Rescue Specialist Unit6a mod 1 Shoring
Rescue Specialist Unit6a mod 1 Shoring
# Shoring system is like double funnel. One needs to collect load thru beams/sheathing, get
it into the post/struts, then distribute safely into the supporting structure below. A heavily
loaded wood post can punch thru a concrete slab etc.
1
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
EXTRICATION OPERATIONS
# Minimum level of lateral strength in any vertical support system SHORING DESIGN
should be 2 % of vertical load, but 10% is desirable where # Weight of Common Bldg Materials
! Reinforced Concrete = 100 PCF
aftershocks are expected. ! Masonry = 125 PCF
! Wood = 35 PCF
! Steel = 400 PCF
! Concrete/Masonry Rubble = 10 PSF/inch
# Trench Shores provide opposing lateral support - to keep # Weight of Common Bldg Construction
! Concrete floors = 90-100 PSF
trench/hole etc. from filling in. Design is normally based on at (lightweight concrete is about 90%)
! Steel beam system/concrete fill slab = 50-70
2
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
! The thickness of rubble/debris on damaged floor must # Normal capacity of undamaged construction:
! One undamaged wood-framed floor will
support one damaged wood floor
also be taken into account. ! One undamaged steel-framed floor will
support one damaged steel floor
! It takes two undamaged reinforced concrete
floors to support one damaged concrete floor
! Thickness of debris from heavy, exterior
# Condition of structure to be supported -concrete beams, solid walls, etc. must also be taken into account
(for URM, this can easily weigh more than a
concrete slab, broken slab, masonry rubble - determines normal story)
# Damaged/Collapsed buildings often contain lateral as well as FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95
! If structure is partly supported by tension structure-like # Difficult to decide on reasonable design load for
damaged structure
system, horizontal forces are often induced in remaining ! Should vertical shoring system support
weight of currently damaged floor, or only
rubble resting on it
structure. ! Multi-story wood bldg that is racked one foot
in 1st story requires 10% stabilizing force (1
! Collapses that have large remaining pieces can be extra ft in 10 ft)
! What add'l force should be allowed for wind
dangerous. Interconnected pieces may depend on each and aftershocks that will occur during Ops
SH-COND
other for support. A complicated balancing act to be
wary about.
! Collapsed structures containing sloped surfaces are
especially difficult, since loads are vertical due to
gravity, but contact surfaces are sloped, and therefore,
vertical and lateral forces induced in shoring are both
very large.
3
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
SHORING CONSIDERATIONS
# Light frame — multi-story bldgs
! Leaning 1st story(ies) may need diagonal
! It is difficult to decide on the design load when a shoring of great capacity
! Wood bldg with crawl spaces that are off
damaged structure is at rest, but of questionable their foudnations may also have upper floors
that nmeed shoring
! Brick veneer is lethal falling hazard, may need
stability. protective tunnel, etc.
- Should vertical shoring support the weight of the # Unreinforced masonry (heavy wall)
! URM walls may be cracked, especially at
corners or peeled, need raker shores
damaged but currently stable floor, or only the ! Cracked walls may need shored openings
! If URM walls have fallen, floors need shoring
! Lean-to/V-shape/pancake patterns may occur
weight of rubble resting on it? ! Large floor planes w/ rubble may have rubble,
lateral flow problem requiring trench-like
- A four story wood building that is offset one foot shoring and close-in shoring
! May need system w/ sheathing/spreader
beams in both vert/lateral directions
in ten in the lower story will require a ten percent SH-COND 2
4
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
5
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
# All wood post systems should have diagonal wood bracing, in north-south and east-west
direction if possible. Bracing should be designed for at least 2%, of the vertical capacity
of the shoring system. (10% if aftershocks are possible.)
6
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
# 4 x 4 posts can be assembled with Ellis Clamps that give them adjustable length. The
failure mode of these assemblies is usually indicated by the crushing of the wood under
the clamps, which gives the system some forgiveness. (If shores 8 ft. or less)
! These shores use more lumber than single posts, but they can be very useful when
working with short 4x4’s.
