JSA FOR PANEL REPLACEMENT
JSA FOR PANEL REPLACEMENT
BLD6-110 Admin,
LOCATION 01/08/2024
KGP ( Khursaniyah gas plant ) DATE
REVIEWED BY APPROVED BY :
Name: Name:
Signature: Signature:
Date: Date:
IPD-JSA-PANEL-001
KHURSANIYAH GAS PLANT
IPD-JSA-PANEL-001
KHURSANIYAH GAS PLANT
Removal of the Old Electrical shock, Wear appropriate PPE including gloves and eye protection.
4 Panel sharp edges, Use proper lifting techniques and tools to handle the heavy panel.
heavy lifting.
CONTRACTOR/OPERATIONS
IPD-JSA-PANEL-001
KHURSANIYAH GAS PLANT
Reconnecting the Mislabeling of circuits leading Carefully label all wires during disconnection. CONTRACTOR/OPERATIONS
6 Circuits to incorrect connections, Verify each connection during the reconnection phase.
electrical shock. Test each circuit individually before full activation.
Testing and Faulty connections, Use appropriate testing equipment to check voltage and continuity. CONTRACTOR/OPERATIONS
Commissioning electrical fires. Have a second qualified electrician review the work.
7 Ensure all circuit breakers are functioning correctly.
Define direction of pulling and check if cable stands are correctly CONTRACTOR/OPERATIONS
Pinch-points, positioned
Caught-in-between,
Cuts, Avoid overexertion
8 Cable Pulling abrasion,
Falls, sufficient manpower shall be provided
Body pains,
Personal injury Frequent breaks/intervals shall be observed.
Observe proper ergonomics CONTRACTOR/OPERATIONS
Personnel positioning adapted to illumination source
9 Cuts/abrasions, Tools/materials shall be kept away from walking areas and removed
Cable Glanding Muscular/joint pains, when unused
Eye strain/headaches,
IPD-JSA-PANEL-001
KHURSANIYAH GAS PLANT
Always use proper PPE and proper tools for the job.
Electrocution, Guaranty that power source is defeated before commencing activity CONTRACTOR/OPERATIONS
Cable Termination Cuts/abrasions, by confirming with concerned personnel.
10 Muscular/joint pains,
Eye injury,
Personal injury
Personnel shall perform housekeeping around his immediate work CONTRACTOR
area prior to leaving and tools to be returned and kept in a safe place
11 House Keeping Fires,
Slips, Equipment’s to be shut down, keys removed, or otherwise batteries
trips, disabled
falls,
Falling from heights, Supervisor/person-in-charge shall, inspect work area to ensure that no
Falling objects equipment’s are left improperly supported or unsupported prior to
close of permit
Rubbish, spoils, combustible materials shall be removed from work area and be
disposed outside of Wasit Plants
IPD-JSA-PANEL-001