AP Trans_Power Q

The document outlines uniform procedures for the synchronization of wind and solar power projects with the grid in Andhra Pradesh, emphasizing the importance of adhering to technical and regulatory standards to ensure grid safety. It details the four stages of synchronization, including statutory inspections, obtaining permissions from APSLDC, and conducting post-synchronization tests. Additionally, it specifies the necessary documentation and compliance checks required at each stage to maintain operational integrity and regulatory compliance.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views

AP Trans_Power Q

The document outlines uniform procedures for the synchronization of wind and solar power projects with the grid in Andhra Pradesh, emphasizing the importance of adhering to technical and regulatory standards to ensure grid safety. It details the four stages of synchronization, including statutory inspections, obtaining permissions from APSLDC, and conducting post-synchronization tests. Additionally, it specifies the necessary documentation and compliance checks required at each stage to maintain operational integrity and regulatory compliance.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 24

TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED

VIDYUT SOUDHA :: HYDERABAD-82.


APTRANSCO – Synchronization of wind and solar power projects (under PPA and
Open Access) with grid – Uniform procedures to be followed in APDISCOMs and
APTRANSCO – Instructions accorded – Regarding.
-----------------------------------------------------------------------------------------------------
T.O.O. (ED/HRD&Plg/APTransco) Ms.No.406 Dated: 06.03.2017

Read the following:

It is observed that uniform procedure is not being followed during the


synchronization of wind and solar power plants with reference to the regulations and
other standards.

It is necessary and important that all the technical (as per standards) and
regulatory requirements are invariably met before synchronization of the plant. This
will avoid disturbances in grid & connected equipment.

In view of the above, to have uniformity & grid safety, a procedure was
evolved from the regulations & other standard practices.

Synchronization of the project is divided in to four stages as given below.

i. Statutory Inspection of the power plant.


ii. Approaching the APSLDC by the project developer for getting
permission for synchronization.
iii. Issue of synchronization permission by APSLDC.
iv. Actual process of synchronization of the generator with grid which will
be supervised by a team of officers.

There are some aspects which are to be verified after synchronization viz.,
measurement of total harmonic distortion, DC injection, flicker etc. as per the
regulations & standards. These can be called as post synchronization tests.

1) The procedure to be followed during pre-synchronization, during synchronization


& post synchronization are given below.

A) Statutory inspection of the power plant:

The project developer has to approach the concerned CGMs of DISCOMs


(Generators connected to Discom SS) or CEs/Zone of TRANSCO
(Generators connected to Transco SS) for statutory inspection when the
project is ready for synchronization.
Page 1 of 9
Accordingly the CGM/DISCOM or CE/Zone/APTRANSCO shall give
instructions to their concerned officers, within 2 days from the date of
receipt of request from developers.

If the generator is connected to substations of DISCOM,


DE/M&P/DISCOM in coordination with DE/MRT/TRANSCO shall
inspect the project &issue the statutory inspection report.

If the generator is connected to substations of TRANSCO,


DE/MRT/TRANSCO in coordination with DE/M&P/DISCOM shall
inspect the project & issue the statutory inspection report.

Statutory inspection & submission of report shall be completed within 10


working days from the date of receipt of instructions from the concerned
CGMs or CE/Zone.

The statutory inspection report should contain the compliance on the


documents & check points mentioned below and general remarks if any.

The statutory inspection report should contain the recommendation of the


inspecting officers, whether the generator can be synchronized to grid and
the same shall be submitted to all the concerned TRANSCO, DISCOM &
SLDC officials without fail.