7
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
Laced Posts
# Four posts may be placed in a square pattern and laced together with 1x4 or 2x4
horizontal and diagonal bracing (laced).
# The strength of each post may then be calculated on the basis of the length/height
between lateral braces (horizontal members)
# Spreader beams and sills may be required to collect and distribute the load, as with any
system.
# The space inside the laced posts may be useful as a safe haven, since it is relatively
strong and one may climb in relatively quickly
8
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
Cribbing
# Multi member lay-up of 4x4 to 8x8 lumber in two or three member per layer configuration.
# Capacity is determined by perpendicular to grain load on sum of all bearing surfaces.
9
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
# Cribs used by contractors (or in short term emergencies) often rely only on the friction
between bearings for lateral strength, not sufficient for aftershocks.
# Individual pieces may be notched like lincoln logs, to provide lateral resistance in addition
to the friction between pieces. Metal clips may also be used to improve lateral strength,
as well as diagonal braces between pairs of cribs.
# Failure is slow, noisy crushing of softer spring wood fibers, which make system very
desirable for unknown loading of US&R work. In order to assure this desirable failure mode
the crib corners must be made by overlapping the individual pieces by three or four inches.
# Solid levels can be placed within the crib to support a jack or spread the load at the ground
level.
# Shrinkage of green lumber will cause crib to shorten and they should be checked daily for
tightness.
# E = 29,000,000 PSI
# Retractable pipe shores are normally adjustable by screw end and/or sleeve and pin. They
may have square steel feet that may even have slope adjustment and nail holes for
attachment.
# Pipe shores used for bracing tilt-up concrete walls come in lengths up to 30 feet and have
rated capacities listed in tables supplied by rental companies.
# Pipe systems are often used with wood spreader beams and sills, which could limit their
capacity. Engineers should be used to design these systems.
10
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
# Vary from about two to more than eight feet long and normally have a rated capacity. They
are intended to support the opposing sides of a trench, with the addition of spreaders &
sheathing
# May be used as initial, unbraced shoring to permit building of more stable system.
# If used as only system they will need to be connected to spreaders at top and bottom and
should be laterally braced.
11
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
12
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
# Light weight aluminum pneumatic piston ram shore which is highly adjustable with ranges
up to 16 ft. They can be configured with various end connections (see below).
# When used in trenches, these shores are initially set with pressurized air. After securing
the shore in place with a large locking nut or steel pins with collar, the safe working load
can range from 20,000 lbs. for four foot shore to 3500 lbs. for ten foot shore. Load charts
for the two leading manufactures are listed in the 1998 rev. of the US&R Structural
Specialist FOG. (Safe loading should be based on Pinned/swivel end connections)
# These shores are used without air in US&R, so as not to apply any sudden pressure to a
damaged structure. The sleeve nut or steel pins are used to adjust length. They may be
included in a system with headers, sole plate, & beam and bracing, but are considered
most useful as individual, temporary shores that allow a braced system to be installed at
reduced risk.
13
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
14
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
15
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
16
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
17
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
18
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
# This type of shoring is needed when one side of a trench has caved in.
# These systems have been successfully used to temporarily raise river levees.
# They must be designed for specific condition of type of load (soil, water) and type of
supporting soil.
SHOR 11-A
19
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
# Need to be configured in system that will account for both vertical and horizontal
components of force in diagonal member (SHOR-12)
# Raker shores should be placed from 8 ft. on center, depending on wall type and condition.
They should be designed by engineers that have experience with these systems.
# Rakers should be built away from dangerous area next to wall and then carried/walked
into place
# Rakers may be configured using the Full Triangle method (sometimes called Fixed raker)
or as a Flying Raker (Friction Raker) (SHOR-12)
# Either configuration (Full Triangle or Flying) could be used on walls up to about 24 ft. high.
Six inch wood members would be required when raker length exceeds 12 ft., unless
midpoint lateral bracing is provided. It is difficult to obtain lumber over 20 ft. long, but
splices may be made in rakers as long as they are located near where the diagonal and
lateral braces connect. (SHOR-14) Use 2x4x3ft min each side of splice, nailed with 8-16d
each side each end.
