The document outlines the construction progress of the King Abdullah Complex (1) - Boys in Riyadh, managed by Al Bawani Co. and AECOM, with a report dated May 14, 2017. It details the manpower, equipment, completed activities, and ongoing tasks, highlighting various construction phases and their respective completion percentages. The report provides a comprehensive overview of the project's status, including excavation, sub-structure work, and electrical installations.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views

c51

The document outlines the construction progress of the King Abdullah Complex (1) - Boys in Riyadh, managed by Al Bawani Co. and AECOM, with a report dated May 14, 2017. It details the manpower, equipment, completed activities, and ongoing tasks, highlighting various construction phases and their respective completion percentages. The report provides a comprehensive overview of the project's status, including excavation, sub-structure work, and electrical installations.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no.

RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 14-May-17
To the Engineer Report no. C51/751
School Name KING ABDULLAH COMPLEX (1) - BOYS School Code C51
Temperature Max : 34°C Min : 20°C Site Hand-Over Day 21-Dec-14
Weather Sunny Cloudy Rainy Humidity High Medium Low

Contractor's Manpower (including Subcontractors)* Plant/Equipment*

Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 1 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 20 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 0 BOBCAT 1
Precast Manager 1 Carpenter 0 Dump Truck 0
Const. Manager 1 Welder 0 Roller/ Compactor 0
Project Control Team 1 Steelfixer 0 Portable Generator 0
QA/QC 1 E/M 4 Mobile Crane 1
Tech. Support 1 Mason 2 Tower Crane 0
Purch & Procurement 1 Painter Loabor 0 Pick up 0
Set. Manager 1 Plastering man 4 Water Tanker 1
Site Engineer 1 labor 28 Welding Machine 0
General Fork Lift
Safety/ HSE 1 1
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 0
Surveyor & Survayor Assistant 1 Bulldozer 0
Guard 1 Levelling Machine 0
Total station 0
Container 2
Water Tank 0
Portacabin 3
Temporary Genset 0

Sub Total/Main 16 59 4

Sub-contractors

Sub Total/Subcon 0 0 0

Grand Total 16 59 4

Activities and Tasks*


COMPLETED ACTIVITIES ON-GOING ACTIVITIES
Percentage
Type of Work Building Name Start Date Finish Date Type of Work Building Name Activity name Start Date Finish Date
Complete
Excavation Electric Room (A) 20-Jul-16 4-Aug-16 Excavation Gate Work (A) Excavation Work 80.00% 5-May-17
Electric Room (B) 7-May-16 10-May-16 Boundary Wall (A) Excavation Work For Boundary Wall 85.00% 7-Jun-16
Guard House (A) 7-May-16 10-May-16 Boundary Wall (B) Excavation Work For Boundary Wall 40.00% 7-Jun-16
Guard House (B) 30-May-16 21-Jun-16 Sub Structure Boundary Wall (A) Bituminous Waterproofing for Boundary Wall 85.00% 10-Oct-16
Site layout (A) 2-Feb-15 13-Aug-15 R.C Concrete Column Neck for Boundary Wall 85.00% 13-Oct-16
Water Tank 22-May-16 5-Jun-16 P.C Concrete for Boundary Wall 85.00% 21-Sep-16
Site layout (B) 11-Jan-15 19-Sep-15 R.C Concrete Footing for Boundary Wall 85.00% 1-Oct-16
Water Tank (B) 22-May-16 5-Jun-16 Boundary Wall (B) P.C Concrete for Boundary Wall 40.00% 21-Sep-16
Sub Structure Main Building (A) - GF 30-Jan-16 24-Jul-16 R.C Concrete Footing for Boundary Wall 40.00% 1-Oct-16
Multi-purpose hall 2-Apr-16 2-Aug-16 Bituminous Waterproofing for Boundary Wall 40.00% 11-Nov-16
Electric Room (A) 26-Jul-16 24-Nov-16 R.C Concrete Column Neck for Boundary Wall 40.00% 1-Oct-16
Electric Room (B) 16-Jul-16 24-Nov-16 Backfilling Site layout (A) Backfilling Level Work ( Landscape ) 35.00% 1-Mar-17
Guard House (A) 27-Jul-16 24-Nov-16 Boundary Wall (A) Backfilling Work for Boundary Wall 85.00% 15-Oct-16
Water Tank 13-Jul-16 26-Apr-17 Site layout (B) Backfilling Level Work ( Landscape ) 20.00% 1-Mar-17
Water Tank (B) 13-Jul-16 28-Mar-17 Boundary Wall (B) Backfilling Work for Boundary Wall 40.00% 7-Nov-16
Backfilling Main Building (A) - GF 30-Apr-16 17-Jul-16 Water Proofing Guard House (A) Membrane Proofing 13.00% 23-Apr-17
Electric Room (A) 20-Aug-16 31-Dec-16 Precast Boundary Wall (A) Precast Concret Columns for Boundary Wall 85.00% 10-Dec-16
Electric Room (B) 9-Aug-16 28-Dec-16 Precast Concret Panels for Boundary Wall 85.00% 5-Dec-16
Guard House (A) 28-Dec-16 13-Mar-17 Boundary Wall (B) Precast Concret Panels for Boundary Wall 40.00% 17-Dec-16
Slab On Grade Main Building (A) - GF 2-Jul-16 3-Aug-16 Precast Concret Columns for Boundary Wall 40.00% 17-Dec-16
Multi-purpose hall 30-Jul-16 13-Aug-16 Block Work Main Building (A) - FF Block Work 95.00% 7-Jan-17
Electric Room (A) 7-Sep-16 1-Jan-17 Main Building (A) - SF Block Work 90.00% 21-Feb-17
Electric Room (B) 28-Aug-16 7-Jan-17 Plaster Main Building (A) - FF Cement Internal Plastering 90.00% 28-Jan-17
Precast Main Building (A) - GF 1-Aug-16 4-Dec-16 Main Building (A) - SF Cement Internal Plastering 75.00% 28-Mar-17
Main Building (A) - FF 29-Aug-16 28-Feb-17 Main Building (B) - FF Cement Internal Plastering 90.00% 22-Jan-17
Main Building (A) - SF 24-Oct-16 27-Mar-17 Main Building (B) - SF Cement Internal Plastering 90.00% 27-Mar-17
Main Building (A) - RF 18-Mar-17 16-Apr-17 Mechanical Main Building (A) - GF Drainage Pipes for Toilets & Testing 70.00% 11-Mar-17
Main Building (B) - GF 9-Aug-16 16-Feb-17 Floor Drain & Clean Out & Testing 70.00% 23-Mar-17
Main Building (B) - FF 29-Aug-16 18-Feb-17 Pipe Fitting & Testing 70.00% 22-Mar-17
Main Building (B) - SF 25-Oct-16 19-Mar-17 HVAC Duct & Testing 80.00% 13-Mar-17
Main Building (B) - RF 1-Mar-17 2-Apr-17 Main Building (A) - FF Drainage Pipes for Toilets & Testing 30.00% 22-Mar-17
Multi-purpose hall 13-Jul-16 19-Jan-17 HVAC Duct & Testing 80.00% 18-Mar-17
Electric Room (A) 14-Sep-16 31-Jan-17 Floor Drain & Clean Out & Testing 30.00% 1-May-17
Electric Room (B) 4-Sep-16 30-Jan-17 Pipe Fitting & Testing 30.00% 5-May-17
Guard House (A) 10-Nov-16 8-Mar-17 Main Building (A) - SF HVAC Duct & Testing 80.00% 19-Mar-17
Block Work Main Building (A) - GF 20-Oct-16 22-Mar-17 Main Building (A) - RF Roof Drain & Testing 50.00% 19-Mar-17
Main Building (B) - GF 18-Nov-16 22-Mar-17 Main Building (B) - GF Drainage Pipes for Toilets & Testing 70.00% 22-Feb-17
Main Building (B) - FF 20-Dec-16 20-Mar-17 Floor Drain & Clean Out & Testing 70.00% 23-Feb-17
Main Building (B) - SF 11-Feb-17 4-Apr-17 Pipe Fitting & Testing 70.00% 23-Feb-17
Plaster Main Building (A) - GF 17-Nov-16 28-Mar-17 HVAC Duct & Testing 80.00% 18-Mar-17
Main Building (B) - GF 10-Dec-16 29-Mar-17 Main Building (B) - FF Drainage Pipes for Toilets & Testing 30.00% 22-Mar-17
Windows Electric Room (A) 17-Apr-17 18-Apr-17 HVAC Duct & Testing 80.00% 20-Mar-17
Electric Room (B) 17-Apr-17 18-Apr-17 Floor Drain & Clean Out & Testing 30.00% 2-May-17
Space Frame Multi-purpose hall 30-Aug-16 8-Jan-17 Pipe Fitting & Testing 30.00% 7-May-17
No R_Type Of Work Electric Room (A) 16-Apr-17 17-Apr-17 Main Building (B) - SF HVAC Duct & Testing 80.00% 19-Mar-17
Electric Room (B) 4-Apr-17 16-Apr-17 Main Building (B) - RF Roof Drain & Testing 50.00% 20-Mar-17
Multi-purpose hall Pipe Fitting 20.00% 21-Mar-17
Drainage Pipes for Toilets 20.00% 19-Mar-17