The following are to be submitted by the Developer for the purpose of


statutory inspection.

a) Approval of the project from NREDCAP.


b) Approved electrical layout, single line diagram (SLD) approved by
TRANSCO/DISCOM.
c) Layout & list of the equipment of the project approved by the Chief
Electrical Inspector to Government (CEIG).
d) Documents with respect to ratings & number of various equipment /
components along with their test certificates & performance curves
wherever applicable.
i. Wind turbines
ii. Solar PV modules
iii. String Combining and Monitoring Boxes (SCMB)in case of
solar generators
iv. Power Conditioners (Inverters)

Page 2 of 9
v. Generator transformers
vi. Auxiliary transformers
vii. Inverter Transformers
viii. Compatibility to LVRT, HVRT (in case of wind generators)
ix. Weather monitoring system
e) Certificate/Document related to the equipment /components
conforming to the relevant minimal technical requirements/standards
published by MNRE, Bureau of Indian Standards (IS) or International
Electro technical Commission (IEC), the Indian Electricity Grid
Code/State Electricity Grid Code whichever is in force and the
specifications of APTRANSCO / APDISCOM wherever applicable.

f) Certificate from the developer for compliance of the equipment to have


harmonic distortion, DC injection, flicker to be within limits as per the
Grid connectivity standards.

g) Documents/test certificates of the equipment for confirming the below.

i. The generating stations (wind and solar) shall be capable of


supplying dynamically varying reactive power support so as to
maintain power factor within limits of 0.95 lagging to 0.95
leading.
ii. The generating stations shall be capable of operating in the
frequency range of 47.5Hz to 52Hz and shall be able to deliver
rated output in the range of 49.5 Hz to 50.5 Hz.

h) Certificate from the developer regarding fulfillment of the terms and


conditions of agreements (PPA, OA etc.) entered into with
APTRANSCO/ APDISCOM including amendments if any.

i) Installation certificate of data transfer / communication system to


APSLDC as approved by APTRANSCO.

j) The factory acceptance and routine accuracy tests of all the metering
equipment at the manufacturer premises.

k) The certificates of metering CTs, PTs and energy meters for their
accuracy tested at NABL accredited lab.

l) Commissioning/Installation reports of the Main, Check & Standby


meters, any in-house meters (Energy accounting & audit meters) and
allied equipment.
Page 3 of 9
m) Protection schemes & adopted relay settings as approved by the Power
Systems wing of APTransco if the generator is connected to
TRANSCO SS.

n) Sanction of estimate and payment of supervision charges if any.

Apart from the verification of the documents submitted as mentioned


above, the following check points shall be verified invariably during the
statutory inspection.

a) Actual Installed capacity & installed capacity as per the approval.

b) In case of solar projects ,

i. Total no. of grid interactive solar PV modules.


ii. Installed capacity in terms of DC and AC Capacities. The DC
capacity shall not exceed the limits specified by the regulations
and Transco orders issued from time to time.
iii. Total no. of modules which are being operated in isolated mode to
meet the auxiliary loads if any.

c) Metering arrangement at the power plant end for measuring gross


generation, auxiliary consumption & net generation etc as per the
requirements.

d) Installation of the interface meters as per the approvals


(Transco/Discom) and in line with the respective agreement conditions
(PPAs/OA agreements).

e) Whether the interconnecting feeder between the project and the


TRANSCO/DISCOM sub-station is provided with appropriate
protection scheme at both ends. In case of generators connecting at 33
kv or below voltage level, Directional over current & Earth fault relays
shall be invariable provided at TRANSCO/DISCOM sub-station end.

f) Capability of the equipment,

to supply dynamically varying reactive power support, to operate in


the frequency range of 47.5Hz to 52Hz,
to deliver rated output in the range of 49.5 Hz to 50.5 Hz
(By verification of the equipment specification &test certificates)

g) Installation of LVRT & HVRT as per regulations (In case of wind


generators).
Page 4 of 9
h) Commissioning of weather monitoring & fore casting mechanism.

i) Commissioning of communication systems for transfer of data to


SLDC.

B) Approaching APSLDC for synchronization permission:

The developer shall approach the APSLDC for getting permission for
synchronization of their plant with grid after statutory inspection. The
following documents are to be submitted by the developer to APSLDC.

a) Statutory inspection report.

b) Static Formats, SCADA, Forecasting & Scheduling as per the Annexure.

c) No dues certificate (In respect of Supervision charges & other charges if


any).

