AP Trans_Power Q
AP Trans_Power Q
It is necessary and important that all the technical (as per standards) and
regulatory requirements are invariably met before synchronization of the plant. This
will avoid disturbances in grid & connected equipment.
In view of the above, to have uniformity & grid safety, a procedure was
evolved from the regulations & other standard practices.
There are some aspects which are to be verified after synchronization viz.,
measurement of total harmonic distortion, DC injection, flicker etc. as per the
regulations & standards. These can be called as post synchronization tests.
Page 2 of 9
v. Generator transformers
vi. Auxiliary transformers
vii. Inverter Transformers
viii. Compatibility to LVRT, HVRT (in case of wind generators)
ix. Weather monitoring system
e) Certificate/Document related to the equipment /components
conforming to the relevant minimal technical requirements/standards
published by MNRE, Bureau of Indian Standards (IS) or International
Electro technical Commission (IEC), the Indian Electricity Grid
Code/State Electricity Grid Code whichever is in force and the
specifications of APTRANSCO / APDISCOM wherever applicable.
j) The factory acceptance and routine accuracy tests of all the metering
equipment at the manufacturer premises.
k) The certificates of metering CTs, PTs and energy meters for their
accuracy tested at NABL accredited lab.
The developer shall approach the APSLDC for getting permission for
synchronization of their plant with grid after statutory inspection. The
following documents are to be submitted by the developer to APSLDC.
a) After getting the request from the project developer, the APSLDC shall
verify the statutory inspection reports and requirements as per the
regulations if any, and issue the synchronization permission within 3
working days.
Page 5 of 9
b) The coordinator for the synchronization process will be DE/OP/DISCOM,
if the generator is connected to substations of DISCOM and
DE/O&M/TRANSCO, if the generator is connected to substations of
TRANSCO.
c) It is to be ensured that the plant is synchronized with grid during the day
time only (in case of solar plants).
Duration of the
Sl.No Description
measurement
Solar plants connected at 33 KV and 6 hours (During the
1
below voltage level generation period)
Wind plants connected at 33 kV and
2 2 Days (Continuously)
below voltage level
Solar plants connected at EHT level 2 Days (During the
3
with or without pooling station generation period)
Wind power plants connected at EHT
4 7 Days (Continuously)
level with or without pooling station
Page 6 of 9
2) The specified limits for total harmonic distortion, DC injection, flicker as per
regulations/standards are as follows.
a. Harmonic current injections from a generating station shall not exceed the
limits specified in IEEE Standard 519.
99th percentile very short time (3 second) values should be less than 1.5 times
the values given in Table below.
95th percentile short time (10 minute) values should be less than the values
given in Table below.
99th percentile very short time (3 second) harmonic currents should be less
than 2.0 times the values given in Table below.
99th percentile short time (10 minute) harmonic currents should be less than
1.5 times the values given in Table below.
95th percentile short time (10 minute) harmonic currents should be less than
the values given in Table below.
b. The Generator shall not inject DC current greater than 0.5% of the full rated
output at the interconnection point.
Page 7 of 9
c. The Generating station shall not introduce flicker beyond the limits specified
in IEC61000.
95th percentile Pst values and all Plt values should be less than the values
given in Table below.
MV HV (35kV<HV<230kV)
(1kV<MV<35kV) &EHV( >230 kV)
Pst 0.9 0.8
Plt 0.7 0.6
4) These orders are issued as per the note approved by the Chairman and Managing
Director on 23.02.2017.
5) These orders are also available on APTRANSCO website and can be accessed at
the address http://www.aptransco.gov.in.
(BY ORDER AND IN THE NAME OF
TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED)
Sd/-
S.Subramanyam
Director/Projects
To
The Executive Director/Planning & HRD / APTransco/VS/Hyderabad
The Chief Engineer/Transmission/ APTransco /VS/Hyderabad
The Chief Engineer/Zone/Visakhapatnam/APTransco
The Chief Engineer/Zone/Vijayawada/APTransco
The Chief Engineer/Zone/Kadapa/APTransco
The Chief Engineer/IPC &Power Systems/APTransco /VS/Hyderabad
The Chief Engineer/SLDC/APTransco /VS/Hyderabad
The Chief Engineer/Construction/ APTransco /VS/Hyderabad
The Chief Engineer/LIS/APTransco /VS/Hyderabad
The Chief Engineer/400 KV Construction/ APTRANSCO /VS/Hyderabad
The Chief Engineer/Commercial/APPCC/VS/Hyderabad
The Chief Engineer/Telecom& IT/ APTRANSCO /VS/Hyderabad – with a
request to place the T.O.O on APTRANSCO website.