Page 1 of 2
Floor Drain 10.00% 20-Mar-17
Electrical Main Building (A) - GF Lighting System Second Fix (Wires ) 30.00% 18-Jan-17
Wiring Devices Second Fix (Wires ) 20.00% 19-Feb-17
Data Communications System First Fix (Pipes ) 70.00% 18-Feb-17
Data Communications System Third Fix (Fixtures ) 70.00% 19-Jan-17
IP Telephone System First Fix (Pipes ) 50.00% 19-Jan-17
Main Building (A) - FF Lighting System Second Fix (Wires ) 60.00% 26-Apr-17
Wiring Devices Second Fix (Wires ) 30.00% 1-May-17
Data Communications System Third Fix (Fixtures ) 60.00% 18-Jan-17
IP Telephone System First Fix (Pipes ) 90.00% 18-Jan-17
Main Building (A) - SF Data Communications System First Fix (Pipes ) 80.00% 18-Jan-17
Lighting System First Fix (Pipes ) 40.00% 7-May-17
Lighting System Second Fix (Wires ) 50.00% 27-Apr-17
Wiring Devices First Fix (Pipes ) 80.00% 19-Jan-17
Wiring Devices Second Fix (Wires ) 30.00% 23-Apr-17
Fire Alarm First Fix (Pipes ) 20.00% 29-Apr-17
IP Telephone System First Fix (Pipes ) 80.00% 19-Jan-17
Main Building (A) - RF Lighting System First Fix (Pipes ) 70.00% 2-May-17
Main Building (B) - GF Lighting System Second Fix (Wires ) 20.00% 18-Jan-17
Wiring Devices Second Fix (Wires ) 20.00% 18-Jan-17
IP Telephone System First Fix (Pipes ) 90.00% 18-Jan-17
Main Building (B) - FF Lighting System First Fix (Pipes ) 90.00% 18-Jan-17
Lighting System Second Fix (Wires ) 60.00% 18-Jan-17
Wiring Devices First Fix (Pipes ) 80.00% 2-May-17
Wiring Devices Second Fix (Wires ) 30.00% 18-Jan-17
Fire Alarm First Fix (Pipes ) 50.00% 18-Jan-17
Data Communications System First Fix (Pipes ) 70.00% 18-Jan-17
IP Telephone System First Fix (Pipes ) 50.00% 18-Jan-17
Main Building (B) - SF Data Communications System First Fix (Pipes ) 80.00% 18-Feb-17
Lighting System First Fix (Pipes ) 60.00% 2-May-17
Wiring Devices First Fix (Pipes ) 80.00% 18-Jan-17
IP Telephone System First Fix (Pipes ) 80.00% 18-Jan-17
Main Building (B) - RF Lighting System First Fix (Pipes ) 60.00% 3-May-17
Multi-purpose hall Wiring Devices First Fix (Pipes ) 40.00% 14-Feb-17
Electric Room (A) Wiring Devices First Fix (Pipes ) 90.00% 1-May-17
Electric Room (B) Wiring Devices First Fix (Pipes ) 80.00% 27-Apr-17
Guard House (A) Wiring Devices First Fix (Pipes ) 80.00% 2-May-17
Doors Main Building (A) - GF Hollow Metal Frames 75.00% 26-Feb-17
Hollow Metal Doors 30.00% 13-Apr-17
Main Building (A) - FF Hollow Metal Frames 70.00% 28-Feb-17
Hollow Metal Doors 33.00% 13-Apr-17
Main Building (A) - SF Hollow Metal Frames 40.00% 28-Feb-17
Hollow Metal Doors 30.00% 2-Apr-17
Main Building (A) - RF Hollow Metal Doors 30.00% 12-Apr-17
Hollow Metal Frames 30.00% 12-Apr-17
Main Building (B) - GF Hollow Metal Frames 80.00% 20-Feb-17
Hollow Metal Doors 33.00% 12-Apr-17
Main Building (B) - FF Hollow Metal Frames 70.00% 26-Feb-17
Hollow Metal Doors 33.00% 12-Apr-17
Main Building (B) - SF Hollow Metal Frames 50.00% 1-Apr-17
Hollow Metal Doors 33.00% 12-Apr-17
Main Building (B) - RF Hollow Metal Doors 30.00% 12-Apr-17
Hollow Metal Frames 50.00% 1-Apr-17
Electric Room (A) Hollow Metal Doors 95.00% 16-Apr-17
Electric Room (B) Hollow Metal Doors 95.00% 16-Apr-17
Tiling Main Building (A) - GF Porcelain Tiles 65.00% 27-Mar-17
Main Building (A) - FF Porcelain Tiles 75.00% 8-Apr-17
Main Building (B) - GF Porcelain Tiles 70.00% 26-Mar-17
Main Building (B) - FF Ceramic Tiles for wall 50.00% 11-Feb-17
Porcelain Tiles 75.00% 16-Apr-17
Main Building (B) - SF Porcelain Tiles 30.00% 7-May-17
Ceiling Main Building (A) - GF Acoustical Panel Ceilings 5.00% 19-Feb-17
Main Building (A) - FF Solid Gypsum Ceiling 5.00% 2-Mar-17
Main Building (B) - GF Solid Gypsum Ceiling 10.00% 19-Feb-17
Main Building (B) - FF Solid Gypsum Ceiling 7.00% 21-Feb-17
Paint Main Building (B) - GF Paint preparation 15.00% 7-May-17
Electric Room (A) Paint (1ST Coat) 80.00% 22-Apr-17
Final Coat Paint 50.00% 8-May-17
Electric Room (B) Final Coat Paint 50.00% 6-May-17
Exposed Aggr. Main Building (B) - RF Colour Exposed Aggregate 22.00% 1-May-17
Multi-purpose hall Colour Exposed Aggregate 18.00% 8-May-17

Materials delivered to Site*


Item Unit Qty. Approved submittal reference

Contractor's authorized signatory Engineer's authorized signatory


Name: Mohammad Abdu Name:
Signature: Signature:
Date: 14-May-17 Date: 14-May-17

* This form is to be used by the General Contractor to capture the above required information on a daily basis to report to the
Construction Supervisor (Engineer).