Kagawaran ng Edukasyon
REHIYON V
TANGGAPAN NG MGA PAARALAN PANSANGAY NG CAMARINES SUR
PUROK NG SILANGANG NABUA
PAARALANG ELEMENTARYA NG PACIFICO -112821
PROJECT PROPOSAL
School: PACIFICO ELEMENTARY SCHOOL Date: February 6, 2025
Municipality/District: NABUA EAST DISTRICT
Congressional: 5th
1.Project Title: 2.Schedule of 3.Proponent:
IMPROVEMENT OF REST ROOMS FOR Implementation: CHRISTOPHER R. HESITA
MALE, FEMALE & PWD February , 2024 School Head
4.Project Location:
Pacifico Elementary School, Nabua, Camarines Sur
5.Goals/Objectives:
7. Overview/Rationale:
DepEd Order No. 10, S. 2016: “All schools shall have adequate, clean, functional, safe, and accessible toilet
facilities that meet the pupil-to-bowl ratio as stipulated in the Philippine Sanitation Code; maintain cleanliness and
safety in and the immediate vicinity of school premises through school-based solid waste management, proper
drainage, and the elimination of all possible breeding grounds for mosquitoes to prevent vector-borne; and ensure
safety in food handling and preparation.”
Paloyon Oriental Elementary School, needs to construct a detached toilet for male, female and PWD to
provide the learners, teachers, parents, stakeholders and visitors a functional restroom. It will ensure that the school has
well-maintained facilities to respond to basic sanitation requirements, and practices are in-place to reduce threats from
life-threatening vector-, water-, and food-borne diseases.
-Liquidation
DESCRIPTION/SPECIFICATION OF ITEM/ARTICLE
ITEM DESCRIPTION/SPECIFICATION QUANTITY UNIT TOTAL
No. COST
(size, color, material, used, capacity,
measures, thickness, length, weight,
diameter, other specific details)
1 CRUSHED GRAVEL CU. M. 2 1,450.00 2,900.00
3 SAND CU. M. 3 900 2,700.00
4 CEMENT BAGS 30 230 6,900.00
5 CABILLA 10MM PCS. 15 155 2,325.00
6 CABILLA 9MM PCS. 15 130 1,950.00
7 TIE WIRE KILO 2 120 240.00
8 FAUCET PCS. PLASTIC 3 150 450.00
9 TOILET BOWL PCS. SMALL 3 1100 3,300.00
10 PVC PIPE BLUE 5 155 775
11 S BLUE CANS, SMALL 2 120 240
12 PVC 3”, BLACK 3 320 960
13 ELBOW 3x90 6 120 720
14 TILES 12 INCHES, WHITE 60 160 9600
14 HOLLOWBLOCKS PCS. 100 16 160
15 YERO METAL, 8FT. 6 600 3600
TOTAL AMOUNT OF MATERIALS: PHP. 38,260.00
LABOR COST (30%) 11,478.00
TOTAL Php. 49,738.00
12.Reporting and Evaluation:
Reporting, Inspection and Evaluation thru School Head School Inspection Team.
13. Enclosure:
1.Implementation Agreement -Pre-repair/to be attached to project/request
2.Project Locator Map -Pictures for ongoing and completed
3.Picture of the pathwalk -Picture together with the pre-repair
4.Perspective plans & Specs -Inspection pictures shall be attached
5. Program of Works -items, quantity and price
6. Others - liquidation documents.
ALLOCATION: ₱ 48,738.00
SOURCE OF FUND: CY 2024 MOOE FUND
MODE OF IMPLEMENTATION: By Administration
PROJECT DURATION: August - September, 2024
PHYSICAL TARGET: Restrooms
Bill of Materials:
DESCRIPTION UNIT UNIT COST TOTAL AMOUNT SOURCE OF FUND
CRUSHED GRAVEL CU. M. 1,450.00 2,900.00
SAND CU. M. 900 2,700.00
CEMENT BAGS 230 6,900.00
CABILLA 10MM PCS. 155 2,325.00 CY 2024 MOOE
CABILLA 9MM PCS. 130 1,950.00 FUND
TIE WIRE KILO 120 240.00
FAUCET PCS. PLASTIC 150 450.00
TOILET BOWL PCS. SMALL 1100 3,300.00
PVC PIPE BLUE 155 775
S BLUE CANS, SMALL 120 240
PVC 3”, BLACK 320 960
ELBOW 3x90 120 720
TILES 12 INCH, WHITE 160 9600
HOLLOWBLOCKS PCS. 16 160
YERO METAL, 8FT. 600 3600
TOTAL AMOUNT OF MATERIALS: PHP. 38,260.00
LABOR COST (30%) 11,478.00
TOTAL: Php. 49,738.00
Checked by:
ENGR. JONATHAN D. NAVARO
Division Technical Property
Approved:
CHRISTOPHER R. HESITA
Head Teacher II
Concurred:
ENGR. VIRGELIO B. BANCASO
Engineer III / Educ. Facilities Section
Republika ng Pilipinas
Kagawaran ng Edukasyon
REHIYON V
TANGGAPAN NG MGA PAARALAN PANSANGAY NG CAMARINES SUR
PUROK NG SILANGANG NABUA
PAARALANG ELEMENTARYA NG PACIFICO -112821
PROGRAM OF WORKS
Checked by:
JONATHAN D. NAVARO
Division Technical Property
Approved:
CHRISTOPHER R. HESITA
Head Teacher II
Concurred:
Prepared by:
Concurred:
PRE-INSPECTION
Findings:
POST-REPAIR INSPECTION
Findings:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________.