C) Issuance of Synchronization permission by APSLDC:

a) After getting the request from the project developer, the APSLDC shall
verify the statutory inspection reports and requirements as per the
regulations if any, and issue the synchronization permission within 3
working days.

b) The approval for the project synchronization shall be communicated to all


the concerned TRANSCO, DISCOM officials& Developer.

D) Actual process of Synchronization:

a) The synchronization process shall be carried out in the presence of the


following committee members within 4 working days after issuance of
permission by APSLDC.
The concerned CGMs of DISCOM & CE/Zone/TRANSCO shall issue
instructions to the members of the committee for synchronization of the
plant.

S.No Designated Officer Organization


1 Divisional Engineer / Operation APEPDCL / APSPDCL
2 Divisional Engineer / M&P APEPDCL / APSPDCL
3 Divisional Engineer / O & M APTRANSCO
4 Divisional Engineer / MRT APTRANSCO

Page 5 of 9
b) The coordinator for the synchronization process will be DE/OP/DISCOM,
if the generator is connected to substations of DISCOM and
DE/O&M/TRANSCO, if the generator is connected to substations of
TRANSCO.

c) It is to be ensured that the plant is synchronized with grid during the day
time only (in case of solar plants).

d) After synchronization of the plant, immediate intimation shall be given to


APSLDC and the report should be submitted to all the concerned with in
one week from the date of synchronization.

E) Post Synchronization Tests:

a) The measurement of total harmonic distortion, DC injection, flicker etc.


shall be carried out for the upcoming projects within one month from the
date of synchronization, there after once in every year periodically as per
the regulations.

b) The measurement shall be done at Point of Common Coupling (PCC). The


PCC is the emanating feeder point of the generator at Transco/Discom
substation.

c) The duration of the measurement shall be as follows.

Duration of the
Sl.No Description
measurement
Solar plants connected at 33 KV and 6 hours (During the
1
below voltage level generation period)
Wind plants connected at 33 kV and
2 2 Days (Continuously)
below voltage level
Solar plants connected at EHT level 2 Days (During the
3
with or without pooling station generation period)
Wind power plants connected at EHT
4 7 Days (Continuously)
level with or without pooling station

d) In respect of the projects which were already commissioned, the


measurement of total harmonic distortion, DC injection, flicker etc. shall
be carried out within three months from the date of issue of these orders,
there after once in every year periodically.

Page 6 of 9
2) The specified limits for total harmonic distortion, DC injection, flicker as per
regulations/standards are as follows.

a. Harmonic current injections from a generating station shall not exceed the
limits specified in IEEE Standard 519.

Recommended harmonic voltage limits:

99th percentile very short time (3 second) values should be less than 1.5 times
the values given in Table below.

95th percentile short time (10 minute) values should be less than the values
given in Table below.

Individual Voltage Total Voltage


Bus Voltage at PCC
Distortion (%) Distortion THD (%)
1 kV < V 3.0 5.0
69 kV < V 1.5 2.5
161 kV < V 1.0 1.5

Recommended harmonic current limits:

99th percentile very short time (3 second) harmonic currents should be less
than 2.0 times the values given in Table below.

99th percentile short time (10 minute) harmonic currents should be less than
1.5 times the values given in Table below.

95th percentile short time (10 minute) harmonic currents should be less than
the values given in Table below.

Maximum Harmonic Current Distortion in Percent of IL


Individual Harmonic Order (Odd Harmonics)
Voltage at PCC <11 11 17 23 35 TDD
120 < V 69KV 4.0 2.0 1.5 0.6 0.3 5.0
69 kV<V 161KV 2.0 1.0 0.75 0.3 0.15 2.5
V >161 kV 2.0 1.0 0.75 0.3 0.15 2.5

b. The Generator shall not inject DC current greater than 0.5% of the full rated
output at the interconnection point.

