32. Sample - Cost Plan
32. Sample - Cost Plan
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 2 of 29 02/14/2025
14 February 2025
………………………………………………..………………………………………………………………………
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 3 of 29 02/14/2025
………………………………………………..………………………………………………………………………
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 4 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - ELEMENTAL ANALYSIS 14 Februa
.…………………..………………………………………………………………………………….………………………………………………………………………………………………………………………………………………
Cost Plan 47,683,452 AED Cost Plan 47,683,452 AED Rate/m2 5,186 AED GFA 9,194 m²
Budget 48,000,000 AED Prev. Cost Plan 47,954,225 AED Budget Rate/m2 5,221 AED Prev. GFA 9,194 m²
Variance (316,548) AED Variance (270,772.78) AED Variance (34) AED Variance - m²
Element Element Cost AED AED cost /m² GFA Percentage (%) Remarks
0 Demolitions
0A Downtakings 84,756 9.22 0.18% Demolition works, site clearance, site preparation etc.
0B Alterations 450,000 48.94 0.94%
Demolitions 534,756 58.16 1.12%
1 Substructure
1A Enabling Works 2,219,800 241.44 4.66% Shoring works, dewatering, bulk excavation etc.
1B Foundation Works 4,433,800 482.25 9.30% Main piling, pile caps, ground beams, raft slab, water proofing etc.
1C Substructure 722,890 78.63 1.52% Retaining walls, basement columns, core walls, lift pits etc.
Substructure 7,376,490 802.32 15.47%
2 Structure
2A Frame 1,198,300 130.34 2.51% Concrete beams, columns, core walls etc.
2B Upper Floors 1,897,500 206.38 3.98% Suspended concrete floor slabs etc.
2C Roof 443,000 48.18 0.93% Roof slab, waterproofing works etc.
2D Stairs 179,750 19.55 0.38% Concrete stair cases, finishes, handrails etc.
Structure 3,718,550 404.45 7.80%
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 5 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - ELEMENTAL ANALYSIS 14 Februa
.…………………..………………………………………………………………………………….………………………………………………………………………………………………………………………………………………
Cost Plan 47,683,452 AED Cost Plan 47,683,452 AED Rate/m2 5,186 AED GFA 9,194 m²
Budget 48,000,000 AED Prev. Cost Plan 47,954,225 AED Budget Rate/m2 5,221 AED Prev. GFA 9,194 m²
Variance (316,548) AED Variance (270,772.78) AED Variance (34) AED Variance - m²
Element Element Cost AED AED cost /m² GFA Percentage (%) Remarks
5 Services
5A Sanitary Appliances 765,360 83.25 1.61%
5B Services Equipment 45,000 4.89 0.09% Parking barriers
5C Disposal Installations 625,192 68.00 1.31%
5D Water Installations 526,185 57.23 1.10%
5E Heat Source 60,000 6.53 0.13% Water heaters etc.
5F Air Conditioning 4,018,140 437.04 8.43%
5G Ventilation Systems 287,010 31.22 0.60%
5H Electrical Installations 3,396,285 369.40 7.12%
5I Gas Installations 120,000 13.05 0.25%
5J Lift & Conveyor Installations 900,000 97.89 1.89% Elevators, escalators etc.
5K Protective Installations 880,164 95.73 1.85% Fire detection, fire fighting installations etc.
5L Communication and Security Installations 2,104,740 228.93 4.41% Telephone, data, CCTV etc.
5M Special Installations 450,000 48.94 0.94% BMS
Services 14,178,076 1,542.10 29.73%
6 External Works
6A Site Work 1,054,150 114.66 2.21% Soft and hard landscaping works, boundary wall, gates etc.
6B External Drainage 131,700 14.32 0.28% Surface water drainage, foul water drainage, etc.
6C External Services 807,760 87.86 1.69% External water, fire, gas, electircity, chilled water supply, etc.
6D Minor Building Works 2,179,200 237.02 4.57% Ancillary buildings, alterations to existing buildings etc.