20
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
21
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
22
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
23
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
# Connection at top of raker should bear on thrust block or notch in wall plate plus thrust
block (SHOR-15). Bearing cut at top is difficult to make a tight fit, but if Raker angle is set
at 45 degrees or 60 degrees, the cut should be relatively easy to repeat. Plywood
scab/gussets should be used to hold this connection together. Connections of Raker to
ground are also shown.
24
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
Raker Shores
# Raker Angle (see SHOR-16) - the angle between the ground and a diagonal (Raker) brace
member should be as small as practicable.
! When the angle is as small as 30 degrees, the horizontal force applied to the wall
is 87% of the force in the diagonal, and the upward force that needs to be resisted
at the wall face is only 50% of the diagonal force.
! When the angle increases to 60O the horiz. is 50%, and the vertical is 87%.
! At 45 degrees the two are equal at 71% of diagonal force.
! The disaster "field" conditions such as need for access, available timber length, or
clearance, may require that the less efficient 60 degree system is the only practical
way to do the bracing.
! One must find the best compromise between structural efficiency and practical
considerations. The simplest to deal with may be 45 degrees (1 to 1) and 60
degrees (1.7 to 1)
25
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
Raker Shores
# The capacity of individual, single Rakers is in the range of 2400 lbs. (2.4k). This is
normally sufficient to brace most masonry or low rise concrete walls up to about 20 ft high.
# The full Triangle Rakers can be configured with a split sole plate (SHOR-17), which is
most useful for bearing on ground. This example shows how a 4 x 4 lumber x 20 ft. long
can be used to brace a 20 ft. wall.
! Lateral bracing is required at mid-height of the 4 x 4 in each direction.
! Overall lateral bracing is required to stabilize the system of Rakers, especially
during aftershocks.
# A second configuration of full Triangle Raker is shown with solid sole plate (SHOR-18).
This is most useful where paving is found next to the wall. It has the same L/D and overall
bracing requirements as the split sole type.
26
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
27
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
28
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
# Can be used to brace concrete tilt-up walls and other reinforced masonry walls.
# The walls would need to be pretty well intact and only in need of bracing, due to
connection failure. (spreading of the load would induce bending moments in the wall).
# Connection of braces to the wall could be by drill-in-anchors and anchorage at the base
could be to a wood curb/pad or slab on grade with a drill-in.
29
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98
# Tiebacks (SHOR-20)
! When URM walls are over thirty feet tall it is probably impractical to attempt to
brace them with raker shores.
! Vertical, or horizontal and vertical strongbacks could be placed on the face of a
hazardous wall and tied across the structure to a floor beam or the opposite side
wall.
! The strongbacks could be made from double 2x6 wood members with the tie being
placed between them. Solid 4x or 6x members could also be used.
! The ties that have been placed by contractors were steel rods with turnbuckles,
bearing washers etc. Cables with come-along could also be used as well as utility
rope, chain, etc. One may need to be creative to obtain an adequate tie, but
climbing rope, used by firefighters should be considered only as a last resort.
(Climbing rope is considered unreliable with the rough treatment of this type of
application and would be discarded)
30
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
31
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
# At the Highway 880 collapse, Loma Prieta Earthquake, shoring contractors used 12x12
vertical posts to support the concrete frames in the first story that were damaged by the
collapse of the second story. The 20 ft. height was too great for cribbing, and a spreader
system was used to interconnect the posts at the ground level. Diagonal bracing was
added to same locations of those rows of posts, but it was very light for the potential load.
32
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
33
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
34
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
! Must consider that rubble will flow into any victim access
trench or tunnel, and close-in vertical and lateral shores
may be required
35
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
36
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
37
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
38
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
EXTRICATION OPERATIONS
! Avoid It — barrier tape around a hazardous area # Have a basic understanding of how
to conduct a proper shoring size-up.
! Identify structural hazards, damage and potential victim COLLAPSE HAZARD MITIGATION
locations. # AVOID IT —
! barrier tape around a hazardous
! Determine the type and placement of shoring systems in leaning brick chimney
# The shoring size-up must be extensive, accurate and continue FEMA US&R RESPONSE SYSTEM
EXTRICATION OPERATIONS
04/95
SHORING SIZE-UP
# Identify structural hazards, damage
and potential victim locations.
