QS English Part 2
QS English Part 2
Quantity Surveying
NCT Equivalence Examination
INSTRUCTIONS
01. This paper consist five (05) questions.
02. Each question has part A and Part B.
03. Answer only one part of each question.
You are required to select the most appropriate foundation material for a foundation of a cottage.
Random Rubble Masonry (RRM) and Grade 25 concrete were proposed as foundation materials.
Data & Outputs for a Cube of 14” thk. RRM in cement : Sand mortar 1:5.
6”-9” Rubble 1.30 cubes for the rate of Rs.6500.00 per 1 Cu.
5.25 Cement bags for the rate of Rs.950.00 per 1 Bag.
0.30 cubes of Sand for the rate of Rs. 13500.00 per 1 Cu.
100 gals of water for the rate of Rs.5.00 per 1 Gal.
4 days of Masons to construct the foundation for the rate of Rs.2000.00 per day
2 U/sk labourers to manual mixing of mortar for rate of Rs.2000.00 per day
2 U/sk labourers to supply mortar
2 U/sk labourers to transport rubble to the place.
Page 1 of 5
1/3 skilled labour to lay concrete for the rate of Rs.2000.00 per day.
1 U/sk labourers to transport concrete for rate of Rs.1500.00 per day
0.5 U/sk labourers for transport materials.
0.5 U/sk labourers for curing.
20 % of Overheads & profits
1.0 Part A
i. Select the most suitable material in cost aspects for the foundation using the given data.
(12 Marks)
ii. Advice your client regarding your decision. (2 Marks)
iii. The super structure of this construction project decided to construct in Grade25 concrete. A
part of the BOQ is mentioned below. Calculate total material, labour and plant cost for the
item. (6 Marks)
1.0 Part B
You are required to select the most appropriate wall material for a construction of a house.
Engineering bricks and Concrete blocks were proposed as wall materials.
i. Select the most suitable material in cost aspects for the walls using the given data.
Data & Outputs for a Sqr. (100ft2) 225mm Thick Brick wall in Cement & Sand 1:5
Page 2 of 5
Small tools -3%
20 % of Overheads & profits
Data & Outputs for a Sqr. (100ft2) of 200mm thick hollow block work in cement &
sand mortar 1:5
2.0 Part A
RIBA plan of work provides a logical and systematic way to identify the essential steps that
necessary for the successful completion of a project. Feasibility, Outline proposals and scheme
design are three main stages in RIBA plan of work.
i. Explain the major activities that have to be carried out by the quantity surveyor in each
of the three stages. (14 Marks)
There is a close collaboration between pre contract cost planning and RIBA plan of work.
ii. Mention the phases of pre contract cost planning process. (6 Marks)
Page 3 of 5
2.0 Part B
Bills of Quantities (BOQ) are a document which provides the project specified measured quantities
of the items of work identified by the drawings and specifications.
3.0 Part A
Aggregates are those chemically inert materials, which when bonded by cement paste from
concrete.
i. Write down the short note for the fine aggregate and coarse aggregate. (4 Marks)
ii. What is the test done for the aggregate to measure good quality characteristic? And write
down brief note for Concrete Admixtures. (4 Marks)
iii. Write down advantages and disadvantages of concrete. (6 Marks)
iv. You are the responsible person for concrete work at the site. According to work program
you have to concrete work at ground floor. What are the basic procedures to success your
concrete work at ground floor? (6 Marks)
3.0 Part B
i. What are the tests used in cement and concrete? (4 Marks)
ii. Explain how to find initial setting time and final setting time of cement (2 Marks)
iii. What is the minimum initial setting time of cement according to BS 12 standard?
(2 Marks)
iv. Sketch the stress-strain curve of concrete in compression test. (2 Marks)
v. Is concrete strong in tension and compression? (2 Marks)
vi. How the weakness in tension capacity of concrete beam is improved? (2 Marks)
vii. What is the workability of concrete and how to measure it in the field? (2 Marks)
viii. What is C25 concrete? (2 Marks)
Page 4 of 5
ix. Why we use 28 days cube strength to define concrete strength and what are the size of
concrete test cube & cylinder? (2 Marks)
4.0 Part A
You are the procurement specialist in Ad Value Consultants Private Limited. One of your clients
wants to construct 18 floors shopping complex in Polonnaruwa area. Design is not much complex
and has a typical floor plan in 12 number of floors.
i. As the first step, you have to select the most appropriate procurement method for the
construction. What is the most suitable procurement method for the project? Justify your
answer giving reasons/assumptions for your opinion. (10 Marks)
ii. After the procurement selection a suitable contractor has to be selected to carry out the
project. Explain the tendering process that has to be followed. (10 Marks)
4.0 Part B
i. What is a tender? (5 marks)
ii. Is an Invitation to Tender published in a newspaper can be considered as an offer? explain
(5 marks)
iii. List out content of bidding documents and explain any document out of them. (10 marks)
5.0 Part A
5.0 Part B
Page 5 of 5