2. BCI11N03-CVL-PRC-AEI-002-REV-0-Procedure for Land Clearing of Civil Works

The document outlines the procedure for land clearing and civil works for the N03 Biomass Nestle Batang project, detailing steps such as clearing, earthwork, excavation, and backfilling. It specifies requirements for materials, compaction, dewatering, and inspection, ensuring compliance with standards and client approval. The document is intended for use by contractors and engineers involved in the project and is subject to copyright restrictions.

Uploaded by

fian 86
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views7 pages

2. BCI11N03-CVL-PRC-AEI-002-REV-0-Procedure for Land Clearing of Civil Works

The document outlines the procedure for land clearing and civil works for the N03 Biomass Nestle Batang project, detailing steps such as clearing, earthwork, excavation, and backfilling. It specifies requirements for materials, compaction, dewatering, and inspection, ensuring compliance with standards and client approval. The document is intended for use by contractors and engineers involved in the project and is subject to copyright restrictions.

Uploaded by

fian 86
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Procedure for Land Clearing of

Civil Works

N03 BIOMASS NESTLE BATANG

BERKELEY ENERGY COMMERCIAL INDUSTRIAL SOLUTIONS

Client : Contractor

APPROVED

APPROVED AS Signature
NOTES

NOT APPROVED Name

REVIEWED
Date

This document is copyright and shall not be reproduced


without the permission of PT. Asuka Engineering
Indonesia

Distribution : Status Code :


Client : Original Copy A01 : Issued For Review
All Engineers : Controlled Copy B01 : Issued For Approval
QA/QC : Controlled Copy C01 : Issued For Construction

0 13-06-2022 BYG AZH ANR Issued For Review


REV.
NO DATE AUTHOR CHECKED APPROVED ISSUE PURPOSE

Document Number Engineering Discipline :


QAQC
BCI11N03-CVL-PRC-AEI-002
Table of Contents

1. CLEARING & GRUBING ................................................................................................................................................. 3


2. EARTH WORK .................................................................................................................................................................. 3
3. EXCAVATION .................................................................................................................................................................. 3
4. DISPOSAL OF SURPLUS SOIL ....................................................................................................................................... 4
5. BACKFILLING .................................................................................................................................................................. 4
6. FILLING AND BANKING ................................................................................................................................................ 4
7. PREPARATION OF SUBGRADE FOR ROADS ............................................................................................................. 5
8. COMPACTION .................................................................................................................................................................. 5
9. DEWATERING .................................................................................................................................................................. 5
10. TOLERANCE ..................................................................................................................................................................... 5
11. INSPECTION AND TEST ................................................................................................................................................. 5
12. SURVEY & TOPOGRAPHY FOR PIPELINE .................................................................................................................. 6
13. EXCAVATION/TRENCHING .......................................................................................................................................... 6

BCI11N03-CVL-PRC-AEI-002 Page 2 of 7
1. CLEARING & GRUBING
1.1. All vegetations and obstacles shall be cleared from the size, prior to excavations or
filling.
1.2. All organic topsoil shall be stripped and deposited in the area, designated on the
drawings, or as directed by the client.
1.3. Roots of tress and any obstacles projecting from the surface finished shall be
grubbed and replaced with suitable materials approved by the client. The grubbed
materials shall be disposed as directed by the client.

2. EARTH WORK
1.4. REFERENCE
1.4.1. The requirements contained in the latest editions of the following standard
shall from an integral part of the requirements specifications in the manner
and to the extend specified here in.
1.4.2. AASHTO-T-180 Sundered method of test for moisture density relations
of soils and soil aggregate mixture using 10.0 ib (4.54 Kg) ramer and in
Drop.
1.4.3. ASTM D 1556 Standard method of test for density of soil in place by
the sand-cone method.
1.4.4. ASTM D 2167 Standard test for density of soil in place by the Rubber-
Ballon method.
1.5. MATERIALS
1.5.1. All materials for filling, back filling, and banking shall be free from
objectionable rubbish, debris grass, roots and other foreign materials, and
shall be subject to the approval of the client.
1.5.2. Granular materials shall be used for back filling around underground
piping up to the top of the pipe.

3. EXCAVATION
3.1. Excavations shall be done to the dimensions, levels, lines and profiles, indicated
on the drawings or as otherwise specified.
3.2. The faces and beds of all excavations, after being excavated to the required
dimensions, shall be carefully trimmed to the required profiles and levels, and be
cleaned of all lose mud, dirt and other debris.
3.3. No excavations shall be refilled or built upon until the formation has been inspected
and approved by the client.
3.4. If shutting and shoring is required, a detailed scheme indicating type, depth,
installations procedure, etc. shall be designated by the client prior the installation.
3.5. If mud of foreign matter is encountered at the excavated bottom, such matter shall
be replaced with suitable materials.

BCI11N03-CVL-PRC-AEI-002 Page 3 of 7
3.6. Over-Excavation bellow the specified level shall be filled with suitable material
approved by the client or with lean concrete up to the specified level of the structure
bottom.
3.7. Where and existing facility is anticipated to be encountered bellow grade during
excavation, the locations shall be carefully done so as not to damage such facility.
3.8. The width of the trench at the bottom for underground piping shall be decided
based on pipe size, depth and soil conditions but shall not be less than the pipe
diameter plus 610 mm to keep access for inspections and mechanical compaction.

