Compuatation of Area and Volume
Compuatation of Area and Volume
Answer:
Rule I: Area of the traverse = 64351.995 sq. m.
Rule II: Area of the traverse = 64351. 995 sq. m.
Rule III: Area of the traverse =64351. 995 sq. m.
(Kanetkar and Kulkarni, Surveying and Levelling, Part-I, 2015)
(b) Areas along Boundaries :- The areas of the irregular strips
may be calculated by multiplying the mean if each successive pair
of adjacent off sets by the distance between them.
Let O1= the offset at chainage x1 along the survey line.
02= the offset at chainage x2 along the survey line.
Mean offset = 1 2
Note :- 01, 03, O5, etc., (the 2nd, 4th, 6th, etc., from the end) are even ordinates, and
02, 04, O6, etc., (the 3rd, 5th, 7th, etc., from the end) are odd ordinates.
Note :- This method necessitates an even number of the divisions of the
area, i.e. the total number of ordinates must be odd. If there be an odd number of
divisions resulting in an even number of ordinates, the area of the last division must
be calculated separately, and added to the result obtained by applying Simpson's
rule to the remaining divisions.
• When one or both of the end ordinates (Oo or 0, or both) are zero, they must not be
omitted from the formula.
• The derivation of the formula is as follows :-
• Simpson's rule, also called the parabolic rule, assumes that the boundaries between
the ordinates are the arcs of a parabola. In fig. 7.9 let
• Ap (OO), Br’ (O1), Cq(O2) = any three consecutive ordinates taken at equal distances
d apart.
• The required area (∆)= the area (Apr'qC) enclosed between the base line AC, the
parabolic arc pr'q, and the end ordinates Ap and Cq.
• Through r’ draw p’r’q' parallel to the chord pq.
• Now the area Apr’qC = area of the trapezoid ApqC + area of segment pr’qrp
between the parabolic are pr’q and the chord pq.
• Area of the trapezoid ApqC =𝐴𝑝+𝐶𝑞 = 𝑂𝑜 +𝑂2
2 2
• Area of the segment pr’qrp = 2 * area of the enclosing.
3
2
• Parallelogram pp’q’q = (rr’ * AC)
3
• Where rr’ = Br’-Br = O1- 𝑂𝑜+𝑂2
2
; and AC = 2d.
𝑂𝑜+𝑂2 2 𝑂𝑜+𝑂2
• Therefore, the required area 1 (∆) = 1
𝑑 2 3 2
3 𝑜 1 2
Offset (m) 3.29 4.05 6.23 5.75 4.76 5.26 4.32 3.92 2.91
Find the area between the survey line and the hedge by using (a) Simpson’s rule,
(b) the trapezoidal rule.
Answers:-
(a) Simpson’s rule = 314.47 sq. meter
(b) Trapezoidal rule = 311.4 sq. meter
Answers:
(a) Simpson’s rule = 369.42 sq. meter
(b) Trapezoidal rule = 359.60 sq. meter
When wheel is placed beyond the hinge away from the tracing
point:
• A is anchor point, T is tracing point, H is pivot point and W is
wheel. Lines AW and TW are right angled to each other. So that
angle AWT is 900. AT is the radius of the zero circle.
• From triangle ATW
AT2 = TW2 +AW2 (1)
From triangle AWH
AH2 = HW2 +AW2
AW2 = AH2-HW2 (2)
Put equation 2 in equation 1
AT2 = TW2 + AH2-HW2
R’2 = (L+L1) 2 + R2- L 12 = L2+2LL 1+R2
R’= (L2+2LL1+R2)1/2
Area of zero circle = R’2 = (L2+2LL1+R2)
When the wheel is located between the hinge and tracing point:
• A is anchor point, T is tracing point, H is pivot point and W is
wheel. Lines AW and TW are right angled to each other. So that
angle AWT is 900. AT is the radius of the zero circle.
• From triangle ATW
AT2 = TW2 +AW2 (1)
From triangle AHW
AH2 = HW2 +AW2
AW2 = AH2-HW2 (2)
Put equation 2 in equation 1
AT2 = TW2 + AH2-HW2
R’2 = (L-L1) 2 + R2- L12 = L2-2LL 1+R2
R’= (L2-2LL1+R2)1/2
Area of zero circle = R’2 = (L2-2LL1+R2))
Note :
• Use plus sign when the zero mark of the dial passes the
fixed index mark in a clockwise direction. Then ∆ = M
(FR. -I.R. + 10N + C).
• Use minus sign when in a counter-clockwise direction
Then ∆ = (FR. – IR. – 10 N + C).
• The constant C is to be added only when the anchor point
is fixed inside the figure.
• When the anchor point is inside the figure, Some
confusion between positive and negetive results arises.
• In order to avoid it, it must be remembered that in the
case of clockwise rotation, the net rotation of the wheel is
always forward, if the area of the figure is greater than
that of the zero circle while it is always backward, if the
area of the figure is less than that of the zero circle.
Planimeter Numericals
Figure 7
The volume of earthwork can be computed as explained
below.