Page 8 of 9
Central Record Section and stock file
T.O.O Section.
Copy communicated to
The Director /Projects/APTRANSCO/ VS/ Hyderabad
The Director/ Operation& Projects/ APEPDCL/ Visakhapatnam
The Director/ HRD & Technical/ APSPDCL/ Tirupati
Copy to:
PS to The Chairman & Managing Director/ APTRANSCO/ VS/ Hyderabad
PS to The Chairman & Managing Director/ APEPDCL/ Visakhapatnam
PS to The Chairman & Managing Director/ APSPDCL/ Tirupati
PS to The Joint Managing Director / V&S / APTRANSCO / Hyderabad
PS to The Joint Managing Director / Fin., Comml., IPC, HRD& IT/APTRANSCO/
Hyderabad
//FORWARDED BY ORDER//
Page 9 of 9
ANNEXURE - II (SOLAR)
I DEVELOPER/OWNER/COMPANY DETAILS
a Address
b Ph No
c Fax No
d E Mail Id
2 Nodal Person details:
a Name
b Address
c Ph No
d Fax No
e E Mail Id
3 Physical Location of the Solar Poewer Park
a Village
b Mandal
c District
4 GPS Cordinates of Solar Park: 4 Corners
a 1 st Corner Lat
b Lon
c 2nd Corner Lat
d Lon
e 3rd Corner Lat
f Lon
g 4th Corner Lat
h Lon
5 GPS Cordinates of Solar Park: Centre
a Lat
b Long
II CAPACITY DETAILS
a DC capacity of Solar Panels:
Cell & Panel Details:
i Each Cell Voltage (V)
ii No. cells in a Panel
iii Connection combination of Panels
iv Panel Voltage(V)
v No.of panels in a Array
vi Array Voltage (V)
Vii Nos. of solar panel
viii Capacity of each panel (KWp)
ix Total Capacity(KWp)
b AC Capacity
i No of Arrays connected to each inverter
ii Inverter input voltage
iii Inverter output voltage
iv No of Inverters
v Capacity of each Inverter(KW)
vi Total Capacity of the Inverters(KW)
c Inverter Transformer Details
i No of Inverter Transformers
ii No. of inverters connected to each transformer
iii Capacity of each Tr(MVA)
iv Total Capacity of the Inverter Trs(MVA)
v Input Voltage(KV)
vi Out put Voltage(KV)
vii Make of Inverter Trs
IV APPROVALS
a From NREDCAP/Govt.
i Total extent of land in acres
Capacity Approval from NREDCAP/GoAP to set up Plant(
ii Attach copy) in MW
Connectivity permission from STU/Discom( indicate
iii name of the Discom)
Total Evacuation permission Accorded in MW ( Attach
iii Copy)
b Name of the pooling Station
i GPS coordinates:
ii Lat
iii Long
iv No of Transformers
v Capacity of each Tr in MVA
vi Voltage rating
vii Make of Trs
c Connected Grid SS
i GPS coordinates
ii Lat
iii Long
iv Lines from PS to Grid SS
v Voltage Level
vi No of Ckts
vii Length
vii Conductor Used
V CONNECTIVITY PROVISIONS
i Connection Agt
ii Site Common Drg
iii Site Responsibility Schedule
iv ABT Meters: Main, Check, Stand By
v SVC/STATCOM
vi AMRs
VI SCADA
Availability of SCADA to transmit the Power system
i
parameters from the PS to SLDC in real time
18 AMRs
If RTU/comms or SCADA connectivity not
19 availble at present, time frame of its avilability
**
If no Connectivity to SLDC SCADA then
provide SLD of PCC, nearest comm. Node for
20
PCC, line connectivity with PCC and intended
comm. Media
Voice & data communication, Transfer of on
line operational data such as Voltage,
21 Frequency,Line FlowsStatus of Breaker and
Isolator position other parameters as specified
by appropriate LD.
II Individual Genarators details
WTG1 WTG2 ..