! How many victims are trapped and where are they structural hazards, damage and
potential victim location
#
it be confirmed? Extensive, accurate and continuous
throughout the rescue operation
OH-3
39
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
# Six-sided Approach
! Survey all four sides, the top and the bottom of the
entire structure paying particular attention to the
collapse area.
! The top survey is extremely important because loose or
hanging debris, structural elements and other overhead
hazards must be identified and addressed.
! Gravity being constant, will continually try to pull the
remains of the structure and its contents to the ground.
! Surveying the bottom is equally important because
shifted loads created by the collapse must be
transferred to other stable structural members or back to
stable ground. FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95
EXTRICATION OPERATIONS
40
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
SHORING PLACEMENT
41
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
EXTRICATION OPERATIONS
interfere with the removal of the victim(s).
! All loads transferred to earth or other suitable structural SHORING PLACEMENT
# The area directly underneath the
element capable of handling the additional load require victim(s) and rescue forces
the shoring systems(s) to be located where they will # Shoring system(s) must be located
where they will not interfere with the
removal of the victim(s)
bear on each other. This is sometimes accomplished by
# All loads transferred to earth by
aligning the shoring systems on top of each other aligning the shoring systems on top
of each other between floors or
#
!
Create safe zones and safe
Access into the building may require shoring to be passageways
42
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
! Establishes the equipment area and cuts the shoring FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95
43
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
44
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
! The Measurer
! Shorer
[these two work together assembling
! Shorer and erecting shores in place]
! Safety
! Runner — ensures tools, equipment and shoring FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95
materials are moved from the shoring operation primary EXTRICATION OPERATIONS
access point to the shoring site and assists in the THE SHORING TEAM
# Cutting Team with a complete six person Rescue Squad: 3) Shorer 3) The Feeder
! The Cutting Team Officer (Rescue Squad Officer) 4) Shorer 4) The Cutter
5) Safety 5) Tools/Equipment
OH-8
! The Cutter
45
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# The main purpose of the vertical shore is to stabilize damaged floors, ceilings or roofs. It
can also be used to replace missing or unstable bearing walls or columns.
46
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
47
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# Lay the sole plate on the floor or ground directly under and in
line where the header will be installed.
! The sole plate should be as level as possible.
48
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# Install the posts between the header and sole plate under each
structural element to be supported.
! The first two posts are installed at opposite ends at least
12” in from each end of the sole plate.
! Keep the posts in line and plumb with the header and
sole plate.
# Install a set of wedges under the bottom of each post and tap
them together simultaneously until the posts are under
compression and tight.
! Nail behind the wedges to secure them in place.
49
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
The main purpose of the horizontal shore is to stabilize a damaged wall against an undamaged
wall in hallways, corridors or between buildings.
50
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
51
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
# Place both wall plates next to each other and attach cleats to
the wall plates just below where the struts will be installed.
# Install the struts between the wall plates. Keep the struts in
line and plumb with the wall plates.
52
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
# Install a set of wedges under one end of each strut and tap
them together simultaneously until the struts are under
compression and tight.
53
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# The main purpose of the window and door shore is to stabilize a window, doorway or other
access way. An extensive collapse can generate a tremendous amount of debris blocking
the primary entrances into a building and sometimes require a window entry.
54
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
55
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# Measure and cut the sole plate to the proper length deducting
the width of the wedges to be used.
# Measure and cut the header to the proper length deducting the
width of the wedges to be used.
56
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# Install the sole plate with a set of wedges at one end and tap
them together simultaneously until the sole plate is under
compression and tight.
! The sole plate should be as level as possible, use shims
as necessary under the sole plate.
# Install the posts between the header and sole plate and against
the sides of the opening.
! Install the first post under the wedge side of the header
to prevent accidental movement if the header wedges
loosen up.
! Keep the posts in line and plumb with the header and
sole plate.
! A set of wedges is installed under each post, on top of
the sole plate. The wedges are then tightened to lock
the shore in place.
