site-
specific safety orientation to all workers
(11) Weekly
employed at the site, and that documentation of
such orientation is maintained at the site by the
general contractor or sub-contractors.
Verify that contractors engaged in scaffold, mast
climber, rigging, hoisting, or sign hanging work
are checking that individuals engaged in such
(12) work possess training, certification, or licensing Daily
for such work, as appropriate, and that
documentation of such check is maintained at the
site by the contractor.
Verify that flag persons are present to stop
(13) pedestrian and/or vehicular traffic during the Throughout the day
following intermittent operations:
(i) During all lifting and hoisting operations;
(ii) When trucks enter and exit the site;
(iii) When materials are being lifted over the
sidewalk shed;
(iv) When dangerous operations, e.g., blasting,
occur; and
(v) When the sidewalk and/or street is
temporarily closed.
Verify workers are provided with and are utilizing
(14) required personal protection equipment (PPE), Throughout the day
including but not limited to harness and life line.
Prior to the start of any
Verify that a means of communication exists
such hoisting operation;
between the responsible parties when the
(15) and throughout the day as
operator of hoisting machinery has no vision of
such hoisting operation is
the lift or loading areas.
ongoing
Prior to the commencement
Verify that all signs required by section 3301.9 of of the project; and upon the
(16) the building code are installed and contain the posting of any sign added
required information. after the commencement of
the project
Verify that scaffolds, sidewalk sheds, fences, and Prior to the commencement
(17) other pedestrian protection are free of signs or of the project; and daily
advertisements not directly related to the project. thereafter
Prior to the commencement
Verify that the standpipe system has passed its
of the project; and, if
most recent hydrostatic pressure test and flow
(18) applicable, when a new
test, and that the sprinkler system has passed its
hydrostatic pressure test
most recent hydrostatic pressure test.
and/or flow test is required.
Verify that where active work is occurring, where
project material/debris/equipment is being stored,
(19) Daily
and where sidewalk sheds, fences, or other
pedestrian protection is located:
(i) Standpipe valves/hose connections/fire
department connections are in place; and
(ii) Standpipe valves/hose connections/fire
department connections are free from
obstruction.
In areas where a sidewalk shed or fence has
been installed, verify that the required red light Prior to the commencement
(20) marking the fire department connection is of the project; and daily
functional and the required sign identifying the thereafter
fire department standpipe connection is visible.
If "hot works" (welding, grinding operations
Prior to start of any "hot
producing sparks, torch operations, etc.)
works" operations; and
operations are performed, verify that fire
(21) throughout the day as "hot
extinguishers and dedicated personnel with valid
works" operations are
FDNY fire watch certificate of fitness are on site
performed.
at the location of "hot works" operations.
Prior to the start of any
Verify compliance with the provisions of section welding operation from a
3314.11.5 of the building code when welding suspended scaffold; and
(22)
operations are conducted from a suspended throughout the day as
scaffold. welding operations occur
from a suspended scaffold
Verify that all flammable/combustible liquids and
gases are located in a well-ventilated area, away
(23) from combustible materials, and away from open Throughout the day
flame or sources of ignition in accordance with
the requirements of the fire department.
Verify that, where active work is occurring, where
(24) Throughout the day
project material/debris/equipment is being stored,
or where sidewalk sheds, fences, or other
pedestrian protection are located:
(i) Building egress is not obstructed;
(ii) Areas used by the public are maintained free
from ice, snow, grease, debris, equipment,
materials, projections, tools, hoses, wires, ropes,
or other items, substances, or conditions that
may constitute a slipping, tripping, or other
hazard; and
(iii) Guards, shields or barricades surround all
exposed, electrically charged, moving or
otherwise dangerous parts of machines and
equipment so as to prevent contact with the
public.
Prior to the commencement
(25) Verify that: of the project; and daily
thereafter
(i) Sidewalk shed lights are functioning;
(ii) No brace or rail is hanging unattached at one
or more ends of the sidewalk shed;
(iii) No portions of the sidewalk shed support
structure are disconnected;
(iv) No section of the sidewalk shed parapet is
missing; and
(v) All legs of the sidewalk shed remain on their
support and are supported to the ground.
Prior to the commencement
of the project; and upon the
Verify that contractor sheds and offices are in
installation of any contractor
(26) accordance with section 3303.16 of the building
shed added after the
code.
commencement of the
project
As new chutes are installed
Verify that chutes used for the removal of debris
at the site; as existing
(27) are installed and maintained in accordance with
chutes are relocated at the
section 3303.5.5 of the building code.
site; and weekly thereafter
Verify required safety netting is installed and in
(28) Daily
good repair.
Verify required guardrails and toeboards on
(29) Daily
exterior scaffolds are installed and in good repair.
Verify that sufficient containers for the storage of
(30) waste/debris generated by the project are Daily
provided, and that such containers are:
(i) Covered at the end of the shift;
(ii) Covered anytime when full to near the rim;
and
(iii) Wheels are secured at the end of the shift.
Verify that, at the end of the shift, all tools and
loose materials have been secured, and that all
waste/debris generated by the project, including
(31) but not limited to garbage/debris located on Daily, at the end of the shift
scaffolds, mast climbers, sidewalk sheds, roofs,
and setbacks, has been placed into containers or
removed from the site.
Verify that combustible waste/debris generated
(32) by the project is not allowed to accumulate and is Throughout the day
removed from the site.
Verify that tools and equipment not in use are
(33) Throughout the day
kept away from edges or openings.
Verify that materials placed/stored on a sidewalk
shed are placed/stored only in areas designated
on the sidewalk shed plans, and such materials
(34) Daily
are secured against dislodgement, and there is
no evidence of deflection or failure of the
sidewalk shed in the vicinity of the storage.
Verify that, at the end of the shift, suspended
scaffolds have been lowered to the street,
(35) sidewalk shed deck, or building setback, or have Daily, at the end of the shift
been otherwise secured to the roof or the building
in accordance with the scaffold plans.
The qualified person on the jobsite during a façade project has specific regulations for
the protection of the workers and general public. 3301.02 (e) as follows: