V5
V5
Non provision of PPE. The site workers had to provide their own PPE.
Conflict always arose between site workers. To halt this, we dismissed anyone
team members especially the casual workers, Hence, a strict site security was
implemented, a book that enables workers to sign in and out was provided to
keep track.
2
3.1 PROJECT: CONSTRUCTION OF TWO FLOORS OFFICE EXTENSION
900mm and 200mm thick slab. The built of area is about 45m2.
3
Calculation of number of sandcrete blocks, reinforcement and wood for formwork
to be supplied to site at different milestones of the project.
3. Site accounts officer/Paying of workers’ wages.
Counting numbers laid blocks to determine the mason’s wage
Recording of site wages for both daily paid laborers and sub-contractors
overall project life cycle and appreciated the practice of value engineering, I
utilized the BS8110 in the structural design of the building
I learnt the basic block molding technology
I polished my experience on finishing especially plastering and dressing
I learnt that integrity is a priceless virtue in and out of site
I was exposed to more complex structures like raft foundation, retaining wall e.t.c
4
3.2 PROJECT: CONSTRUCTION OF NNPDC HOSING ESTATE, AKWA-IBOM
Client: NNPDC
Contractor: WILANGY CONSTRUCTION COMPANY
Position held: Civil Engineer
Completion: 100%
The site is situated at Atabrikan, Eastern Obolo Lga, Akwa Ibom State Nigeria. The
project is the construction of a NNPDC Housing Estate. The project spanned for a
period of 3 years. The site conditions were favorable, Hence strip foundation with pad
footing was constructed.
5.1.3 SCOPE OF THE WORK:
The scope of this work involved demolition of existing structure and construction of the
building from substructure to finishing.
6
7
8
PROJECT: Asphaltic
Pavement of 1.0km Adohe Road TREASURE STREET
OFF ENEKA ROAD
Client: NDDC
5.1.0 Project Description
This road project was aimed at providing a motor able access road for the
users within the locality so as to enhance movement and transfer of goods and
services.
The length of the road is 1km and the road width is 7. 3m and the road
5.1.1 Responsibilities
Design
9
criteria
Design
Procedure
Pavement composition
Initially, no one among our team realized that the newly constructed cross
culvert (box) which was introduced to carry erosion from one side to the road
and connect with the already provide rubble stone wall channelization that
dissipate the water into the bush needs a man hole for clearing exercise, until
when the engineer representative came and called our attention to it, we broke
the culvert to enhance cleaning and desilting exercise when the need calls for
such.
10
CHAPTER FOUR
5.0 CONCLUSION
This report has shown my involvement in many area of Civil Engineering Works, ranging
Better the life of the Nigeria populace and the world as a whole.
In summary, being in these professions has been challenging and fulfilling. Therefore, no
doubt or regret in chosen this profession. I hope to o more and submit myself tutelage under
senior colleagues.
11
.1 Endorsement
I, the undersigned, have gone through the report that has been prepared and we endorse the
experience attained and reported by the writer. Based on our personal knowledge of the
character and professional reputation of the applicant, I recommend for acceptance of this
Work Experience report by the COREN in Partial fulfillment of the requirements for
registration as Registered Engineer/Technologist.
12