Method Statement for Electrical Infrastructure Works
Method Statement for Electrical Infrastructure Works
This method statement outlines the approach, timelines, activities, sequencing, construction administration, quality
management & health, safety management for the Electrical Infrastructure Works project, estimated to span three years. The
document serves as a comprehensive guide to ensure that all phases of the project are executed efficiently, in compliance with
relevant standards & regulations. The scope includes design, construction, commissioning of substations, transmission lines &
associated civil works.
1. Approach Method
Project Understanding
The electrical infrastructure works involve the construction, and commissioning of substations, transmission lines, cable networks
and associated civil works. The approach method shall be as follows:
Construction Phases
Phase 1: Site Preparation: Clearing and grading of the site, establishing access roads, and setting up site offices.
Phase 2: Civil Works: Construction of foundations, cable trenches, transformer and mini sub Plinths, and substations.
Phase 3: Electrical Installations: Installation of conduits, cable Installation, transformers, switchgear, protective relays.
Phase 4: Testing, commissioning of electrical infrastructure, ensuring it meets performance & safety standards.
Stakeholder Engagement
Community Relations: Engage with local communities to address concerns & ensure minimal disruption
Coordination with Authorities: Maintain regular communication with regulatory bodies & utility companies to ensure
compliance & facilitate smooth project progression.
2. Task-Related Timelines
Project Schedule
A comprehensive Gantt chart will be developed, outlining the start and end dates for each phase of the project, including buffer
periods for unforeseen delays. This can only be achieved once a clearly defined scope of work is agreed upon. The following will
serve as a guide to the consolidated times spent on each activity.
Milestones
Milestone 1: Completion of site preparation and site rehabilitation on completion of works (Month 2).
Contingency Planning
Material Delays: Establish contingency plans with multiple suppliers to mitigate material delays.
Site Preparation
Method Statement for Electrical Doc No:MS10023
Infrastructure Works Rev No:00
Date applicable:18/01/2025
Clearing and Grading: Remove vegetation, debris, and grade the site to the required levels.
Access Roads: Construct temporary and permanent access roads to facilitate the movement of machinery and
personnel.
Site Offices: Set up site offices, storage facilities, and worker amenities.
Civil Works
Foundations: Excavate and construct reinforced concrete foundations for substations and transmission towers.
Cable Trenches: Construct trenches for laying underground cables, ensuring proper drainage and protection.
Transformer Plinths: Build reinforced concrete pads to support transformers and other heavy equipment.
Electrical Installations
Conduit Installation: Install conduits for electrical cables, ensuring proper alignment and secure fittings.
Cable Laying: Lay and terminate high-voltage and low-voltage cables, ensuring compliance with design specifications.
Transformer Installation: Install and secure transformers, switchgear, and protective relays.
Insulation Resistance Tests: Perform insulation resistance tests on all electrical equipment.
High Voltage Tests: Conduct high voltage tests to ensure the integrity of the electrical installations.
Functional Testing: Test the functionality of all equipment and systems before commissioning.
4. Construction Administration
Effective construction administration is essential to ensure that the project is executed according to the plan, within budget
Project Manager: Overall responsibility for project execution, monitoring progress, and stakeholder engagement.
Site Engineers: Supervise on-site activities, ensure compliance with designs and standards, and report progress.
Quality Control Officers: Conduct inspections and tests to ensure quality standards are met.
Documentation
Daily Logs: Maintain daily logs of activities, weather conditions, and incidents.
Communication Plan
Meetings: Hold regular progress meetings with the project team, subcontractors, and stakeholders.
Reporting: Provide weekly and monthly progress reports to the client and regulatory bodies.
5. Quality Management
Quality management ensures that all works meet the required standards & specs, contributing to the overall success of the
project.
Inspection & Testing: Conduct regular inspections, testing of materials, workmanship to ensure compliance with
specifications
Supplier Audits: Perform audits on suppliers to ensure the quality of materials and equipment.
Documentation: Maintain records of all quality control activities, including inspection and test results.
Material Defects Delays and cost overruns Stringent quality control and testing
Workmanship Rework and project delays Regular inspections and skilled training
Errors
Design Errors Non-compliance with standards Detailed design reviews and audits
Non-Conformance Reporting
Corrective Actions: Implement corrective actions to address non-conformances and prevent recurrence.
Health and safety management is critical to protecting workers and ensuring the project adheres to legal and ethical standards.
Risk Assessment
Working at Falls and serious injuries Use of fall protection and training
Heights
Heavy Machinery Accidents and injuries Training and safe operating procedures
Safety Measures
Personal Protective Equipment: Ensure all workers wear appropriate PPE, including helmets, gloves & safety harnesses.
Safety Signage: Install safety signage at critical points to warn of potential hazards.
Safety Drills: Conduct regular safety drills to prepare workers for emergency situations.
Training
Safety Training: Conduct safety training programs for all workers, focusing on hazard recognition and safe work
practices.
Specialized Training: Provide specialized training for workers involved, such as working at heights & electrical
installations.
Safety Inspections: Conduct regular safety inspections to identify and mitigate potential hazards.
Method Statement for Electrical Doc No:MS10023
Infrastructure Works Rev No:00
Date applicable:18/01/2025
Incident Reporting: Implement a system for reporting and investigating incidents, with a focus on preventing
recurrence.
Corrective Actions: Take prompt corrective actions to address safety issues and improve overall safety performance.