4. DISPOSAL OF SURPLUS SOIL


4.1. Surplus soil shall be disposed of in the area designated by the client.
4.2. Surplus soil disposal area shall be properly drained and graded.

5. BACKFILLING
5.1. No back filling shall be allowed before construction bellow grade is inspected, tasted
and approved from are removed, and trash and debris are cleaned.
5.2. Back filling shall be done in layer not exceeding 30cm in thickness before
compaction.
5.3. Compaction of the materials shall be accomplished with equipment approved by the
client.
5.4. Back filling material shall be placed carefully around the structures and be
thoroughly compacted to prevent any damage to the permanent works.
5.5. Back filling around underground piping shall be accomplished in the following
manner
5.5.1. Granular materials shall be used for back filling around underground piping
up to the top of the pipe and be packed in layers not exceeding 20cm, or
the pipe diameter whichever is smaller in thickness before compaction.
5.5.2. The material from excavation may be used for backfilling above the pipe;
however, the material shall be subjected to the approval of the client.
5.6. Back filling material shall not be placed against unsupported walls until the mortar
or concrete has attained sufficient Strangford supporting the backfill load.
5.7. Back filling material shall be compacted to meet the requirements.

6. FILLING AND BANKING


6.1. Filling and banking shall be done and layers not exceeding 30cm in thickness
before compaction and be compacted thoroughly using approved equipment.
6.2. Each layer of soil shall ex and over the full width of the embankment.
6.3. The fill and embankment shall be compacted to the lines and grades indicated on
the drawing.
6.4. The material shall be compacted to meet the requirement.

BCI11N03-CVL-PRC-AEI-002 Page 4 of 7
7. PREPARATION OF SUBGRADE FOR ROADS
7.1. Soft soil and obstacles encountered in the sub grade shall be removed and replaced
with suitable material as approved by the client.
7.2. The sub grade shall be compacted as specified on the drawings prior to placing fill
material.
7.3. The sub grade shall be true to the line and slope shown and the drawings.

8. COMPACTION
8.1. Unless otherwise specified backfilling material shall be compacted to 95 percent of
maximum dry density to optimum content determined by ASTM D1557
8.2. Sub grade for heavy roads and thank foundation and shall be compacted to 95
percent of maximum dry density to optimum content determined by ASTM D1557
8.3. Prior the commencing compaction, the maximum thickness before compaction of
each layer the minimum number of passes of compaction equipment shall be
determined by the field compaction to ensure the compaction meets the specified
requirements. The above passes shall be approved by the client.

9. DEWATERING
9.1. A suitable de watering system shall be provided to maintain quality and to ensure
progress of earth work.
9.2. Where necessary, a temporary sump and trench shall be installed for de watering
and when no longer required, shall be backfill with suitable material approve by the
client.

10. TOLERANCE
Unless other wide specified, the finished surface shall be within 5cm of the lines indicated
on the drawings.

11. INSPECTION AND TEST


11.1. General
11.1.1. The final lines, levels and slopes Shea, are inspected to ensure that the
specified requirements have been met.
11.2. Inspection of Compaction
11.2.1. Back filling shall be accepted when the material is placed in layers not
exceeding the specified thickness and compacted with compaction
equipment in at least the number of passes determined in accordance
with requirements. No other inspections will be made for compaction of back
filling.
11.2.2. Inspection of compaction for earth work other than back filling shall be
performed in accordance with the field compaction test prescribed in
the related specification.
11.2.3. Field Compaction Test

BCI11N03-CVL-PRC-AEI-002 Page 5 of 7
11.2.3.1. Maximum dry density shall be determined in accordance
with ASTM D1557
11.2.3.2. The compaction test at the site shall be performed in
accordance with ASTM D1556 or D2167.
11.2.4. A method of determining compaction other than the above may be
employed if approved by the Engineer, and provided that the relationship
between the results of the adopted method and the specified density is
established prior to inspection.
11.3. Test reports shall be prepared for all tests and be submitted to the engineer
immediately after the test is completed.

12. SURVEY & TOPOGRAPHY FOR PIPELINE


12.1. The contractor will layout his work from the engineer established base lines and
bench marks indicated on the drawings and will responsible for all measurements
in connections therewith.
12.2. Contractor will make such surveys and computation as are necessary to
determine the boundary limit, location of structure, elevation of ground and
structure, and the quantities of world performed or placed during each period for
which a progress payment is to be made.
12.3. All surveying data shall be submitted to the engineer for checking, and approval.
12.4. The contractor shall be responsible of maintaining and preserving all stakes and
other marks established by the engineer until authorized to remove them.

13. EXCAVATION/TRENCHING
13.1. The trench can be excavated with Excavator. Before excavation the alignment
pipe is clearly surveyed and marking trench of centreline. Trenching shall be
configured in accordance with minimum allowable roping radius of the pipe and
hot bend will be installed.
13.2. Location if may be required a trench deeper and wider than shown on the drawing
in order to properly install the pipe line in unstable underwater area or near the
bank of the water courses are properly and safety trenched in accordance with
accepted practice.
13.3. Excavate material shall be stacked down stream so that it does fall back in to the
trench. Placement and storage of excavated material from the bed of crossing will
be determined for each particular crossing condition.
13.4. In no even shall the soil obstruct stream flow, if dumping back in the river is not
permitted soil shall be stacked temporarily at approved locations.

BCI11N03-CVL-PRC-AEI-002 Page 6 of 7
Close - Out

BCI11N03-CVL-PRC-AEI-002 Page 7 of 7