work method statement
work method statement
PROCEDURE
SCOPE
This document contains guidance for test or calibration of self-indicating weighing
instruments (hereafter called “instrument”), in particular for
1. measurements to be performed,
2. calculation of the measuring results,
3. determination of the uncertainty of measurement,
4. contents of calibration certificates.
The object of the calibration is the indication provided by the instrument in response
to an applied load. The results are expressed in units of mass. The value of the load
indicated by the instrument will be affected by local gravity, the load temperature and
density, and the temperature and density of the surrounding air.
It is up to the calibrating laboratory and the client to agree on the anticipated value of
The uncertainty of measurement that is appropriate in view of the use of the instrument
and in view of the cost of the calibration.
Any such procedure must include, for a limited number of test loads, the determination
of the error of indication and of the uncertainty of measurement assigned to these errors.
The test procedure should as closely as possible resemble the weighing operations that
are routinely being performed by the user – e.g. weighing discrete loads, weighing
continuously upwards and/or downwards, use of tare balancing function.
The procedure may further include rules how to derive from the results advice to
the user of the instrument with regard to the errors, and assigned uncertainty of
measurement, of indications which may occur under normal conditions of use of the
instrument, and/or rules on how to convert an indication obtained for a weighed object
into the value of mass or conventional value of mass of that object.
If an instrument is moved to another location after the calibration, possible effects from
The most suitable operating procedure for high resolution balances (with relative
resolution better 1 × 10 -5 of full scale) is to perform the adjustment of the balance
immediately before the calibration and also immediately before use.
Instruments fitted with an automatic zero-setting device or a zero-tracking device [2] (or
[3]) should be calibrated with the device operative or not, as set by the client.
For onsite calibration the user of the instrument should be asked to ensure that the
normal conditions of use prevail during the calibration. In this way disturbing effects
such as air currents, vibrations, or inclination of the measuring platform will, so far as is
possible, be inherent in the measured values and will therefore be included in the
determined uncertainty of measurement.
3. MEASUREMENT METHODS
Tests are normally performed to determine
the repeatability of indications,
the errors of indications,
The effect of eccentric application of a load on the indicatior.
Linearity test
A Calibration Laboratory deciding on the number of measurements for its routine
calibration procedure should consider that, in general, a larger number of
measurements tends to reduce the uncertainty of measurement but increase the cost.
Details of the tests performed for an individual calibration may be fixed by agreement of
the client and the Calibration Laboratory, in view of the normal use of the
instrument. The parties may also agree on further tests or checks which may assist in
evaluating the performance of the instrument under special conditions of use. Any such
agreement should be consistent with the minimum numbers of tests as specified in the
following sections.
3.1 Repeatability test
The test consists of the repeated deposition of the same load on the load
receptor ,under identical conditions of handling the load and the instrument, and under
constant test conditions.
The test load(s) need not be calibrated nor verified, unless the results serve for the
determination of errors of indication as per 5.2. The test load should, as far as possible,
consist of one single body.
The test is performed with at least one test load which should be selected in a
reasonable relation to Max and the resolution of the instrument, to allow an appraisal of the
instrument performance.
The status of the zero-setting or zero-tracking device if fitted should be recorded.
The purpose of this test is an appraisal of the accuracy of the instrument over the whole
weighing range.
Where a significantly smaller range of calibration has been agreed, the number of
test loads may be reduced accordingly, provided there are at least 3 test points
including
Min and Max, and the difference between two consecutive test loads is not greater
than 0,15Max.
Prior to the test, the indication is set to zero. The test loads once in one of these manners
are normally applied
The test, or individual loadings, may be repeated to combine the test with the
repeatability test under 5.1
1. Centre
2. Front left
3. Back left
4. Back right
5. Front right
There may be applications where the test load cannot be placed in or close to the
centre of the load receptor. In this case, it is sufficient to place the test load at the
remaining positions as indicated in Figure 5.3-1. Depending on the platter shape, the
number of the off-centre positions might deviate from figure 5.3-1.
3.5 Calibration
Calibration of instrument is different from model to model and manufacturer to
manufacture. Generally, it is a simple procedure described in the user’s manual which
comes with the instrument. This procedure should only be carried out by a trained
personnel. (refer to technical manual).
4.0 CALIBRATION CERTIFICATE
This section contains advice regarding what information may usefully be provided in a
calibration certificate.
Warning that the certificate may be reproduced only in full unless the
calibration laboratory permits otherwise in writing.