RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 14-May-17
To the Engineer Report no. C51/751
School Name KING ABDULLAH COMPLEX (1) - BOYS School Code C51
Temperature Max : 34°C Min : 20°C Site Hand-Over Day 21-Dec-14
Weather Sunny Cloudy Rainy Humidity High Medium Low
Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 1 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 20 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 0 BOBCAT 1
Precast Manager 1 Carpenter 0 Dump Truck 0
Const. Manager 1 Welder 0 Roller/ Compactor 0
Project Control Team 1 Steelfixer 0 Portable Generator 0
QA/QC 1 E/M 4 Mobile Crane 1
Tech. Support 1 Mason 2 Tower Crane 0
Purch & Procurement 1 Painter Loabor 0 Pick up 0
Set. Manager 1 Plastering man 4 Water Tanker 1
Site Engineer 1 labor 28 Welding Machine 0
General Fork Lift
Safety/ HSE 1 1
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 0
Surveyor & Survayor Assistant 1 Bulldozer 0
Guard 1 Levelling Machine 0
Total station 0
Container 2
Water Tank 0
Portacabin 3
Temporary Genset 0
Sub Total/Main 16 59 4
Sub-contractors
Sub Total/Subcon 0 0 0
Grand Total 16 59 4
Page 1 of 2
Floor Drain 10.00% 20-Mar-17
Electrical Main Building (A) - GF Lighting System Second Fix (Wires ) 30.00% 18-Jan-17
Wiring Devices Second Fix (Wires ) 20.00% 19-Feb-17
Data Communications System First Fix (Pipes ) 70.00% 18-Feb-17
Data Communications System Third Fix (Fixtures ) 70.00% 19-Jan-17
IP Telephone System First Fix (Pipes ) 50.00% 19-Jan-17
Main Building (A) - FF Lighting System Second Fix (Wires ) 60.00% 26-Apr-17
Wiring Devices Second Fix (Wires ) 30.00% 1-May-17
Data Communications System Third Fix (Fixtures ) 60.00% 18-Jan-17
IP Telephone System First Fix (Pipes ) 90.00% 18-Jan-17
Main Building (A) - SF Data Communications System First Fix (Pipes ) 80.00% 18-Jan-17
Lighting System First Fix (Pipes ) 40.00% 7-May-17
Lighting System Second Fix (Wires ) 50.00% 27-Apr-17
Wiring Devices First Fix (Pipes ) 80.00% 19-Jan-17
Wiring Devices Second Fix (Wires ) 30.00% 23-Apr-17
Fire Alarm First Fix (Pipes ) 20.00% 29-Apr-17
IP Telephone System First Fix (Pipes ) 80.00% 19-Jan-17
Main Building (A) - RF Lighting System First Fix (Pipes ) 70.00% 2-May-17
Main Building (B) - GF Lighting System Second Fix (Wires ) 20.00% 18-Jan-17
Wiring Devices Second Fix (Wires ) 20.00% 18-Jan-17
IP Telephone System First Fix (Pipes ) 90.00% 18-Jan-17
Main Building (B) - FF Lighting System First Fix (Pipes ) 90.00% 18-Jan-17
Lighting System Second Fix (Wires ) 60.00% 18-Jan-17
Wiring Devices First Fix (Pipes ) 80.00% 2-May-17
Wiring Devices Second Fix (Wires ) 30.00% 18-Jan-17
Fire Alarm First Fix (Pipes ) 50.00% 18-Jan-17
Data Communications System First Fix (Pipes ) 70.00% 18-Jan-17
IP Telephone System First Fix (Pipes ) 50.00% 18-Jan-17
Main Building (B) - SF Data Communications System First Fix (Pipes ) 80.00% 18-Feb-17
Lighting System First Fix (Pipes ) 60.00% 2-May-17
Wiring Devices First Fix (Pipes ) 80.00% 18-Jan-17
IP Telephone System First Fix (Pipes ) 80.00% 18-Jan-17
Main Building (B) - RF Lighting System First Fix (Pipes ) 60.00% 3-May-17
Multi-purpose hall Wiring Devices First Fix (Pipes ) 40.00% 14-Feb-17
Electric Room (A) Wiring Devices First Fix (Pipes ) 90.00% 1-May-17
Electric Room (B) Wiring Devices First Fix (Pipes ) 80.00% 27-Apr-17
Guard House (A) Wiring Devices First Fix (Pipes ) 80.00% 2-May-17
Doors Main Building (A) - GF Hollow Metal Frames 75.00% 26-Feb-17
Hollow Metal Doors 30.00% 13-Apr-17
Main Building (A) - FF Hollow Metal Frames 70.00% 28-Feb-17
Hollow Metal Doors 33.00% 13-Apr-17
Main Building (A) - SF Hollow Metal Frames 40.00% 28-Feb-17
Hollow Metal Doors 30.00% 2-Apr-17
Main Building (A) - RF Hollow Metal Doors 30.00% 12-Apr-17
Hollow Metal Frames 30.00% 12-Apr-17
Main Building (B) - GF Hollow Metal Frames 80.00% 20-Feb-17
Hollow Metal Doors 33.00% 12-Apr-17
Main Building (B) - FF Hollow Metal Frames 70.00% 26-Feb-17
Hollow Metal Doors 33.00% 12-Apr-17
Main Building (B) - SF Hollow Metal Frames 50.00% 1-Apr-17
Hollow Metal Doors 33.00% 12-Apr-17
Main Building (B) - RF Hollow Metal Doors 30.00% 12-Apr-17
Hollow Metal Frames 50.00% 1-Apr-17
Electric Room (A) Hollow Metal Doors 95.00% 16-Apr-17
Electric Room (B) Hollow Metal Doors 95.00% 16-Apr-17
Tiling Main Building (A) - GF Porcelain Tiles 65.00% 27-Mar-17
Main Building (A) - FF Porcelain Tiles 75.00% 8-Apr-17
Main Building (B) - GF Porcelain Tiles 70.00% 26-Mar-17
Main Building (B) - FF Ceramic Tiles for wall 50.00% 11-Feb-17
Porcelain Tiles 75.00% 16-Apr-17
Main Building (B) - SF Porcelain Tiles 30.00% 7-May-17
Ceiling Main Building (A) - GF Acoustical Panel Ceilings 5.00% 19-Feb-17
Main Building (A) - FF Solid Gypsum Ceiling 5.00% 2-Mar-17
Main Building (B) - GF Solid Gypsum Ceiling 10.00% 19-Feb-17
Main Building (B) - FF Solid Gypsum Ceiling 7.00% 21-Feb-17
Paint Main Building (B) - GF Paint preparation 15.00% 7-May-17
Electric Room (A) Paint (1ST Coat) 80.00% 22-Apr-17
Final Coat Paint 50.00% 8-May-17
Electric Room (B) Final Coat Paint 50.00% 6-May-17
Exposed Aggr. Main Building (B) - RF Colour Exposed Aggregate 22.00% 1-May-17
Multi-purpose hall Colour Exposed Aggregate 18.00% 8-May-17