1. Locate the points of no cut or no fill. These are the points of
intersection of the full-line contour and the corresponding
dash-line contour. The points are marked a, b, d, e, h, and j,
etc. in Fig, 7.
2. Determine the areas entirely in filling (area abcdefa) and the
area entirely in cutting (area dghjked)
3. At various contour elevations, draw the horizontal sections of
the earth fill, ( ) and the earth cut ( ). These
are shown hatched in Fig. 7.
4. Determine the base areas of fills from the horizontal sections
etc. and the base areas of cut from the horizontal
sections etc. The areas can be easily computed with
a planimeter.
2. Horizontal Planes Method.
2 3
Likewise,
199.0 to 198.0, =
198.0 to 197.0, = 0
197.0 to 196.2, =
Total = 284.83
3. Equal Depths Method
2 to 3 m depth, = = 195
Total = 900
3. Equal Depths Method
Figure 8
Mass-haul diagram
• A mass-haul diagram is a plot between the cumulative
volume of earthwork and the distance. It is a continuous
curve whose ordinate represents the algebraic sum of the
volumes of cutting and filling, and the abscissa
represents the distance.
• While computing the algebraic sum of volumes, the
cuttings are usually assumed as positive and the fillings,
as negative.
• In hillside sections, the difference of the volumes of
cuttings and fillings, with its proper sign, is used to
compute the algebraic sum of volumes.
Mass-haul diagram
• While computing the volumes, due allowance shall be
made for the swelling of the excavated material or for
the reduction in volume due to compaction of the filled
material.
• Generally, the excavated soil increases in volume when
removed from the ground. But when again filled and
compacted, it may occupy less volume than what it
occupied originally in situ.
• An ordinary soil may have an overall decrease
(shrinkage) of about 10 to 20% when fully compacted.
On the other hand, some rocks may have an overall
increase (bulking) of 25 to 35%.
Mass-haul diagram
1. Divide the length of the road (or railway) into separate reaches.
2. Compute the volume of earthwork for each reach using the
methods already discussed.
3. Plot a longitudinal section of each reach on a suitable scale (Fig.
1).
4. Determine the accumulated volumes at various points, taking the
volume at the starting point as zero.
5. Generally, the mass-haul diagram is drawn below the L-section.
Select a suitable base line for the mass-haul diagram.
6. Plot the cumulative volumes as ordinates and the distance as
abscissa. Keep the distances between the reaches the same as in the
L-section. Plot the positive cumulative volumes above the base
line, and the negative volumes below the base line.
7. Join the ends of the adjacent ordinates by a smooth curve.
Points to be noted in the mass-haul diagram
1. The mass-haul diagram rises in the case of cuttings, and falls in the case
of fillings.
2. The maximum point occurs at the end of a cut, and the minimum point
occurs at the end of a filling reach.
3. The difference between the ordinates at two points is equal to the volume
of cut (or fill) between the two points, provided there is no maximum or
minimum point between them.
4. The vertical distance between a maximum point and the next minimum
point is equal to the volume of the filling.
5. The vertical distance between a minimum point and the next maximum
point is equal to the volume of the cutting.
6. If the diagram cuts the base line at any two points in succession, the
volume of cuttings between the two points is equal to the volume of
fillings, as the algebraic sum of the volumes is zero.
7. Any horizontal line drawn parallel to the base line and intersecting the
curve at two points is a balancing line. It indicates a length over which
the volume of cuttings is equal to that of filling.
BASIC DEFINITIONS
1. Haul distance: It is the distance between the working face of an
excavation along the route and the tip end of the embankment formed
from the excavated material.
2. Average haul distance: It is the distance between the centre of gravity
of the excavation and that of the embankment.
3. Haul: It is equal to the total volume of the excavation multiplied by the
average haul distance. It is also equal to the area between the mass-haul
curve and the balancing line. If haul is known, the average haul
distance can be obtained by dividing it by the volume. The unit of haul
is 1 station-metre. One station-metre is equal to 1 m³ of material moved
through one station (100 m).
4. Free-haul distance (F.H.D.): It is the distance upto which the hauling
is done by the contractor without charging extra. Generally, the rate
quoted is for excavation and free hauling upto a certain distance, called
free- haul distance.
BASIC DEFINITIONS
5. Overhaul: It is the distance beyond the free haul distance for which
extra payment is made to the contractor.
6. Borrow: It is the material needed for the embankment taken from
borrow pits. If the material available from the excavation is not
sufficient for the embankment, borrow pits are dug to take out extra
material.
7. Waste (spoil): It is the material excavated from cuts but not used for
embankment. When the excavated quantity is greater than that required
for embankment, extra material is dumped in spoil banks.
8. Limit of economical haul (L.E.H.): It is the maximum limit of the
haul distance beyond which it is not economical to use the material
obtained from cuts. Beyond the limit of economical haul, it is more
economical to waste the material or to take the material from the
borrow pits than to haul it.
BASIC DEFINITIONS
The limit of economical haul is obtained from the following relation
For illustration, if free haul distance is 200 m, the cost of excavation is Rs.