Values of DC current injection at 33%, 66% and the maximum generation


shall be less than 0.5% of rated output current.

Page 7 of 9
c. The Generating station shall not introduce flicker beyond the limits specified
in IEC61000.

95th percentile Pst values and all Plt values should be less than the values
given in Table below.

MV HV (35kV<HV<230kV)
(1kV<MV<35kV) &EHV( >230 kV)
Pst 0.9 0.8
Plt 0.7 0.6

3) The proposed schedule of measurement of total harmonic distortion, DC


injection, flicker etc. shall be informed to the MRT Vigilance wing & APSLDC.
MRT Vigilance wing may witness the tests randomly.

4) These orders are issued as per the note approved by the Chairman and Managing
Director on 23.02.2017.

5) These orders are also available on APTRANSCO website and can be accessed at
the address http://www.aptransco.gov.in.
(BY ORDER AND IN THE NAME OF
TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED)

Sd/-
S.Subramanyam
Director/Projects
To
The Executive Director/Planning & HRD / APTransco/VS/Hyderabad
The Chief Engineer/Transmission/ APTransco /VS/Hyderabad
The Chief Engineer/Zone/Visakhapatnam/APTransco
The Chief Engineer/Zone/Vijayawada/APTransco
The Chief Engineer/Zone/Kadapa/APTransco
The Chief Engineer/IPC &Power Systems/APTransco /VS/Hyderabad
The Chief Engineer/SLDC/APTransco /VS/Hyderabad
The Chief Engineer/Construction/ APTransco /VS/Hyderabad
The Chief Engineer/LIS/APTransco /VS/Hyderabad
The Chief Engineer/400 KV Construction/ APTRANSCO /VS/Hyderabad
The Chief Engineer/Commercial/APPCC/VS/Hyderabad
The Chief Engineer/Telecom& IT/ APTRANSCO /VS/Hyderabad – with a
request to place the T.O.O on APTRANSCO website.

Page 8 of 9
Central Record Section and stock file
T.O.O Section.

The Chief General Manager / Commercial/APEPDCL


The Chief General Manager / O&CS/APEPDCL
The Chief General Manager /RA&PP/APEPDCL
The Chief Engineer/Projects/APEPDCL

The Executive Director/Projects/APSPDCL/Tirupati


The Chief General Manager/Operation/ APSPDCL/Tirupati
The Chief General Manager/P&MM, IPC& Civil/APSPDCL/Tirupati
The Chief Engineer /Operation/APSPDCL/Kurnool
The Chief Engineer /Operation/APSPDCL /Tirupati
The Chief Engineer /Operation/APSPDCL /Vijayawada

Copy communicated to
The Director /Projects/APTRANSCO/ VS/ Hyderabad
The Director/ Operation& Projects/ APEPDCL/ Visakhapatnam
The Director/ HRD & Technical/ APSPDCL/ Tirupati

Copy to:
PS to The Chairman & Managing Director/ APTRANSCO/ VS/ Hyderabad
PS to The Chairman & Managing Director/ APEPDCL/ Visakhapatnam
PS to The Chairman & Managing Director/ APSPDCL/ Tirupati
PS to The Joint Managing Director / V&S / APTRANSCO / Hyderabad
PS to The Joint Managing Director / Fin., Comml., IPC, HRD& IT/APTRANSCO/
Hyderabad

//FORWARDED BY ORDER//

ASSISTANT DIVISIONAL ENGINEER


CONNETIVITY,
O/o. ED/HRD & PLANNING,
APTRANSCO, VIDYUT SOUDHA,
HYDERABAD.