# Install diagonal braces on the window and door shore when the
opening is not used for access or egress.
57
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
The main purpose of the raker shore is to support leaning or unstable walls and columns by
transferring additional weight down the raker, to the ground or other structural supporting
members, and away from the wall or column.
58
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
# The two types of (Full Triangle) Fixed Raker Shores are the
solid sole plate and the split sole plate.
! The Solid Sole Plate (Full Triangle) Fixed Raker Shore
(CSS O/H-13) — utilized more in urban environments
where concrete/asphalt commonly cover the ground.
! The Split Sole Plate (Full Triangle) Fixed Raker Shore
(CSS O/H-14) — utilized more in suburban
environments where open ground is available.
59
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
60
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
61
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
62
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
63
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
64
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
# The Top Cleat — short two foot piece of 2”X lumber nailed to
the top of the wall plate to keep the raker from riding up the wall
plate.
65
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
66
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
# Diagonal Braces —diagonal braces increase the strength of the raker by reducing the
L/D ratio.
! The diagonal braces should be long enough to reach from the wall plate and sole
plate connection to near the mid point of the raker.
! On the solid sole raker shore, a 2” X 6” or two 2” X 4” are nailed to both sides of the
wall plate and sole plate connection and mid point on the raker.
! On the split sole raker shore, a 2” X 6” or two 2” X 4” are nailed to both sides of the
wall plate and just above the bottom braces connection and mid point on the raker.
# Bottom Braces — on split sole raker shores, a 2” X 6” or two 2” X 4” are nailed just
above the ground and attached as close to the bottom of the raker as possible and the
bottom of the wall plate with a fill block near the middle for additional stability.
! Placed at the bottom of the wall plate and along the raker above the ground on the
(Flying) Friction Raker Shore.
# Horizontal Braces — horizontally connects the raker shores together near the top and
bottom of the raker to provide additional stability to the raker shore system.
! Horizontal braces attached to the mid point of the raker increase the strength of the
raker by reducing the L/D ratio.
# “X” and “V” Braces — connects the raker shores in a “X” or “V” pattern near the bottom
and middle of the raker depending on access needs and available lumber.
! Provides additional stability to the raker shore system and decreases the lateral
movement when at least a pair are used at the beginning and end of the raker
shore system.
67
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
# Backing Material —
! Plywood (Full and Half Sheets) require a minimum of 3/4” or two 1/2” sheets of
plywood nailed together.
! 2” X Lumber (2” X 8, 10” & 12”)
! Nailed to the back of the wall plate can help distribute the weight of the wall over
a wider area and prevent the wall plate from pushing through an unstable wall.
! Very useful on unreinforced masonry (URM)
! Nailed to the back of the sole plate can help distribute the weight of the wall over
a wider area and prevent the sole plate from pushing into soft or muddy soil.
! Backing material must contact the wall at the raker support point and at the bottom
of the wall plate.
! Shims may be needed to fill void spaces.
! Backing material can be used to attach the wall plate to the wall or sole plate to the
ground.
# Determine where to erect the raker shores and the height of its support points.
! After initial temporary shoring has been installed as needed, clear the area of
debris.
! Three to four feet wide and at least the height of the support point out from the wall
or column.
# Measure and cut the wall plate to the proper length, if needed.
# Measure, cut the top cleat and attach it to the top of the wall plate with at least 16-16d
nails.
! The top cleat is usually 2” X lumber two feet long for rakers at 45 degree angles or
less.
! The top cleat is usually 2” X lumber three feet long with 24 to 36-16d nails for
rakers at 60 degree angles.
! Another method for 60 degree angle rakers is to use the two foot cleat with 16-16d
nails and cut a 1” deep notch just below the location for the bottom of the cleat.
Length of the notch will be two times the width of the raker (8” for 4” X 4” and 12”
for 6” X 6”).
68
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
! The longer cleat with more nails or the notch below the two foot cleat are required
because of the greater vertical forces applied to rakers at 60 degree. angles.
# Measure and cut the raker to the proper length and angle to reach the support point.
! Solid sole raker shores need both ends of the raker to be angle cut with 1 1/2”
return cuts for full contact with the wall plate, top cleat, sole plate and wedges.
