Time Schedule

The document outlines the bar schedule for retrofitting works at Hardy Associates Limited in Gazipur, Bangladesh, starting from August 27 to December 31, 2021, over a duration of 18 weeks. It details various construction tasks such as RCC column retrofitting, top tie beam construction, and footing retrofitting, along with specific activities for each task scheduled across the weeks. The schedule includes dismantling, excavation, rebar placement, casting, plastering, and painting for different building components.

Uploaded by

Abdul Jabber
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views

Time Schedule

The document outlines the bar schedule for retrofitting works at Hardy Associates Limited in Gazipur, Bangladesh, starting from August 27 to December 31, 2021, over a duration of 18 weeks. It details various construction tasks such as RCC column retrofitting, top tie beam construction, and footing retrofitting, along with specific activities for each task scheduled across the weeks. The schedule includes dismantling, excavation, rebar placement, casting, plastering, and painting for different building components.

Uploaded by

Abdul Jabber
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

BAR SCHEDULE FOR RETROFITTING WORKS

Factory Name: Hardy Associates Limited . at Chandra, Kaliakoir, Gazipur, Bangladesh


Starting Date 27th August
Closing date: 31st December 2021
Duration: 18 week
Building Item Name of work Mode of Works 1st week 2nd week 3rd week 4th week 5th week 6th week 7th week 8th week 9th week 10th week 11th week 12th week 13th week 14th week 15th week 16th week 17th week 18th week
A).RCC column retrofitting 1. Flloor & brick wall dismantling
2.0 Earth excavation & Surface
3.0 Anchoring &Rebar placement
4.0 Chemical, Shuttering & casting
5.0 Plastering
6.0 Painting
Building-1

B). Construction of top tie beam 1.0 Wall dismantling


2.0 shuttering
3.0 Rebar placement
4.0 Casting
5.0 Shutter removing
6.0 Plastering
7.0 Painting
C). Retrofitting of truss diagonal chord
D). Installation of vertical bracing
E). Roof cable bracing installation
A). Footing retrofitting 1). Prop Installation & Wall dismantling work
2.0 Earth excavation & surface preparation
3.0 Anchoring & rebar placement
4.0 shuttering & casting

B). Column & Shear wall below ground 1). Prop Installation & Wall dismantling work
2.0 Earth excavation & surface preparation
3.0 Anchoring & rebar placement
4.0 shuttering & casting
C). Column & Shear wall ground floor 1). Prop Installation & Wall dismantling work
3.0 Anchoring & rebar placement
Building-4

4.0 shuttering & casting


5.0 Plastering
6.0 Painting
D). Column & Shear wall 1st floor 1). Prop Installation & Wall dismantling work
3.0 Anchoring & rebar placement
4.0 shuttering & casting
5.0 Plastering
6.0 Painting
E). Column & Shear wall 2nd floor 1). Prop Installation & Wall dismantling work
3.0 Anchoring & rebar placement
4.0 shuttering & casting
5.0 Plastering
6.0 Painting