External Works 4,172,810 453.86 8.75%
7 Special Construction
7A Civil defense equipment 650,000 70.70 1.36% Special Civil Defense equipment
Special Construction 650,000 70.70 1.36%
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 6 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - ELEMENTAL ANALYSIS 14 Februa
.…………………..………………………………………………………………………………….………………………………………………………………………………………………………………………………………………
Cost Plan 47,683,452 AED Cost Plan 47,683,452 AED Rate/m2 5,186 AED GFA 9,194 m²
Budget 48,000,000 AED Prev. Cost Plan 47,954,225 AED Budget Rate/m2 5,221 AED Prev. GFA 9,194 m²
Variance (316,548) AED Variance (270,772.78) AED Variance (34) AED Variance - m²
Element Element Cost AED AED cost /m² GFA Percentage (%) Remarks
8 Preliminaries
8A Preliminaries 10.00% 3,940,781.18 428.63 8.26% All Contractor's Facilities - allowance of 10%
Preliminaries 3,940,781 428.63 8.26%
9 Contingencies
9A Contingencies 10.00% 4,334,859 471.49 9.09% Allowed 10% for design and construction contingencies
Contingencies 4,334,859 471.49 9.09%
10 Inflation
10A Inflation 0.00% - - - Included in contingencies
Inflation - - -
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 7 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - ELEMENTAL ANALYSIS 14 Februa
.…………………..………………………………………………………………………………….………………………………………………………………………………………………………………………………………………
Cost Plan 47,683,452 AED Cost Plan 47,683,452 AED Rate/m2 5,186 AED GFA 9,194 m²
Budget 48,000,000 AED Prev. Cost Plan 47,954,225 AED Budget Rate/m2 5,221 AED Prev. GFA 9,194 m²
Variance (316,548) AED Variance (270,772.78) AED Variance (34) AED Variance - m²
Element Element Cost AED AED cost /m² GFA Percentage (%) Remarks
.…………………..………………………………………………………………………………….………………………………………………………………………………………………………………………………………………
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 8 of 29 02/14/2025
14 February 2025
………………………………………………………………………………………………………………………………………………………….…..
Remarks
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 9 of 29 02/14/2025
14 February 2025
………………………………………………………………………………………………………………………………………………………….…..
Remarks
Parking barriers
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 10 of 29 02/14/2025
14 February 2025
………………………………………………………………………………………………………………………………………………………….…..
Remarks
Included in contingencies
Not Included
Not Included
Not Included
Included in construction cost
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 11 of 29 02/14/2025
14 February 2025
………………………………………………………………………………………………………………………………………………………….…..
Remarks
………………………………………………………………………………………………………………………………………………………….…..
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 12 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - AREA SCHEDULE AND FUNCTIONAL AREA ANALYSIS 14 February 2025
...………….……...……………………………………………………….……………………………………………………………………………………...……………………………………….
1. Basement
a. Basement 1,191.00
1,191.00
2. Main Building No
a. Ground 3,655.00
b. First 2,303.00
c. Second 1,920.00
d. Roof 125.00
8,003.00
3. Ancillary Buildings
a. Armory & Pump room 190.00
b. Service block 106.00
c. Car Service 155.00
d. Substation 149.00
e. Security room 64.00
664.00
4. Total Gross Floor Area 9,858.00 m2
...………….……...……………………………………………………….……………………………………………………………………………………...……………………………………….
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A - Page 13 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST TRACK 14 February 2025
……………..……...……………………………………………………….……………………………………………………………………………………...……………………………………….
Concept Cost Plan Schematic Cost Plan Detail Design Cost Plan (AED) Pre Tender Estimate (AED)
Item
Item Description Element Total Element Total Variance from Pre. CP Element Total Variance from Pre. CP Element Total Variance from Pre. CP Remarks
Ref.
(AED) (AED) Amount % (AED) Amount % (AED) Amount %
1. Demolitions 534,756.00
2. Substructure 7,376,489.75
3. Structure 3,718,550.00
4. Architectural and ID Works 8,414,130.00
5. FF&E 363,000.00
6. Services 14,178,076.00
7. External Works 4,172,810.00
8. Special Construction 650,000.00
9. Preliminaries 3,940,781.18
11. Contingencies 4,334,859.29
12. Inflation -
13. Other Project Costs -
14. Total Cost 47,683,452.22
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A - Page 14 of 29 02/14/2025
……………..……...……………………………………………………….……………………………………………………………………………………...……………………………………….