! Split sole raker shores only one end need one end of the raker to be angle cut with
a 11/2” return cut for full contact with the wall plate and top cleat.
! The other end of the raker will contact the short sole plate dug into the ground at
a 30 to 45 degree angle.
# Measure and cut the sole plate to the proper length, if needed.
! The solid sole raker shore sole plate must extend from the wall plate several feet
past the point at which the raker intersects at the floor.
! The split sole raker sole plate is approx. two ft long.
# Place the wall plate against the area to be shored and plumb up in both directions.
! If the area is bulged or cracked due to the strain exerted by the collapse debris, the
wall plate may need to be shimmed.
! Full contact must be maintained between the base of the wall plate and the area
being shored.
! Full contact must also be maintained between the wall plate and the support point
of the raker.
# Attach the sole plate to the bottom of the wall plate with gusset plates and nails on both
sides on solid sole raker shores.
! The wall plate and sole plate should be as level, plumb and at right angles to each
other.
! Attach the sole plate to the floor if possible and use shims as necessary to keep it
level.
! Split sole raker shores require a shallow hole dug at a 30 to 45 degree angle for the
sole plate and raker to push against.
69
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
# Install the raker by gently lowering it onto the wall plate and sliding it up into position under
the top cleat.
! The ends of the raker should be flush and in full contact with the wall plate, top
cleat and sole plate.
! Attach the top of the raker to the wall plate with gusset plates and nails on both
sides.
# On the solid sole raker shore, attach the bottom cleat to the sole plate just behind the base
of the raker with room left to apply wedges.
! On the split sole raker shore, the bottom cleat is attached to the short sole plate on
top of the bottom end of the raker after the raker shore is tightened with wedges.
# On the solid sole raker shore, install wedges between the bottom cleat and the base of the
raker and tighten them slightly.
! After adjusting the shims or spacers between the wall plate and the object being
shored to ensure full contact with the support point and the raker and the bottom of
the wall plate, finish tightening the wedges.
# Secure all wedges by placing a cleat against the sides of the wedges and nail it in place
or toe nail the wedges.
! Nails may need to be Duplex for future adjustment of the wedges.
70
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
# After the raker shore is assembled, prevent the raker shore from sliding up the wall. (CSS
O/H-17)
! To attach the wall plate directly to a concrete and masonry wall.
- a minimum of two 1/2” drill-in anchors, lag screws or rebar should be placed
through the wall plate or four 1/2” drill-in anchors through two 9” long
channel brackets attached with two on each side of the wall plate near the
top.
- on concrete walls only, when backing material is attached to the wall plate,
the use of at least five 3” powder charge pins with washers through the
backing material on each side of the raker is acceptable.
71
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98
72
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# After the solid sole raker shore is assembled, prevent the sole
plate from sliding back away from the wall.
! To attach the sole plate directly to concrete, asphalt or
dirt. Drill a minimum of two 1” holes through the sole
plate, concrete or asphalt and pound 1” steel pickets or
rebar directly into the ground.
! To attach the sole plate to concrete and masonry.
- a minimum of two 1/2” drill-in anchors, lag screws
or rebar should be placed through the sole plate
or four 1/2” drill-in anchors through two 9” long
channel brackets attached with two on each side
of the sole plate.
- on concrete only, when backing material is
attached to the sole plate, the use of at least five
3” powder charge pins with washers through the
backing material on each side of the sole plate is
acceptable.
! An anchor can be secured to the ground or floor behind
the sole plate to prevent the sole plate from backing
away from the wall.
- timber anchors should be as least 4” X 4” size
lumber.
- steel anchors or channel brackets should be at
least 1/4” thick.
- concrete curbs, walls and other nearby secure
structures may also be used.
73
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
74
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
75
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
76
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# Horizontal Shore with two struts, using at least one lumber strut
with gusset plates or cleats connecting the strut to the wall
plates and one pipe screw jack.
! Cleats should be attached to the wall plates under the
struts where appropriate.
! Diagonal braces are mentioned but not attached.