Page 9 of 9
ANNEXURE - II (SOLAR)

STATIC DATA OF SOLAR POWER PARK

I DEVELOPER/OWNER/COMPANY DETAILS

1 Name of owner or company or developer

a Address
b Ph No
c Fax No
d E Mail Id
2 Nodal Person details:
a Name
b Address
c Ph No
d Fax No
e E Mail Id
3 Physical Location of the Solar Poewer Park
a Village
b Mandal
c District
4 GPS Cordinates of Solar Park: 4 Corners
a 1 st Corner Lat
b Lon
c 2nd Corner Lat
d Lon
e 3rd Corner Lat
f Lon
g 4th Corner Lat
h Lon
5 GPS Cordinates of Solar Park: Centre
a Lat
b Long
II CAPACITY DETAILS
a DC capacity of Solar Panels:
Cell & Panel Details:
i Each Cell Voltage (V)
ii No. cells in a Panel
iii Connection combination of Panels
iv Panel Voltage(V)
v No.of panels in a Array
vi Array Voltage (V)
Vii Nos. of solar panel
viii Capacity of each panel (KWp)
ix Total Capacity(KWp)
b AC Capacity
i No of Arrays connected to each inverter
ii Inverter input voltage
iii Inverter output voltage
iv No of Inverters
v Capacity of each Inverter(KW)
vi Total Capacity of the Inverters(KW)
c Inverter Transformer Details
i No of Inverter Transformers
ii No. of inverters connected to each transformer
iii Capacity of each Tr(MVA)
iv Total Capacity of the Inverter Trs(MVA)
v Input Voltage(KV)
vi Out put Voltage(KV)
vii Make of Inverter Trs
IV APPROVALS
a From NREDCAP/Govt.
i Total extent of land in acres
Capacity Approval from NREDCAP/GoAP to set up Plant(
ii Attach copy) in MW
Connectivity permission from STU/Discom( indicate
iii name of the Discom)
Total Evacuation permission Accorded in MW ( Attach
iii Copy)
b Name of the pooling Station
i GPS coordinates:
ii Lat
iii Long
iv No of Transformers
v Capacity of each Tr in MVA
vi Voltage rating
vii Make of Trs
c Connected Grid SS
i GPS coordinates
ii Lat
iii Long
iv Lines from PS to Grid SS
v Voltage Level
vi No of Ckts
vii Length
vii Conductor Used

V CONNECTIVITY PROVISIONS
i Connection Agt
ii Site Common Drg
iii Site Responsibility Schedule
iv ABT Meters: Main, Check, Stand By
v SVC/STATCOM
vi AMRs
VI SCADA
Availability of SCADA to transmit the Power system
i
parameters from the PS to SLDC in real time

ii Availability of SCADA to transmit the inverter level data


parameters to SLDC in real time

iii Availability of SCADA to transmit the weather data and


Forecasting parameters in real time to SLDC
iv Solar sensors are provided for (Yes/No)
a Humidity
b UV Index
c Cloud cover
d Solar Insolation
PARAMETERS TO BE TRANSMITTED IN REAL TIME FOR
VII FORECASTING & SCHEDULING
i Global horizontal irradiance (GHI)
ii Ambient temperature
iii Temperature at the back of the PV modules
iv Diffuse Irradiance
v Direct Irradiance
If no Connectivity to SLDC SCADA , then provide SLD of
vi PCC, nearest commn., node for PCC, line connectivity with
PCC and intended commn. Media
Voice & data commn., Transfer of on line operational data
such as Voltage, Frequency,Line flows, status of Breaker &
vii Isolator position , other parameters as specified by
appropriate LD.
Description of Solar Generation Data communication between
vii field and SLDC
VII Solar Panels & Inverter Details
a Static data points:
1 System location and orientation
2 PV Panel Manufacturer and Model
PV panel material -poly Csi /mono Csi/ a-Si Thinfilm/ CdTe
3 Thinfilm/ CIGS Thinfilm
4 Elevation and orientation angles of arrays or concentrators
5 power Curve
The type of solar generation technology employed at the
6 Generating Facility
7 Distance above mean sea level etc.
8 Adjustable/Fixed Panel structure
IX LVRT & HVRT
1 LVRT feature available /not available
2 LVRT Settings available
3 LVRT Settings adopted
4 HVRT feature available /not available
5 HVRT Settings available
6 HVRT Settings adopted
7 Harmonic current injection as per (IEEE) Std.519
Test of injection of DC current at interconnection point(shall
8 not be greater than0.5% of the full rated output)
9 Test of introduce flicker (IEC-61000)
ANNEXURE - II (WIND)