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A - Page 15 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
0. DEMOLITIONS
DOWNTAKINGS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Earthworks
Site clearance m2 12,108 1.00 1.00 12,108.00 7.00 84,756.00
Total 84,756.00
GFA 9,194.00
Rate/m² 9.22
ALTERATIONS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Relocation of electrical cables Item 1.00 1.00 1.00 1.00 450,000.00 450,000.00
Total 450,000.00
GFA 9,194.00
Rate/m² 48.94
1. SUB STRUCTURE
ENABLING WORKS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Excavation
Bulk excavations and cart away m3 4,480.00 1.00 1.00 4,480.00 35.00 156,800.00
Anti termite treatment m2 4,000.00 1.00 1.00 4,000.00 7.00 28,000.00
Dewatering
Setting up item 1.00 1.00 1.00 1.00 25,000.00 25,000.00
Running Months no. 1.00 1.00 1.00 1.00 162,000.00 162,000.00
Removing item 1.00 1.00 1.00 1.00 8,000.00 8,000.00
Shoring & Piling
Secant piles to perimeter 600mm diameter m 230.00 1.00 1.00 230.00 8,000.00 1,840,000.00
Total 2,219,800.00
GFA 9,194.00
Rate/m² 241.44
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 16 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
FOUNDATION WORKS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Bored Piles
Bored Piles 750mm diameter no 275.00 1.00 1.00 275.00 4,800.00 1,320,000.00
Cutting piles no 275.00 1.00 1.00 275.00 350.00 96,250.00
Concrete pile caps Concrete, reinforcement & formwork no 275.00 1.00 1.00 275.00 3,881.25 1,067,343.75
Fill with suitable excavated materials 200mm thick m3 3,102.40 1.00 1.00 3,102.40 15.00 46,536.00
Blinding 50mm thick m3 3,878.00 1.00 1.00 3,878.00 90.00 349,020.00
Concrete raft slab 350mm thick m3 1,100.00 1.00 1.00 1,100.00 1,150.00 1,265,000.00
Construction & Movement Joints item 1.00 1.00 1.00 1.00 15,000.00 15,000.00
Waterproofing to bottom of raft m2 3,878.00 1.00 1.00 3,878.00 50.00 193,900.00
Waterproofing to sides of raft m2 115.00 1.00 1.00 115.00 50.00 5,750.00
Waterproofing m2 1,500.00 1.00 1.00 1,500.00 50.00 75,000.00
Total 4,433,799.75
GFA 9,194.00
Rate/m² 482.25
SUB STRUCTURE Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Concrete retaining wall
Retaining wall m3 230.00 0.30 4.40 303.60 1,150.00 349,140.00
Waterproofing m2 1,012.00 1.00 1.00 1,012.00 50.00 50,600.00
Sundries
Lift pits m3 27.00 1.00 1.00 27.00 1,150.00 31,050.00
Internal ramps m3 44.00 1.00 1.00 44.00 1,150.00 50,600.00
Columns (basement level)
Concrete columns m3 122.00 1.00 1.00 122.00 1,150.00 140,300.00
Core walls to stairs & lift shafts ( basement level)
Concrete walls m3 88.00 1.00 1.00 88.00 1,150.00 101,200.00
Total 722,890.00
GFA 9,194.00
Rate/m² 78.63
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 17 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
2. STRUCTURE
FRAME Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Beams (1 floor)
Concrete beams m3 262.00 1.00 1.00 262.00 1,150.00 301,300.00
Columns (1 level)
Concrete columns m3 385.00 1.00 1.00 385.00 1,150.00 442,750.00
Core walls to stairs & lift shafts
Concrete walls m3 395.00 1.00 1.00 395.00 1,150.00 454,250.00
Total 1,198,300.00
GFA 9,194.00
Rate/m² 130.34
UPPER FLOORS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 1,897,500.00
GFA 9,194.00
Rate/m² 206.38
ROOF Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Roof slab
Concrete slab m3 85.00 1.00 1.00 85.00 1,150.00 97,750.00
Waterproofing m2 275.00 1.00 1.000 275.00 210.00 57,750.00
Roof Beams
Concrete beams m3 250.00 1.00 1.00 250.00 1,150.00 287,500.00
Total 443,000.00
GFA 9,194.00
Rate/m² 48.18
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 18 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
STAIRS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 179,750.00
GFA 9,194.00
Rate/m² 19.55
EXTERNAL WALLS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
External walls above ground floor leve m2 3,467.00 1.00 1.00 3,467.00 140.00 485,380.00
Total 485,380.00
GFA 9,194.00
Rate/m² 52.79
WINDOWS AND EXTERNAL DOORS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 1,015,150.00
GFA 9,194.00
Rate/m² 110.41
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 19 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
INTERNAL WALLS AND PARTITIONS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 1,853,600.00
GFA 9,194.00
Rate/m² 201.61
INTERNAL DOORS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 1,037,500.00
GFA 9,194.00
Rate/m² 112.85
INTERNAL WALL FINISHES Comments Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 1,230,000.00
GFA 9,194.00
Rate/m² 133.78
