0% found this document useful (0 votes)
5 views103 pages

Rescue Specialist Unit6a mod 1 Shoring

The FEMA US&R Response System Rescue Specialist Training Manual outlines the principles and design considerations for shoring during extrication operations. Shoring provides temporary support for damaged structures to ensure safety during search and rescue efforts, requiring careful calculation of loads and stability. The manual details various shoring systems, including wood post systems and cribbing, emphasizing the need for lateral bracing and adjustable components to accommodate shifting loads.

Uploaded by

Comandante Nuno
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views103 pages

Rescue Specialist Unit6a mod 1 Shoring

The FEMA US&R Response System Rescue Specialist Training Manual outlines the principles and design considerations for shoring during extrication operations. Shoring provides temporary support for damaged structures to ensure safety during search and rescue efforts, requiring careful calculation of loads and stability. The manual details various shoring systems, including wood post systems and cribbing, emphasizing the need for lateral bracing and adjustable components to accommodate shifting loads.

Uploaded by

Comandante Nuno
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 103

FEMA US&R RESPONSE SYSTEM

RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

BASIC DEFINITION AND PRINCIPALS

Shoring is normally the temporary support of structures during construction, demolition,


reconstruction, etc. in order to provide the stability that will protect property as well as workers
and the public.

SHORING FOR US&R IS THE TEMPORARY SUPPORT OF ONLY THAT PART OF A


DAMAGED, COLLAPSED, OR PARTLY COLLAPSED STRUCTURE THAT IS REQUIRED FOR
CONDUCTING SEARCH AND/OR RESCUE OPERATIONS AT REDUCED RISK TO THE
VICTIMS AND US&R FORCES

# Shoring system is like double funnel. One needs to collect load thru beams/sheathing, get
it into the post/struts, then distribute safely into the supporting structure below. A heavily
loaded wood post can punch thru a concrete slab etc.

1
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

BASIC DEFINITION AND PRINCIPALS (continued)


# Shoring should be built as a system that has the following:
! Header beam, wallplate, other element collects load
! Post or other load carrying element that has adjust
ability and positive end connections
! Sole plate, bearing plate, or other element to spread the
load into the ground or other structure below.
! Lateral bracing to prevent system from racking
(becoming parallelogram), and prevent system from
buckling (moving sideways).
! Built-in forgiveness (will give warning before failure)
Example: If vertical shore is proportioned properly,
(posts with length to width ratio of 25 or less) one
can hear the header or sole crush against the post
prior to the post starting to fail. FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95

EXTRICATION OPERATIONS

# Minimum level of lateral strength in any vertical support system SHORING DESIGN
should be 2 % of vertical load, but 10% is desirable where # Weight of Common Bldg Materials
! Reinforced Concrete = 100 PCF
aftershocks are expected. ! Masonry = 125 PCF
! Wood = 35 PCF
! Steel = 400 PCF
! Concrete/Masonry Rubble = 10 PSF/inch

# Trench Shores provide opposing lateral support - to keep # Weight of Common Bldg Construction
! Concrete floors = 90-100 PSF
trench/hole etc. from filling in. Design is normally based on at (lightweight concrete is about 90%)
! Steel beam system/concrete fill slab = 50-70

least half the pressure of water (equivalent fluid weight of at PSF


! Wood floor = 10-25 PSF (may have concrete
fill)
least 30PSF per ft. of depth, PCF) ! Add 10-15 PSF for wood/metal inter. walls
! Add 10+ PSF for furniture (each floor)

CONSIDERATIONS FOR DESIGN AND SELECTION SH-DES

# WEIGHTS OF COMMON BUILDING MATERIALS.


! Concrete = 150 PCF PCF = lbs per cubic ft
! Masonry = 125 PCF PSF = lbs per square ft
! Wood = 35 PCF
! Steel = 490 PCF
! Conc/Masonry Rubble=10PSF PER INCH (of thickness)

# WEIGHTS OF COMMON BUILDING CONSTRUCTION


! Concrete floors weigh from 90 to 150 PSF
! Steel beam w/ concrete-filled metal deck = 50-70PSF
! Wood floors weigh from 10 to 25 PSF (floors w/ thin
concrete fill are 25 PSF or more)
! Add 10 to 15 PSF for wood or metal stud interior walls,
each floor level
! Add 10 PSF or more for furniture/contents each floor
(more for storage, etc.)