3 per m3, and the overhaul is Rs. 2 per station metre, the limit of
economical haul is given by
It may be noted that upto a distance of 350 m, the cost of overhaul is less
than the cost of excavation, but beyond 350 m, the cost of overhaul will be
more. For example, for a distance of 400 m (i.e. 200 m beyond free haul
distance), the cost of overhaul will be Rs. 4 but the cost of excavation is
Rs. 3/-. It would be more economical to take the material from the borrow
pit than to haul it from the cut.
BASIC DEFINITIONS
9. Lead: It is the horizontal distance through which excavated material is
moved from the cut to the required embankment. Generally, a lead of
30 m is included in the cost. The term lead has the same meaning as the
average haul distance. However, the term is general and used for the
horizontal distance moved for bringing any material to the site. For
example, when we say that cement will have a lead of 5 km, we mean
that cement will be brought to the site from a distance of 5 km.
10.Lift: It is the vertical distance through which excavated material from a
cut is moved to the required embankment. Generally, a lift of 1.5 m is
included in the cost. If the embankment is constructed at a higher level
than the cut area, the contractor charges extra for lift. Like lead, lift is
also a general term and is used for the vertical distance moved for
bringing any material to the site. For example, if concrete is to be
deposited at a height of 10 m above the ground level, it will have a lift
of 10 m.
BASIC DEFINITIONS
11. Balancing line: Any horizontal line drawn on the mass-haul diagram is
a balancing line because it balances the volumes of cutting and filling.
There is no difference in the cumulative volume between the two points
where the balancing line cuts the mass haul diagram.
12. Shrinkage factor: It is the ratio of the volume of the compacted soil to
the volume occupied by it in situ conditions. For most soils, a shrinkage
factor of 0.8 is generally taken.
13. Bulking factor: It is the ratio of the volume of the dumped rock to the
volume occupied by it in situ conditions. For most rocks, a bulking
factor of 1.25 is generally taken.
MOVEMENT OF EXCAVATED MATERIAL
Fig. 3 shows a mass-haul diagram. The balancing lines EF and CF are also
marked.
When the loop of the mass-haul curve cutoff by a balancing line is above
that line, the excavated material must be moved forward to the right in the
direction of the increasing abscissa. However, when the loop is below the
balancing line, the material must be moved backwards to the left in the
direction of decreasing abscissa. The directions of movement are shown by
arrows for loops AEF and CBD.
5. The best solution from the haul consideration is to minimize the area
between the mass-haul curve and the balancing line. However, it may
result in large waste and borrows, and may not be overall economical.
The true economy can only be achieved by keeping the overall cost of
excavation, hauling, wasting and borrowing to a minimum.
A number of solutions would be possible, depending upon the free-haul
distance, overhaul limit of economic haul, etc. and the solution which
gives the minimum overall cost is the most economical.
6. It is worth noting that the aim is to reduce the overall cost and not to
minimize the volume of excavation.
COMPUTATION OF OVERALL COST
The mass-haul diagram can be used to compare the various alternatives of
the utilization of the excavated material, and to determine the most
economical alternative. The most economical scheme for distribution of
the excavated material may be found by comparing the cost for different
positions of the balancing lines.
4
VOLUME BY SPOT LEVELS
The volume of the entire pit can be expressed as
ℎ 𝑎 +ℎ 𝑏 +ℎ 𝑐 +ℎ 𝑑 ℎ 𝑏 +ℎ 𝑒 +ℎ 𝑓 +ℎ 𝑐 ℎ 𝑒 +ℎ 𝑔 +ℎ ℎ +ℎ 𝑓
V
4 4 4
𝐴
V
4 1 2 3 4
Triangular Prisms. Fig. 5 (b) shows the pit divided into triangles in
plan. These triangles represent the truncated triangular prisms. In this
case, one corner point can be common upto eight tringles. Determine
the depths h1, h2… etc. which are common to one, two, …etc, triangular
prisms. The volume of one triangular prism abc is given by
𝑎 𝑏 𝑐
Answers:
Volume = 2553.75 m3
CAPACITY OF RESERVOIR
The capacity of a reservoir can be determined from the contour plan. This
is a particular case of computation of volume from the contour plan when
the finished surface is a level surface.
Fig. 6 shows the contour plan of the reservoir on the upstream of a dam.
The contour of 125 m represents the water edge at full reservoir level
(F.R.L.) of 125.00. The water spread at R.L. of 125.00 is equal to the
surface area of the reservoir when it is full. Likewise, the water spread at
R.L. of 120, 115, 110, 105 and 100 are also shown.
The volume is computed by assuming that the reservoir is divided into a
number of horizontal slices. For computation of the volume, the whole
area lying within a contour line and the upstream of the dam is determined
with a planimeter. It must be noted that the areas required are the whole
areas upto the dam and not the areas between adjacent contours.
CAPACITY OF RESERVOIR
1 𝑛 2 4 3 5
Area (ha) 3 8 10 15 20 25
Determine (a) the capacity of the reservoir if the full reservoir level is
125.00, (b) the elevation of the water surface when the reservoir if half-
full. Ignore the volume below R.L. 100.00
Answers:
(a) 337.5 ha-m
(b) 116.79 m
References