Labor Productivity

The Construction Labour Productivity Guide outlines standard productivity rates for various construction tasks, including earthwork, concreting, formwork, reinforcement, masonry, plastering, flooring, structural steel work, waterproofing, and miscellaneous works. Each category provides specific metrics for output per worker per day, such as excavation rates and concrete placement volumes. This guide serves as a reference for planning and managing construction labor efficiency.

Uploaded by

khaled Ahmed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
267 views2 pages

Labor Productivity

The Construction Labour Productivity Guide outlines standard productivity rates for various construction tasks, including earthwork, concreting, formwork, reinforcement, masonry, plastering, flooring, structural steel work, waterproofing, and miscellaneous works. Each category provides specific metrics for output per worker per day, such as excavation rates and concrete placement volumes. This guide serves as a reference for planning and managing construction labor efficiency.

Uploaded by

khaled Ahmed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

CONSTRUCTION LABOUR PRODUCTIVITY GUIDE

SATISH HAVLE - PLANNING MANAGER

Labour productivity is a crucial factor in construction projects. Below is a reference guide for construction labour
productivity based on industry standards.

1. Earthwork & Excavation


- Excavation (Manual) - Soft Soil: 2.5 - 4.0 CUM per worker per day
- Excavation (Manual) - Hard Soil: 1.5 - 2.5 CUM per worker per day
- Excavation with JCB: 80 - 100 CUM per worker per day
- Earth Filling & Compaction (Manual): 4.0 - 6.0 CUM per worker per day

2. Concreting Work
- Concrete Mixing (Manual): 1.5 - 2.0 CUM per worker per day
- Concrete Placing (PCC/RCC): 3.0 - 5.0 CUM per worker per day
- Concrete Vibrating: 8.0 - 12.0 CUM per worker per day

3. Formwork (Shuttering)
- Column Shuttering: 6 - 10 SQM per worker per day
- Beam & Slab Shuttering: 8 - 12 SQM per worker per day
- Removal of Shuttering: 20 - 25 SQM per worker per day

4. Reinforcement Work
- Rebar Cutting & Bending: 100 - 150 KG per worker per day
- Rebar Fixing: 80 - 120 KG per worker per day

5. Masonry Work
- Brickwork (230 mm thick): 3 - 6 SQM per worker per day
- Blockwork (200 mm thick): 6 - 10 SQM per worker per day

6. Plastering & Finishing


- Internal Plaster (12mm): 8 - 12 SQM per worker per day
- External Plaster (20mm): 5 - 8 SQM per worker per day
- Painting (Primer + 2 Coats): 15 - 25 SQM per worker per day

7. Flooring & Tiling


- Tile Laying (600x600 mm): 10 - 15 SQM per worker per day
- Granite/Marble Laying: 5 - 8 SQM per worker per day

8. Structural Steel Work


- Fabrication: 50 - 100 KG per worker per day
- Erection: 100 - 150 KG per worker per day

9. Waterproofing Work
- Brickbat Coba Waterproofing: 8 - 12 SQM per worker per day
- Membrane Waterproofing: 20 - 30 SQM per worker per day
- Chemical Coating (2 coats): 30 - 50 SQM per worker per day

10. Miscellaneous Works


- Door/Window Fixing (Aluminum): 5 - 8 SQM per worker per day
- False Ceiling (Gypsum): 8 - 12 SQM per worker per day
- Electrical Conduiting & Wiring: 8 - 15 Points per worker per day

#Construction #Productivity #Engineering #ProjectManagement