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 20 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
INTERNAL FLOOR FINISHES Comments Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 1,330,000.00
GFA 9,194.00
Rate/m² 144.66
INTERNAL CEILING FINISHES Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 1,462,500.00
GFA 9,194.00
Rate/m² 159.07
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 21 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
FITTINGS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 113,000.00
GFA 9,194.00
Rate/m² 12.29
FURNITURE AND PLANTS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 0.00
GFA 9,194.00
Rate/m² 0.00
EQUIPMENT Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 250,000.00
GFA 9,194.00
Rate/m² 27.19
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 22 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
5. SERVICES
SANITARY APPLIANCES Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 765,360.00
GFA 9,194.00
Rate/m² 83.25
SERVICES EQUIPMENT Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 45,000.00
GFA 9,194.00
Rate/m² 4.89
DISPOSAL INSTALLATION Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 625,192.00
GFA 9,194.00
Rate/m² 68.00
WATER INSTALLATION Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 526,185.00
GFA 9,194.00
Rate/m² 57.23
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 23 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
HEAT SOURCE Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 60,000.00
GFA 9,194.00
Rate/m² 6.53
AIRCONDITIONING Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
A/C system Chill water by "PAL " m2 9,567.00 1.00 1.00 9,567.00 420.00 4,018,140.00
Total 4,018,140.00
GFA 9,194.00
Rate/m² 437.04
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 24 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
VENTILATION INSTALLATION Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 287,010.00
GFA 9,194.00
Rate/m² 31.22
ELECTRICAL INSTALLATION Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 3,396,285.00
GFA 9,194.00
Rate/m² 369.40
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 25 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
GAS INSTALLATIONS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Allowance for Storage facility Item 1.00 1.00 1.00 1.00 120,000.00 120,000.00
Total 120,000.00
GFA 9,194.00
Rate/m² 13.05
LIFTS & CONVEYOR INSTALLATIONS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Excluding Lifts & Escalators at entrances -
Passenger Elevator included with mall cost no 6.00 1.00 1.00 6.00 150,000.00 900,000.00
Total 900,000.00
GFA 9,194.00
Rate/m² 97.89
PROTECTIVE INSTALLATIONS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 880,164.00
GFA 9,194.00
Rate/m² 95.73
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 26 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
COMMUNICATION & SECURITY INSTALLATIONS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 2,104,740.00
GFA 9,194.00
Rate/m² 228.93
SPECIAL INSTALLATION Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 450,000.00
GFA 9,194.00
Rate/m² 48.94
7. EXTERNAL WORKS
EXTERNAL CIVIL WORKS (SITE WORKS) Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 1,054,150.00
GFA 4,390.00
Rate/m² 240.13
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 27 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
EXTERNAL DRAINGE INSTALLATION Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 131,700.00
GFA 4,390.00
Rate/m² 30.00
EXTERNAL SERVICES Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Water Supply/Irrigation
Piping m2 4,390.00 1.00 1.00 4,390.00 12.00 52,680.00
Pumps, valves etc. m2 4,390.00 1.00 1.00 4,390.00 65.00 285,350.00
Electric Mains
Cables m2 4,390.00 1.00 1.00 4,390.00 37.00 162,430.00
Lighting m2 4,390.00 1.00 1.00 4,390.00 25.00 109,750.00
Tele Communication
Cables m2 4,390.00 1.00 1.00 4,390.00 15.00 65,850.00
Sewer Mains
Piping m2 4,390.00 1.00 1.00 4,390.00 30.00 131,700.00
Total 807,760.00
GFA 4,390.00
Rate/m² 184.00
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 28 of 29 02/14/2025
CONCEPT DESIGN COST PLAN - COST PLAN DATA BASE Rates at: 14 February 2025
MINOR BUILDING WORKS Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Total 2,179,200.00
GFA 664.00
Rate/m² 3,281.93
8. SPECIAL CONSTRUCTION
CIVIL DEFENSE BUILDING Reference Unit Quantity Calculations % Total Qty Rate Dhs Total Dhs
Civil defense equipments Item 1.00 1.00 1.00 0.00% 1.00 650,000.00 650,000.00
Total 650,000.00
GFA 9,194.00
Rate/m² 70.70
Concept Design Cost PLan Ver.-01 07 Jan 2018 Annexure A Page 29 of 29 02/14/2025