2
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

BASIC DEFINITION AND PRINCIPALS (continued)

# Normal capacity of undamaged, existing construction.


! One undamaged wood or steel framed floor will support
one damaged floor FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95

! It normally takes two undamaged concrete floors to EXTRICATION OPERATIONS

support one damaged floor GENERAL RULES OF THUMB

! The thickness of rubble/debris on damaged floor must # Normal capacity of undamaged construction:
! One undamaged wood-framed floor will
support one damaged wood floor
also be taken into account. ! One undamaged steel-framed floor will
support one damaged steel floor
! It takes two undamaged reinforced concrete
floors to support one damaged concrete floor
! Thickness of debris from heavy, exterior
# Condition of structure to be supported -concrete beams, solid walls, etc. must also be taken into account
(for URM, this can easily weigh more than a
concrete slab, broken slab, masonry rubble - determines normal story)

spreading system needs. # Useful information for shoring multi-story bldgs,


it assumes that the shoring is placed over beams,
etc., and in multi-level shoring that the shoring
aligns from story to story

# The condition of foundation/support of shoring - solid/soft SH-RULE

ground, slab on ground, floor over basement below, rubble,


number of un-damaged stories below, determines extent of
system.

# Availability of shoring materials - pre-plan, local contractors,


foreign location.
! For collapsed structures want light, portable, adjustable,
reliable, and forgiving shoring system.

# Damaged/Collapsed buildings often contain lateral as well as FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95

vertical instability. EXTRICATION OPERATIONS

! Building with cracked (damaged) and out of plumb SHORING SELECTION


walls/columns require lateral support in proportion to # Total load of structure easily calculated:
! Don't know where load is concentrated
the offset story, (as much as 20 % of weight of ! Similar to mine collapse — unknown arch
action
! Shoring system must give overload warning
building). ! Brittle failure mode is very undesirable

! If structure is partly supported by tension structure-like # Difficult to decide on reasonable design load for
damaged structure
system, horizontal forces are often induced in remaining ! Should vertical shoring system support
weight of currently damaged floor, or only
rubble resting on it
structure. ! Multi-story wood bldg that is racked one foot
in 1st story requires 10% stabilizing force (1
! Collapses that have large remaining pieces can be extra ft in 10 ft)
! What add'l force should be allowed for wind

dangerous. Interconnected pieces may depend on each and aftershocks that will occur during Ops

SH-COND
other for support. A complicated balancing act to be
wary about.
! Collapsed structures containing sloped surfaces are
especially difficult, since loads are vertical due to
gravity, but contact surfaces are sloped, and therefore,
vertical and lateral forces induced in shoring are both
very large.

3
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

BASIC DEFINITION AND PRINCIPALS (continued)

! Total load of structure above can be relatively easily


calculated, but where individual load concentrations are
being applied is often difficult to determine. A shoring
system that will give warning of overload is therefore FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95

most desirable. EXTRICATION OPERATIONS

SHORING CONSIDERATIONS
# Light frame — multi-story bldgs
! Leaning 1st story(ies) may need diagonal
! It is difficult to decide on the design load when a shoring of great capacity
! Wood bldg with crawl spaces that are off
damaged structure is at rest, but of questionable their foudnations may also have upper floors
that nmeed shoring
! Brick veneer is lethal falling hazard, may need
stability. protective tunnel, etc.

- Should vertical shoring support the weight of the # Unreinforced masonry (heavy wall)
! URM walls may be cracked, especially at
corners or peeled, need raker shores
damaged but currently stable floor, or only the ! Cracked walls may need shored openings
! If URM walls have fallen, floors need shoring
! Lean-to/V-shape/pancake patterns may occur
weight of rubble resting on it? ! Large floor planes w/ rubble may have rubble,
lateral flow problem requiring trench-like
- A four story wood building that is offset one foot shoring and close-in shoring
! May need system w/ sheathing/spreader
beams in both vert/lateral directions
in ten in the lower story will require a ten percent SH-COND 2

stabilizing force, but what additional force should


be allowed for wind or aftershock?

