STANDARD COSTING ILLUSTRATIVE PROBLEM
STANDARD COSTING ILLUSTRATIVE PROBLEM
Assume that the company manufactures smoked crabs in its Smoking Department with the following
ingredients on a per lot basis:
Material standard:
3,000 pounds of crabs at P5 per pound P15,000
Labor standard:
40 hours at P15 per hour 600
Variable overhead standard:
5 hours at P150 per machine hour 750
(P150 = budgeted monthly variable OH of P15,000 at Budgeted activity
of 100 machine hours)
Fixed overhead standard:
8 hours at P140 per hour of move or wait time 1,120
(P140 = budgeted monthly Fixed overhead of P28,000 at a budgeted
activity of 200 hours)
Total standard Smoking Dept. cost for 1 lot of smoked crabs P17,420
MATERIAL VARIANCES
MPUV = P3,022.50 UF
Adjusted cost (SP x AQ)
P5.00 x 60,450 P302,250
MQV = P2,250 UF
Standard Cost (SP x SQ)
20 lots x 3,000 lbs. = 60,000 P300,000
P5.00 x 60,000
Materials Price Usage Variance (MPUV) = indicates whether the amount paid for material was below or
above the standard price.
Materials Quantity Variance (MQV) = indicates whether the actual quantity used was below or above
the standard quantity allowed for the actual output.
LABOR VARIANCES
LRV = P650 F
Adjusted cost (SP x AQ)
P15 x 1,000 P15,000
LEV = P300 UF
Standard Cost (SP x SQ)
20 lots x 40 hrs per lot = 800 P12,000
hrs
P15 x 800
Labor Rate Variance (LRV) = shows the difference between the actual wages paid to labor for the period
and the standard wages for all hours worked.
Labor Efficiency Variance (LEV) = shows the difference between the actual hours worked and the
standard hours allowed for the production achieved results.
For Variable Factory Overhead (VOH)
VOH Spending Variance – difference of actual VOH and the Budgeted VOH based on actual input activity
rate are often caused by price difference, paying higher or lower prices than standard prices allowed.
VOH Efficiency Variance – difference of budgeted VOH based on actual input activity and applied VOH
quantifies the effect of using actual input which is higher than the standard for the production achieved.
I. If FOH is recorded separately as to variable and fixed
Standard input allowed for the achieved production level- measures capacity utilization for the period.
FFOH Spending variance – difference of actual fixed overhead and the budgeted fixed overhead based
on budgeted input of activity at actual output achieved.
FFOH Volume variance - difference between budgeted and applied fixed overhead. It is caused solely by
producing at a level that differs from that used to compute the predetermined fixed overhead rate.
VOH rate at standard hours allowed based on actual production achieved + FFOH rate at standard hours
allowed based on actual production achieved.
*Budgeted OH
Volume variance – difference between total budgeted overhead based on the standard input allowed for
the actual output achieved and the total applied overhead.
It is the Two Variance method further analyzed into Overhead Spending Variance, Overhead Efficiency
Variance and Volume variance.
Total P41,050
Overhead spending variance – is the difference of total actual overhead and budgeted overhead at the
actual hours of activity.
Overhead Efficiency variance – is related solely to variable overhead and is the difference between total
budgeted overhead at the actual input activity and total budgeted overhead at the standard input
allowed (output activity).
Volume variance - is the amount the same as in the two variance method and also in the four variance
method.