77
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# The use of same dimension lumber for the headers, wall plates,
sole plates, posts and struts will ease in the construction of the
shoring systems and make the braces more effective.
78
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
79
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
80
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# The use of same dimension lumber for the wall plates, rakers
and sole plates will ease in the construction of the shoring
systems and make the braces more effective.
81
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
82
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# The tongue:
! Shorter, narrower part is usually 16" long and 1½ wide.
# The Heel:
! The point where the tongue and the body meet on the
outside edge.
# The Face:
! The side with the manufacturer’s stamp.
! The side that is visible when the body is held in the left
hand and the tongue in the right hand.
# The Back:
! Opposite of the face.
83
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
84
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
85
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
86
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
Using the Steel Framing Square to Determine the Length of A Raker (continued)
87
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
88
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
89
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
90
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# Explain how the Shore Assembly Team “Measure” will relay the
size and length of material to cut and that number will already
account for the thickness of the header, sole plate and wedges.
The “Cutter” simply cuts what is requested.
# Always mark the length of cut lumber on the lumber, for quicker
identification and installation of the correct piece of shoring
material.
# The cutting team will mark and cut two pair of field wedges.
! Cut one pair with a Rotary Saw
! Cut the other pair with a Chain Saw
91
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# The cutting team will mark and cut the end of a rake at 45
degrees and after cutting the angle end cut off the rake, they
will cut the end of the rake at 60 degrees.
92
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# Notched Cribbing
! Mark 2” from the end of the cribbing to prevent the end
piece from splitting off.
! From the 2” mark, make a second mark the true
thickness of the lumber being used for cribbing.
- 4” X 4” = 3½ ” - 6” X 6” = 5 ½”
! Adjust a circular saw to the depth of 1” and cut the two
lines and then between the two lines every 1/2” inch.
! Ensure saw is unplugged while adjusting blade depth.
! Hit the sliced pieces of lumber with a hammer towards
the remaining cribbing to break off the pieces.
! Clean out the notch with the claw end of the hammer
until smooth.
! Have one of the squad members repeat this process on
the opposite end of the cribbing.
! Notches should only be made on one side of the
cribbing to maintain the thickness/strength of lumber.
93
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
94
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
2 Cleats, 2” X 4” X 12”
2 Plywood gusset plates,12” X 12” X 3/4” thick
4 Plywood gusset plates, 6” X 6” X 3/4” thick
2 Triangle gusset plates, 12” X 12” X 17”
2 Wedges, 4” X 4” X 18”
2 Wedges, 2” X 4” X 12”
6 Cribbing, 4” X 4” X 18”
2 Plywood Sheets, 4’ X 8’ X 3/4” thick
6 2” X 4” X 8’
6 4” X 4” X 8’
6 Wooden Pallets
95
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
96
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# The three squads will rotate through all three scenarios in the
following order:
1 A B C
2 C A B
3 B C A
97
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
98
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
99
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
# The four shoring sites will be reviewed first and the equipment
and cutting station will be reviewed last.
# One solid sole raker shall be brought from the Raker shore
Work Station and assembled at the location where the raker
shore system will start.
! The remaining raker shores will be left pre-constructed
and in tact at the Raker Shore Work Station.
100
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
Plywood
Gussets 12" X 12" X 3/4" . . . . . . . . . . . . 128
Wooden
Pallets . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 each
Radios . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
101
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
Tri-Square .............. 2
Speed Square .............. 2
Steel Framing Square . . . . . . . . . . . . . . 4
Chalk Lines .............. 2
Utility Razor Knife .............. 3
Cats Paw Nail Puller .............. 2
Container for pulled nails- can, box, ? . . . 3
Ellis Clamps .............. 12
Ellis Jacks .............. 2
Ellis Post Screw Jacks . . . . . . . . . . . . . . 4
Shovel, Round Point .............. 2
Pipe Screw Jacks, 2" .............. 6
Pipe, 2", Schedule 40, 10 foot section . . . 2
Pipe Cutter, 2" capabililty . . . . . . . . . . . . . 1
High Lift Jack with Ext. Tubes . . . . . . . . . 2 each
102
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94
103