VERTICAL SHORING SYSTEMS

# These systems are primarily intended to provide vertical


support, but should all have some lateral bracing for stability.
(2% min., 10% reasonable) However, often, individual vertical
supports are initially installed without lateral bracing, in order
reduce risk while constructing a well braced system.

Wood Post Systems

# Unless very short, post strength depends on buckling and


varies relative to its length and the modulus of elasticity (E).
! Square Posts P/A allow = .3E/(L/D) squared

! Round Posts P/A allow = .23E/(L/D) squared.

! (E varies from 1M to 1.8M PSI depending on wood


species. P/A = compression stress) PSI=lbs/sq inch

! (L = Length, D = Least width or Dia., L/D max = 50)


As stated on pg. 2, if want to hear warning of failure, it
is better to limit L/D of posts in vertical shores to 25.
Example 4x4 max. length = 50x3.5 =175" = 14.5ft
4x4 length for L/D of 25 = 25x3.5 = 88" = 8ft

4
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

VERTICAL SHORING SYSTEMS

Wood Post Systems (continued)

# The strength of a wood post system is determined by:


! Perpendicular to grain bearing on the header or sole
plate (allowable bearing stress varies from 300 PSI to
700PSI depending on wood species.
! Vertical capacity of the posts.
! Strength of header beam and/or sole plate.
! Strength of ground or structure below sole plate.
! If posts are kept short (8 ft for 4x4, 12 ft for 6x6) the
system will give warning of failure by crushing the softer
crossgrain (spring wood) at the bearing of the post on
the sill or header.

# Douglas Fir or Southern Pine are the most common types of


structural timber used in the U.S. Average values for these
species are:
! E = 1,600,000 PSI
! Compression parallel to grain = 1100 PSI
! Compression perpendicular to grain = 600 PSI

# These systems are normally made adjustable by cutting and


shimming with full bearing, opposing wood wedges. All posts
should be positively attached at top and bottom, using plywood
gussets or metal clips. This requirement must be considered
along with the need to readjust the shims when making the
connections.

# The capacity of header beam and sole plate are determined by


bending an/or horizontal shear strength. Average values for
Douglas Fir and Southern Pine are:
! Fb = extreme fiber bending stress = 1500 PSI
! Fh = horizontal shear stress = 90 PSI

# The capacity of a system supported on the ground may be


limited by the soil bearing capacity and transverse spreading
of load may be desirable to avoid excess settlement.

5
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

VERTICAL SHORING SYSTEMS

Wood Post Systems (continued)

# All wood post systems should have diagonal wood bracing, in north-south and east-west
direction if possible. Bracing should be designed for at least 2%, of the vertical capacity
of the shoring system. (10% if aftershocks are possible.)

6
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

VERTICAL SHORING SYSTEMS (continued)

Wood Post Systems (continued)

# 4 x 4 posts can be assembled with Ellis Clamps that give them adjustable length. The
failure mode of these assemblies is usually indicated by the crushing of the wood under
the clamps, which gives the system some forgiveness. (If shores 8 ft. or less)
! These shores use more lumber than single posts, but they can be very useful when
working with short 4x4’s.

7
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

VERTICAL SHORING SYSTEMS (continued)

Wood Post Systems (continued)


# Metal, adjustable post feet for 4 x 4 & 6 x 6 are made by Ellis and called Screw Jacks. The
foot base plate has nail holes for positive attachment.

Laced Posts
# Four posts may be placed in a square pattern and laced together with 1x4 or 2x4
horizontal and diagonal bracing (laced).
# The strength of each post may then be calculated on the basis of the length/height
between lateral braces (horizontal members)
# Spreader beams and sills may be required to collect and distribute the load, as with any
system.
# The space inside the laced posts may be useful as a safe haven, since it is relatively
strong and one may climb in relatively quickly

8
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

VERTICAL SHORING SYSTEMS (continued)

Cribbing
# Multi member lay-up of 4x4 to 8x8 lumber in two or three member per layer configuration.
# Capacity is determined by perpendicular to grain load on sum of all bearing surfaces.

