Labor Productivity
Labor Productivity
Labour productivity is a crucial factor in construction projects. Below is a reference guide for construction labour
productivity based on industry standards.
2. Concreting Work
- Concrete Mixing (Manual): 1.5 - 2.0 CUM per worker per day
- Concrete Placing (PCC/RCC): 3.0 - 5.0 CUM per worker per day
- Concrete Vibrating: 8.0 - 12.0 CUM per worker per day
3. Formwork (Shuttering)
- Column Shuttering: 6 - 10 SQM per worker per day
- Beam & Slab Shuttering: 8 - 12 SQM per worker per day
- Removal of Shuttering: 20 - 25 SQM per worker per day
4. Reinforcement Work
- Rebar Cutting & Bending: 100 - 150 KG per worker per day
- Rebar Fixing: 80 - 120 KG per worker per day
5. Masonry Work
- Brickwork (230 mm thick): 3 - 6 SQM per worker per day
- Blockwork (200 mm thick): 6 - 10 SQM per worker per day
9. Waterproofing Work
- Brickbat Coba Waterproofing: 8 - 12 SQM per worker per day
- Membrane Waterproofing: 20 - 30 SQM per worker per day
- Chemical Coating (2 coats): 30 - 50 SQM per worker per day