Higher Nationals in
Engineering / Aeronautical Engineering /
Nuclear Engineering / Rail Engineering /
Manufacturing Operations
PEARSON-SET ASSIGNMENT GUIDANCE
UNIT: 4 Managing a Professional Engineering Project
(Pearson-set)
For use with the following qualifications:
Pearson BTEC Level 4 Higher National Certificate in Engineering
Pearson BTEC Level 4 Higher National Certificate in Aeronautical Engineering
Pearson BTEC Level 4 Higher National Certificate in Nuclear Engineering
Pearson BTEC Level 4 Higher National Certificate in Rail Engineering
Pearson BTEC Level 4 Higher National Certificate in Manufacturing Operations
First teaching from September 2017
Issue 3
Edexcel, BTEC and LCCI qualifications
Edexcel, BTEC and LCCI qualifications are awarded by Pearson, the UK’s largest awarding body offering academic
and vocational qualifications that are globally recognised and benchmarked. For further information, please visit
our qualification websites at www.edexcel.com, www.btec.co.uk or www.lcci.org.uk. Alternatively, you can get in
touch with us using the details on our contact us page at qualifications. pearson.com/contactus
About Pearson
Pearson is the world’s leading learning company, with 40,000 employees in more than 70 countries working to
help people of all ages to make measurable progress in their lives through learning. We put the student at the
centre of everything we do, because wherever learning flourishes, so do people. Find out more about how we
can help you and your learners at qualifications.pearson.com
References to third-party material made in this specification are made in good faith. We do not endorse, approve
or accept responsibility for the content of materials, which may be subject to change, or any opinions expressed
therein. (Material may include textbooks, journals, magazines and other publications and websites.) All
information in this document is correct at time of publication. All the material in this publication is copyright ©
Pearson Education Limited 2019
• teaching of, or seminars on, project management and/or subject specific skills delivered by
external experts.
• teaching of, or seminars on, project management theory and practice and/or subject specific
skills delivered by external experts.
Please note that there is a suggested scheme of work for this unit available within HN Global at
www.highernationals.com.
At each milestone, the tutor liaises with the student to check whether it has been achieved. They may
need to redirect the student if necessary.
Authentication of a project
Centres are to provide confirmation of the authenticity of a project. It is important that students are
made aware of the issue of plagiarism. Students are required to sign a declaration stating that the
work they are submitting is their own.
• Project briefs for this unit must be based on a theme and topic chosen from a selection
released by Pearson in the first week of March of every year. You will select the topic from the
selection made available by Pearson.
• The topic and type of project chosen must be appropriate for small-scale research. The project
must balance the duration of time committed to delivering input to support student's research
and the time necessary to conduct the project.
• The project topic and type of project should be verified by the Programme Leader as part of the
internal verification process.
• Group work is not appropriate for this project. Student work must be individual.
• Teaching delivery must include how the student should go about planning, researching,
conducting, recording and reflecting on the project.
• It is good practice for your scheme of work to include individual student support appointments
to support and monitor completion of the project, and project workshops to give students the
opportunity to complete each stage of the project.
• Encourage students to keep notes of their progress, as this will be required as evidence. A
logbook is recommended.
• Students will need to reflect on the success of their project and their own performance in a
personal performance review at the end of the project. This is a written reflection of 500 words
(students will not be penalised if they exceed this word limit). It is advisable to provide students
with an appropriate structure for this reflection (see the Performance Review template below).
• The project could take the following forms but these are not exclusive:
Types Examples
Research projects
• Professional engineering
research report
• Industrial/commercial fieldwork
investigation
• Implementation of Planned
Preventative Maintenance
system (PPM)
Environmental Awareness
• Product lifecycle assessment
Name:
Project title:
Date:
Points to consider:
• What have you completed?
• Did you need to make any changes to your project management plan?
Points to consider:
• Did you identify risks/issues with a lack of skills required for undertaking
research/tasks?
• Did you identify any additional risks/issues that have an impact on the project
management plan?
Problems encountered
Points to consider:
• What barriers did you face?
Points to consider:
• How did you feel when you had to deal with tasks/problems?
Points to consider:
• Which tasks are a priority?
• Did the project succeed in its aims? How do you know? Specifically, please outline any
evaluation and assessment undertaken.
• What things do you think worked well and why? Evaluate all aspects of the project (e.g.
initial inception, project activities and project outcomes) from a range of perspectives.
• What problems emerged during the project and how were they tackled? Was there
timely identification of issues and resolution during the project process?
• How will this inform and support your continuous professional engineering
development?
• Your centre will set a project brief based on the topic and theme released by Pearson in the first
week of March of every year.
• Read the brief and think about what the project brief is asking.
• Research what the project brief is asking. How can you approach the problem, opportunity,
hypothesis and requirements being posed?
• Apply a range of secondary research sources to plan/scope and support the project and its
findings. Secondary research sources may include textbooks, journal articles, newspapers and
magazine articles (not factual accounts).
• Develop your project plan based on the deliverables of the project, the constraints of the
project and the assumptions made.
• Conduct your project according to your stated project plan and meet with your tutor to receive
a sign-off at each stage of the project process.
• Primary research sources may include original first-hand accounts, legal and historical
documents, results of experiments and research data collection. Apply both qualitative and
quantitative research methods to evaluate data collected from primary research.
• Keep notes of your progress throughout the project. It is important to keep a record of your
work, which must be used to record the development of your ideas and your progress through
the project. For example, a logbook could be used and include:
o A record of what you did, when and what you were thinking.
o A record of where things went wrong and what you did to overcome any unexpected
results.
• You will be asked to reflect on the success of your project and your own performance in a
personal performance review at the end of the project. This is a written reflection of around 500
words.
• Produce an appropriate project management plan that includes relevant actions to meet
objectives and timeframes.
• Conduct research to generate knowledge which will form the basis for analysis of the scenario
posed in the brief.
• Analyse your findings and draw conclusions to form the basis for recommendations.
• Present and produce your project in an appropriate manner for the intended audience.
o The success of the project and its effectiveness in addressing the issues identified in the
Pearson-set theme and topic.
LO2 Conduct planned project activities to generate outcomes D2 Critically evaluate the
which provide a solution to the identified engineering problem success of the project plan
making recommendations for
P3 Conduct project activities, M2 Explore alternative methods improvements
recording progress against to monitor and meet project
original project plan. milestones, justify selection of
chosen method(s).