9
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

VERTICAL SHORING SYSTEMS (continued)

# Stability is dependent on height to width of crib and should not exceed 3 to 1.

# Cribs used by contractors (or in short term emergencies) often rely only on the friction
between bearings for lateral strength, not sufficient for aftershocks.

# Individual pieces may be notched like lincoln logs, to provide lateral resistance in addition
to the friction between pieces. Metal clips may also be used to improve lateral strength,
as well as diagonal braces between pairs of cribs.

# Failure is slow, noisy crushing of softer spring wood fibers, which make system very
desirable for unknown loading of US&R work. In order to assure this desirable failure mode
the crib corners must be made by overlapping the individual pieces by three or four inches.

# Solid levels can be placed within the crib to support a jack or spread the load at the ground
level.

# Shrinkage of green lumber will cause crib to shorten and they should be checked daily for
tightness.

# Cribs may be used to support sloped surfaces as will be discussed later

Steel Pipe Systems

# Pipe capacity depends on buckling strength.

# P/A allow = 0.5E/(L/R) squared

# E = 29,000,000 PSI

# (L = length; R = radius of gyration = average radius of pipe)

# Retractable pipe shores are normally adjustable by screw end and/or sleeve and pin. They
may have square steel feet that may even have slope adjustment and nail holes for
attachment.

# Pipe shores used for bracing tilt-up concrete walls come in lengths up to 30 feet and have
rated capacities listed in tables supplied by rental companies.

# Pipe systems are often used with wood spreader beams and sills, which could limit their
capacity. Engineers should be used to design these systems.

10
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

VERTICAL SHORING SYSTEMS (continued)

Trench Jacks (SHOR-5)

# Vary from about two to more than eight feet long and normally have a rated capacity. They
are intended to support the opposing sides of a trench, with the addition of spreaders &
sheathing
# May be used as initial, unbraced shoring to permit building of more stable system.
# If used as only system they will need to be connected to spreaders at top and bottom and
should be laterally braced.

11
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

VERTICAL SHORING SYSTEMS (continued)

# Diagonally Braced Metal Frame Systems (SHOR-6)


! Steel and aluminum tubular frames are available in capacities up to 50,000lb. per
two post frame. They have adjustable height and spreader systems. They may be
stacked and guyed to reach great heights, and have diagonal bracing members.

12
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

VERTICAL SHORING SYSTEMS (continued)

Pneumatic Shores (SHOR-7)

# Light weight aluminum pneumatic piston ram shore which is highly adjustable with ranges
up to 16 ft. They can be configured with various end connections (see below).

# When used in trenches, these shores are initially set with pressurized air. After securing
the shore in place with a large locking nut or steel pins with collar, the safe working load
can range from 20,000 lbs. for four foot shore to 3500 lbs. for ten foot shore. Load charts
for the two leading manufactures are listed in the 1998 rev. of the US&R Structural
Specialist FOG. (Safe loading should be based on Pinned/swivel end connections)

# These shores are used without air in US&R, so as not to apply any sudden pressure to a
damaged structure. The sleeve nut or steel pins are used to adjust length. They may be
included in a system with headers, sole plate, & beam and bracing, but are considered
most useful as individual, temporary shores that allow a braced system to be installed at
reduced risk.

13
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

SPECIALTY SHORES (Airbags are lifting device - not shores)

# Airbags - tough neoprene bags that come in sizes from six


inches to thirty-six inches square. They can be pressurized to
lift very heavy objects a short distance and often are helpful in
releasing an entrapped victim. One must be careful to
remember that they can be punctured by rebar, and that objects
that are lifted must be laterally restrained by other means, since
the bags have little lateral strength. Airbags should always be
used while being backed-up with some other system to protect
against a puncture failure.

# Aluma Beams -are light gage, shaped, aluminum joist or


beams that are normally used as shoring for wet concrete.
(See page 12 , shown spanning between the Aluminum
Frames) They have been used to construct shelters from
falling debris, as plywood sheathing can be placed
between the Aluma Beams and nailed too them to provide
a surface that is quite flexible but strong. The flexibility of
the aluminum (3 times that of a similar steel structure) is
ideal for catching falling objects, since the flexibility
reduces the strength required for the CATCH structure.