1 Name of the Generator:
2 Contact Person name:
3 Address,, Ph nos, Fax No E mail ID
4 WTG Location No & GPS Co ordinates:
5 Village, Mandal, District:
connected Line from the WTG to PS
Voltage Level
Conductor used
6
No of Lines
Name of the Line if any
Indicate the WTG s connected to each line
III Generator Static Data
1 Type
2 Manufacturer
3 Year of Mfg.
4 Make
5 Model
6 Sl No
7 Capacity in MW
8 commissioned date
9 Hub height in m
10 total height in M
11 RPM range
12 Rated wind speed m/s
13 Performance Parameter
14 Rated electrical power at Rated wind speed :
15 Cut in speed
16 Cut out Speed
17 Survival speed (Max wind speed)
18 Ambient temperature for out of operation
19 Ambient temperature for in operation
20 survival temperature
21 Low Voltage Ride Through (LVRT) setting
22 High Voltage Ride Through (HVRT) setting
23 lightning strength (KA & in coulombs)
24 Noise power level (db)
25 Rotor
26 Stall/Pitch control
27 Hub type
28 Rotor diameter
29 Number of blades
30 Blade Length in M
31 Area swept by blades
32 Rated rotational speed
33 Rotational Direction
34 Coning angle
35 Tilting angle
36 Design tip speed ratio
37 Blade
38 Length
39 Diameter
40 Material
41 Twist angle
42 Generator
43 Generator Type
44 Generator no of poles
45 Generator speed
46 Winding type y
47 Rated Gen. Voltage
48 Rated Gen. frequency
49 Generator current
50 Rated Temperature of generator
51 Generator cooling
52 Generator power factor
53 KW/MW @ Rated Wind speed
54 KW/MW @ peak continuous
55 Frequency Converter
56 Filter generator side
57 Filter grid side
58 Transformer
59 Transformer capacity
60 Transformer cooling type
61 Voltage
62 Winding configuration
63 Weight
64 Rotor weight
65 Nacelle weight
66 Tower weight
67 Over speed Protection
68 Design Life
69 Design Standard
70 Latitude
71 Longitude
72 COD Details
Past Generation History from the COD to the
73 date on which DAS facility provided at RLDC,
if applicable
74 Distance above mean sea level
IV Generator Protection LVRT
LVRT Availability (LVRT Feature
available/LVRT Not Possible/LVRT feature
1
avilable to be enabled/LVRT Design supported
but to be fitted/LVRT feature to be retrofitted)
2 LVRT Settings as per CEA Regn
3 LVRT Setting adopted(Enclose Test Certificate)
4 Useful life of the WTG beyond 04.01.2021
5 WTGS with useful life up to 04.01.2018
V Real-time Data Telemetry requirement (Suggested List)
SCADA:
1 Description of Wind Generation Data
Communication between Field and SLDC
2 Turbine Generation (MW)
3 Wind Speed
4 Turbine Availability Status
5 Generator Status (on/off-line)
6 Nacelle Position (relative to true north)
7 Wind Direction (relative to true north)
8 Yaw Error
9 Rotor RPM
10 Blade Pitch
11 Voltage
12 Ambient.air temperature
13 Barometric pressure
14 Relative humidity
15 Air Density
16 MW,MVAR,V
17 Power System Parameters
VI Generator Test Certificates
Approved Test Reports
1 Type test certificated
2 FAT certificates
3 Precommissioning test certificates
4 Test reports of Harmonic Current Injection
5 Test reports of DC current Injection
6 Test reports of Flicker
VII CEA connectivity Regn Provisions
Devloper/Generator
ANNEXURE - III (WIND & SOLAR)
7 Whether any PPA has been signed: (Y/N) If yes ,then attach details
58 14:15 14:30
59 14:30 14:45
60 14:45 15:00
61 15:00 15:15
62 15:15 15:30
63 15:30 15:45
64 15:45 16:00
65 16:00 16:15
66 16:15 16:30
67 16:30 16:45
68 16:45 17:00
69 17:00 17:15
70 17:15 17:30
71 17:30 17:45
72 17:45 18:00
73 18:00 18:15
74 18:15 18:30
75 18:30 18:45
76 18:45 19:00
77 19:00 19:15
78 19:15 19:30
79 19:30 19:45
80 19:45 20:00
81 20:00 20:15
82 20:15 20:30
83 20:30 20:45
84 20:45 21:00
85 21:00 21:15
86 21:15 21:30
87 21:30 21:45
88 21:45 22:00
89 22:00 22:15
90 22:15 22:30
91 22:30 22:45
92 22:45 23:00
93 23:00 23:15
94 23:15 23:30
95 23:30 23:45
96 23:45 24:00:00
Co-ordinating Agency/Generator
Contact Person
Mobile No
Ph No
Fax No
Email ID