26-09-2023
26-09-2023
2. On Level 15 make a foundation for an LPG cylinder with steel and plywood. Also outside
plaster of the lift machine room has been completed. The application of Medium and primer
on the ceiling of the lift machine room has been completed. Two sides of the walls have been
4. On Level 13 Plaster work in Flat # 11 (03 Rooms) has been done. Also cutting and chipping
of the bathroom floor is in progress. In flat # 07 grinding on the ceiling for paint work has
been done.
5. On Level 12-bathroom shuttering of the lintel with steelwork has been finished and is ready
6. On Level 11-bathroom shuttering of the lintel with steelwork has been finished and is ready
to take concrete with dry mix. Also, the Application of fine in flat # 05 has been completed.
Did plaster in Flat # 12 one room only. Did grouting around plumbing works in Flat #
9. On Level 08, repairing AC pipes and plumbing works with C/S mortar is in progress.