Static data of Wind Turbine Generators


I Developer details
1 Name of the Power Plant

No of WTGs:______X Capacity of each


2 Capacity in MW
WTG:________MW= _______MW

3 Name of the Developer


4 Address, Ph nos, Fax No, E mail ID
5 Nodal Person ,Ph:, E mail ID
Capacity Approval from NREDCAP/GoAP to set
6 _______ MW
up Plant( Attach copy)
7 Connectivity permission from STU/Discom
Total Evacuation / Connectivity permission
8 _______ MW
Accorded( Attach Copy)
Name of the pooling Station
GPS coordinates,
9
Capacity,
Voltage Level
Connected Grid SS
10
GPS coordinates
Lines from PS to Grid SS,
Voltage Level
11 No of Ckts,
Length,
conductor used
12 Connection Agt
13 Site Common Drg
14 Site Responsibility Schedule
15 ABT Meters: Main, Check, Stand By
16 SVC/STATCOM
SCADA:
Commn Type
17
Availability of SCADA

18 AMRs
If RTU/comms or SCADA connectivity not
19 availble at present, time frame of its avilability
**
If no Connectivity to SLDC SCADA then
provide SLD of PCC, nearest comm. Node for
20
PCC, line connectivity with PCC and intended
comm. Media
Voice & data communication, Transfer of on
line operational data such as Voltage,
21 Frequency,Line FlowsStatus of Breaker and
Isolator position other parameters as specified
by appropriate LD.
II Individual Genarators details
WTG1 WTG2 ..
1 Name of the Generator:
2 Contact Person name:
3 Address,, Ph nos, Fax No E mail ID
4 WTG Location No & GPS Co ordinates:
5 Village, Mandal, District:
connected Line from the WTG to PS
Voltage Level
Conductor used
6
No of Lines
Name of the Line if any
Indicate the WTG s connected to each line
III Generator Static Data
1 Type
2 Manufacturer
3 Year of Mfg.
4 Make
5 Model
6 Sl No
7 Capacity in MW
8 commissioned date
9 Hub height in m
10 total height in M
11 RPM range
12 Rated wind speed m/s
13 Performance Parameter
14 Rated electrical power at Rated wind speed :
15 Cut in speed
16 Cut out Speed
17 Survival speed (Max wind speed)
18 Ambient temperature for out of operation
19 Ambient temperature for in operation
20 survival temperature
21 Low Voltage Ride Through (LVRT) setting
22 High Voltage Ride Through (HVRT) setting
23 lightning strength (KA & in coulombs)
24 Noise power level (db)
25 Rotor
26 Stall/Pitch control
27 Hub type
28 Rotor diameter
29 Number of blades
30 Blade Length in M
31 Area swept by blades
32 Rated rotational speed
33 Rotational Direction
34 Coning angle
35 Tilting angle
36 Design tip speed ratio
37 Blade
38 Length
39 Diameter
40 Material
41 Twist angle
42 Generator
43 Generator Type
44 Generator no of poles
45 Generator speed
46 Winding type y
47 Rated Gen. Voltage
48 Rated Gen. frequency
49 Generator current
50 Rated Temperature of generator
51 Generator cooling
52 Generator power factor
53 KW/MW @ Rated Wind speed
54 KW/MW @ peak continuous
55 Frequency Converter
56 Filter generator side
57 Filter grid side
58 Transformer
59 Transformer capacity
60 Transformer cooling type
61 Voltage
62 Winding configuration
63 Weight
64 Rotor weight
65 Nacelle weight
66 Tower weight
67 Over speed Protection
68 Design Life
69 Design Standard
70 Latitude
71 Longitude
72 COD Details
Past Generation History from the COD to the
73 date on which DAS facility provided at RLDC,
if applicable
74 Distance above mean sea level
IV Generator Protection LVRT
LVRT Availability (LVRT Feature
available/LVRT Not Possible/LVRT feature
1
avilable to be enabled/LVRT Design supported
but to be fitted/LVRT feature to be retrofitted)
2 LVRT Settings as per CEA Regn
3 LVRT Setting adopted(Enclose Test Certificate)
4 Useful life of the WTG beyond 04.01.2021
5 WTGS with useful life up to 04.01.2018
V Real-time Data Telemetry requirement (Suggested List)
SCADA:
1 Description of Wind Generation Data
Communication between Field and SLDC
2 Turbine Generation (MW)
3 Wind Speed
4 Turbine Availability Status
5 Generator Status (on/off-line)
6 Nacelle Position (relative to true north)
7 Wind Direction (relative to true north)
8 Yaw Error
9 Rotor RPM
10 Blade Pitch
11 Voltage
12 Ambient.air temperature
13 Barometric pressure
14 Relative humidity
15 Air Density
16 MW,MVAR,V
17 Power System Parameters
VI Generator Test Certificates
Approved Test Reports
1 Type test certificated
2 FAT certificates
3 Precommissioning test certificates
4 Test reports of Harmonic Current Injection
5 Test reports of DC current Injection
6 Test reports of Flicker
VII CEA connectivity Regn Provisions