# Steel and/or reinforced concrete culvert sections could be


considered as a protection device for entry thru an area where
protection from smaller falling hazards was required.

# Shoring At Column/Slab Connections - The danger of a


punching shear failure occurring at a flat slab/column joint is
often present due to heavy debris loading on slabs that do not
collapse initially. Since most of the cracking that warns of this
type of collapse hazard is on the top of the slab and may be
covered by the debris, it may be prudent to increase the
column's periphery by adding vertical shoring on all four
sides. Shoring consisting of vertical posts could be used and
laterally braced back to the column. All the normal problems
i.e. what's the load, supporting system etc. need to be
considered.

14
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING
VERTICAL SHORES ON SLOPED SURFACES
# If load is transferred from structure to shoring thru sloped surface the direction of the load
will be perpendicular to the sloped surface and not vertical.
# This type of loading will cause both horizontal and vertical loading in the shoring system,
since horizontal bearings should not be cut into the structure.
# Shoring systems for sloped surfaces should normally be constructed with header beams,
vertical, diagonals, and sole plates connected together in a system.
# The shores/posts should be placed on a slope perpendicular to the sloped floor, and
diagonal bracing should be designed for atleast 10% (preferably more) of the weight
of the shored structure. Two types of these shores are shown in SHOR-9, pg. 16,
one supported on an earth surface and one on pavement. The earth can be cut to
provide perpendicular bearing to the shores, but on pavement surfaces, nailed thrust
blocks (cleats) are used to transfer the horizontal component of the shore’s force.
# Cribbing can be used in this condition, as long as the slope isn't too great. Cribs can be
built into the slope, and notched crib members should be used since they can transfer
more lateral load than the usual friction interconnection.

15
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

16
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

17
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS


Principles of trench shoring may sometimes need to be applied to US&R, where pulverized
masonry rubble tend to cave into an otherwise accessible space.
# There are several systems used, such as Hydraulic Shores, Pneumatic Shores, Tieback
Systems and Drilled-in Solid or Pole Systems. The design of these systems is very
competently presented in the CALTRANS, Trenching and Shoring Manual.

Hydraulic Trench Shore


# These are frames made from aluminum hydraulic ram(s) with continuous side rails
# They are intended to be dropped into open trenches from the top and pressurized with a
5 gallon hand pump to between 500 - 1000 PSI.
# Shores can have a single ram with 2’ long rails or double rams with rails up to 12’ long.
Standard double ram frames have rails in 3’-6 , 5’-0 , and 7’-0 lengths
# They are intended to be dropped into open trenches from the top, and special, thick,
plywood panels are added against the soil to spread the load and confine soils.
# The larger shores can be spread as far as 8’ which could be useful for vertical support, but
are difficult to carry and install in irregular shaped openings. They require the pressure
to be maintained in order to support any load (no locking device as for pneumatic shores),
and , therefore are not recommended for use supporting critical vertical loads.

18
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS (continued)

Other Trench Shores

# Trench Jack (Screw Jack)


# Post Screw Jack
# Pneumatic Shore
# All have same capabilities as in vertical application.

One-Sided Trench Shore

# This type of shoring is needed when one side of a trench has caved in.
# These systems have been successfully used to temporarily raise river levees.
# They must be designed for specific condition of type of load (soil, water) and type of
supporting soil.

SHOR 11-A

19
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS (continued)

Raker Shores (Used to diagonally brace walls and buildings)


# Useful in bracing URM and other heavy walls that have cracked, (especially at corners)
and/or are leaning away from building.

# Need to be configured in system that will account for both vertical and horizontal
components of force in diagonal member (SHOR-12)

# The vertical component may be resisted by:


! Friction, which may be increased in a full triangular configuration, by applying more
horizontal load at the base, against the wall. However, friction should not be
considered as reliable, especially during aftershocks.
! By placing drilled-in anchors thru the wall plate into the masonry. (This may be too
dangerous in some areas of badly cracked walls)
! By bearing the wall plate against a projection in the wall surface, or by placing the
raker at an opening and nailing a cleat onto the plate so that it will bear on the
opening head.
# The required horizontal force may be less than two percent of the wall weight, since URM
walls are seldom left standing very far out of plumb. However, since aftershocks are likely
to occur, raker systems should be designed for about 10 percent of the weight of the wall
and roof that is within the tributary area that they support.

