Revised Variation instruction -1012502 (Time Extention due to winter break ) (1)

The document is a variation instruction from UNOPS to Sayed Abad Construction Company regarding the contract for upgrading Peerbagh streets. The contract period has been extended to 27 June 2025 without additional costs due to winter delays. The contractor is required to submit a request for time extension and a revised work plan within three days before executing the variation.

Uploaded by

Wafiullah SAYED
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views

Revised Variation instruction -1012502 (Time Extention due to winter break ) (1)

The document is a variation instruction from UNOPS to Sayed Abad Construction Company regarding the contract for upgrading Peerbagh streets. The contract period has been extended to 27 June 2025 without additional costs due to winter delays. The contractor is required to submit a request for time extension and a revised work plan within three days before executing the variation.

Uploaded by

Wafiullah SAYED
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Notices and Communications

004 – Variation instruction – Clause 8

Date: 02 Feb 2025


Contract Ref. No.: 1012502

Employer: UNOPS
Contractor: Sayed Abad Construction Company

Attention to: Mohammad Ullah Habibi


Contractor’s Representative
Contractor’s Representative
Khoshal Khan, Speen Kalay, PD#4, Kabul, Afghanistan.
[email protected]
,Cell: +9370798404080 & +93 788616088

Contract: Upgrading of Peerbagh streets with plum concrete surface with a total length of 556m &
construction of 44m stone masonry retaining wall in Gozar #01, District #03, Lot-01, Gardez
City.

Subject: Variation instruction

Dear Mohammad Ullah Habibi,

In reference to Clause 8 [Variations] of the General Conditions, the Contractor is hereby instructed to carry out
the following Variation to the contract period:

The contract period extended to 27 June 2025 without extra cost due to the Cold weather break (winter delays).

The Contractor is further requested, in accordance with Clause 8 [Variations], to submit a request letter for time
extension and revised work plan for Variation and on the execution of the Works, including the Time for
Completion, as soon as practicable and within three days and before the Contractor carries out the Variation.

Sincerely,

Signed by: Najeeb Ahmad MASOUD


Employer’s Representative

Copy to: Nicholas Mark Gardner, Country Director & Representative, UNOPS-AFCO

Construction Contract for Minor Works 1 of 1 Version 1.0 | 2022