Is the The generating station capable of


supplying dynamically varying reactive power
1
support so as to maintain power factor within
the limits of 0.95 lagging to 0.95 leading.
Is the generating units shall be capable of
operating in the frequency range of 47.5 Hz to
2 52 Hz and shall it be able to deliver rated
output in the frequency range of 49.5 Hz to
50.5 Hz.
Is the generator have facility to control active
power injection in accordance with a set point,
which shall be capable of being revised based
on the directions of the appropriate Load
Despatch Centre.Provided that as far as
3
possible, reduction in active power shall be
done without shutting down an operational
generating unit and with reduction being
shared by all the operational generating units
pro-rata to their capacity
participate in contingency operations such as
load shedding, increasing or reducing
generation, is landing, black start, providing
4
start-up power and restoration as per the
procedure decided by the Appropriate Load
Despatch Centre
The requester and user shall make
arrangements for integration of the controls
and features of his system into
the Automatic Generation Control, Automatic
5
Load Shedding, Special Protection System,
Energy Management Systems and Supervisory
Control and Data Acquisition System of the
respective state or region.
The requester and user shall prepare single
line schematic diagrams in respect of its
system facility and make the same available to
6 the Appropriate Transmission Utility or
licensee through which his system is
connected and the Appropriate Load Despatch
Centre.
Before connecting, the requester shall
complete all inspections and tests finalised in
consultation with the Appropriate
Transmission Utility or licensee or generating
station to which his equipment is connected.
7 The requester shall make available all
drawings, specifications and test records of
the project equipment pertaining to integrated
operation to the Appropriate Transmission
Utility or licensee or generating station as the
case may be.
Prior to synchronisation of the distributed
generation resource for the first time with
electricity system, the applicant and the
8 appropriate licensee shall agree on the
protection features and control diagrams as
per the provisions of CEA connectivity Regn,
CERC , APERC, IEGC and IEC Stds.
one copy each of the approved drawing and
diagrams showing important equipment,
protection and control features shall be signed
9
by representative of the applicant and the
licensee and shall be in possession of the
applicant and licensee.