# Raker shores should be placed from 8 ft. on center, depending on wall type and condition.
They should be designed by engineers that have experience with these systems.

# Lateral bracing, consisting of continuous horizontal struts (capable of resisting


compression and tension) and diagonal bracing (in either V or X configuration) should be
installed in all raker systems.

# Rakers should be built away from dangerous area next to wall and then carried/walked
into place

# Rakers may be configured using the Full Triangle method (sometimes called Fixed raker)
or as a Flying Raker (Friction Raker) (SHOR-12)

# Either configuration (Full Triangle or Flying) could be used on walls up to about 24 ft. high.
Six inch wood members would be required when raker length exceeds 12 ft., unless
midpoint lateral bracing is provided. It is difficult to obtain lumber over 20 ft. long, but
splices may be made in rakers as long as they are located near where the diagonal and
lateral braces connect. (SHOR-14) Use 2x4x3ft min each side of splice, nailed with 8-16d
each side each end.

20
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS (continued)

21
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS

Raker Shores (continued)


# Flying Rakers take the least amount of material to build but have several disadvantages
(SHOR-13) They are recommended for use to initially stabilize a wall and/or building until
a system with more reliable bracing can be installed.

22
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS

Raker Shores (continued)


# Full Height Rakers will weigh more, use more material, but are easier to walk along the
ground for installation and can be more adequately braced.
! They can be built into tall, multi-raker configurations using 4x4 members with lateral
bracing to bring the L/D ratio to between 35 and 40. (SHOR-14)
! Multi-raker are fairly complicated, but show how the smaller timbers can be used
in a system to stabilize a two story wall. Note that the bracing needs to be placed
in two mutually perpendicular directions.

23
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS

Raker Shores (continued)

# Connection at top of raker should bear on thrust block or notch in wall plate plus thrust
block (SHOR-15). Bearing cut at top is difficult to make a tight fit, but if Raker angle is set
at 45 degrees or 60 degrees, the cut should be relatively easy to repeat. Plywood
scab/gussets should be used to hold this connection together. Connections of Raker to
ground are also shown.

24
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS (continued)

Raker Shores
# Raker Angle (see SHOR-16) - the angle between the ground and a diagonal (Raker) brace
member should be as small as practicable.
! When the angle is as small as 30 degrees, the horizontal force applied to the wall
is 87% of the force in the diagonal, and the upward force that needs to be resisted
at the wall face is only 50% of the diagonal force.
! When the angle increases to 60O the horiz. is 50%, and the vertical is 87%.
! At 45 degrees the two are equal at 71% of diagonal force.
! The disaster "field" conditions such as need for access, available timber length, or
clearance, may require that the less efficient 60 degree system is the only practical
way to do the bracing.
! One must find the best compromise between structural efficiency and practical
considerations. The simplest to deal with may be 45 degrees (1 to 1) and 60
degrees (1.7 to 1)

25
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS (continued)

Raker Shores

# The capacity of individual, single Rakers is in the range of 2400 lbs. (2.4k). This is
normally sufficient to brace most masonry or low rise concrete walls up to about 20 ft high.

# The full Triangle Rakers can be configured with a split sole plate (SHOR-17), which is
most useful for bearing on ground. This example shows how a 4 x 4 lumber x 20 ft. long
can be used to brace a 20 ft. wall.
! Lateral bracing is required at mid-height of the 4 x 4 in each direction.
! Overall lateral bracing is required to stabilize the system of Rakers, especially
during aftershocks.

# A second configuration of full Triangle Raker is shown with solid sole plate (SHOR-18).
This is most useful where paving is found next to the wall. It has the same L/D and overall
bracing requirements as the split sole type.

# A quick, temporary raker can be constructed using pneumatic shores. (SHOR-16a)


! They can be used as individual units, or be configured in a system of two or more
that are interconnected with 2x6 wood bracing.
! Special rails and connections are available for the shore manufacturers, as well as
base plate and bracing connections.