Devloper/Generator
ANNEXURE - III (WIND & SOLAR)

QCA & Station Details

Details to be submitted by the Wind/Solar generating stations /Principal Generator/QSE

1 Type: Wind/Solar Generator

Individual/on Behalf of Group of


2 QCA
generators
If on Behalf of Group of generators
3 group of then details of agreement to be
attached
Total Installed Capacity of Generating
4
Station
5 Total Number of Units with details
Physical Address of the RE Generating
6
Station

7 Whether any PPA has been signed: (Y/N) If yes ,then attach details

8 Connectivity Details Location/Voltage Level

9 Metering Details Meter No. 1. Main 2. Check 3 Stand By

10 Connectivity Diagram (Please Enclose)

11 Static data As per attached sheet


Name:
Designation :
12 Contact Details of the Nodal-Person Number: Landiine Number, Mobile Number,
Fax Number
E - Mail Address :
Name :
Designation :
Contact Details of the Alternate Nodal Number: Landiine Number, Mobile Number,
13
Person Fax Number
E - Mail Address :
1

ANNEXURE - IV (WIND & SOLAR)

DECLARATION OF AVAILABILITY BY GENERATORS 15 MINUTES BLOCKWISE AVAILABILITY


Message to : The Chief Engineer / SLDC / APTRANSCO /,Vidyut Soudha / Hyderabad
Name of the Generating station / pooling Stn : Voltage Level: Developer:
Installed capacity (MW) : MW QCA:
Connected Grid SS:
Injection point :
Voltage Level at Injection point: KV
Declaration of availability for date
Rev No: 0 1 2 3 4 5 -- -- --
Date of reporting
Time of reporting (Hrs)
From(Block
Time Interval of no)
Revision(hrs) To ( Block
no)
Time Availability Availability Availability Availability Availability Availability Availability Availability Availability
Block No
From To MW MW MW MW MW MW MW MW MW
1 00:00 00:15
2 00:15 00:30
3 00:30 00:45
4 00:45 01:00
5 01:00 01:15
6 01:15 01:30
7 01:30 01:45
8 01:45 02:00
9 02:00 02:15
10 02:15 02:30
11 02:30 02:45
12 02:45 03:00
13 03:00 03:15
14 03:15 03:30
15 03:30 03:45
16 03:45 04:00
17 04:00 04:15
18 04:15 04:30
19 04:30 04:45
20 04:45 05:00
21 05:00 05:15
22 05:15 05:30
23 05:30 05:45
24 05:45 06:00
25 06:00 06:15
26 06:15 06:30
27 06:30 06:45
28 06:45 07:00
29 07:00 07:15
30 07:15 07:30
31 07:30 07:45
32 07:45 08:00
33 08:00 08:15
34 08:15 08:30
35 08:30 08:45
36 08:45 09:00
37 09:00 09:15
38 09:15 09:30
39 09:30 09:45
40 09:45 10:00
41 10:00 10:15
42 10:15 10:30
43 10:30 10:45
44 10:45 11:00
45 11:00 11:15
46 11:15 11:30
47 11:30 11:45
48 11:45 12:00
49 12:00 12:15
50 12:15 12:30
51 12:30 12:45
52 12:45 13:00
53 13:00 13:15
54 13:15 13:30
55 13:30 13:45
56 13:45 14:00
57 14:00 14:15
2

58 14:15 14:30
59 14:30 14:45
60 14:45 15:00
61 15:00 15:15
62 15:15 15:30
63 15:30 15:45
64 15:45 16:00
65 16:00 16:15
66 16:15 16:30
67 16:30 16:45
68 16:45 17:00
69 17:00 17:15
70 17:15 17:30
71 17:30 17:45
72 17:45 18:00
73 18:00 18:15
74 18:15 18:30
75 18:30 18:45
76 18:45 19:00
77 19:00 19:15
78 19:15 19:30
79 19:30 19:45
80 19:45 20:00
81 20:00 20:15
82 20:15 20:30
83 20:30 20:45
84 20:45 21:00
85 21:00 21:15
86 21:15 21:30
87 21:30 21:45
88 21:45 22:00
89 22:00 22:15
90 22:15 22:30
91 22:30 22:45
92 22:45 23:00
93 23:00 23:15
94 23:15 23:30
95 23:30 23:45
96 23:45 24:00:00

Co-ordinating Agency/Generator
Contact Person
Mobile No
Ph No
Fax No
Email ID