26
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS (continued)

27
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS (continued)

28
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS (continued)

Tilt-up wall braces (SHOR-19)

# Can be used to brace concrete tilt-up walls and other reinforced masonry walls.

# The walls would need to be pretty well intact and only in need of bracing, due to
connection failure. (spreading of the load would induce bending moments in the wall).

# Connection of braces to the wall could be by drill-in-anchors and anchorage at the base
could be to a wood curb/pad or slab on grade with a drill-in.

# These braces could also act in tension.

29
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 07/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

LATERAL SHORING SYSTEMS (continued)

# Tiebacks (SHOR-20)
! When URM walls are over thirty feet tall it is probably impractical to attempt to
brace them with raker shores.
! Vertical, or horizontal and vertical strongbacks could be placed on the face of a
hazardous wall and tied across the structure to a floor beam or the opposite side
wall.
! The strongbacks could be made from double 2x6 wood members with the tie being
placed between them. Solid 4x or 6x members could also be used.
! The ties that have been placed by contractors were steel rods with turnbuckles,
bearing washers etc. Cables with come-along could also be used as well as utility
rope, chain, etc. One may need to be creative to obtain an adequate tie, but
climbing rope, used by firefighters should be considered only as a last resort.
(Climbing rope is considered unreliable with the rough treatment of this type of
application and would be discarded)

30
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

SHORING SYSTEMS USED IN US&R

# The Special Medical Response Team, a group of medical first


responders organized to aid mine collapse victims, has a plan
to use a combination of pneumatic shores and cribbing to
assure vertical support in order to provide medical care within
the collapse. They first set the pneumatic shores and then
follow with the cribbing.

# The House Moving Contractor, R. Trost, provided emergency


shoring after the 1989 Loma Prieta Quake for twenty five
buildings in the San Francisco Marina District. The 3 & 4 story
wood buildings were out of plumb in the first story as much as
2 feet. As shown in SHOR-21 & 22, they provided lateral
stability by placing 6x8 diagonal shores from the inside of the
street curb to the second floor, and added 6x6 diagonals in
doorways. They later placed story high cribbing and large
steel beams to provide better vertical support, and allow for
later straightening of the buildings.

! One must carefully consider where this type of bracing


is connected to the structure in order for it to effectively
obtain a vertical reaction while it is providing the
horizontal resistance.

31
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

SHORING SYSTEMS USED IN US&R

# At the Highway 880 collapse, Loma Prieta Earthquake, shoring contractors used 12x12
vertical posts to support the concrete frames in the first story that were damaged by the
collapse of the second story. The 20 ft. height was too great for cribbing, and a spreader
system was used to interconnect the posts at the ground level. Diagonal bracing was
added to same locations of those rows of posts, but it was very light for the potential load.

# Large back-hoe/excavator or bucket-loader vehicles have been used to provide lateral


(raker) support to leaning walls and buildings at several disaster sites. Very good idea for
an emergency condition.

32
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

SHORING SYSTEMS USED IN US&R

33
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

SHORING FOR SPECIFIC BUILDING TYPES

# Shoring considerations for light frame, multi-story buildings

! Multi-story frame with leaning first story need


lateral/diagonal shoring that acts against the floor plane

! Wood building with crawl space that have moved off


foundation have normally come to rest, but roof and
upper story floors may also be offset/cracked and need
vertical shoring

! Brick veneer on wood frame walls often are falling


hazards in aftershocks, and may need to be shored or
protective tunneling type structure may be required to
protect access.

# Shoring considerations related to URM buildings (Heavy Wall)

! URM walls may be cracked (especially at corners) or


peeled and need diagonal/raker shores.

! Cracked URM walls may also require shoring of


openings.

! When URM exterior walls have fallen the remaining


wood floors may require vertical shoring.

34
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

SHORING FOR SPECIFIC BUILDING TYPES

# Shoring considerations related to URM buildings (continued)

! Floors often collapse into the following patterns:

- LEAN-TO - shoring is usually required under the


suspended floor and possibly on the outside wall,
opposite where the floor is still connected.
Victims might be found under the suspended
floor and on top of this floor at the lowest end

- V-SHAPE - shoring is usually required under the


two suspended floor pieces and possibly on the
outside walls, opposite where the floors are still FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95

connected. Victims might be found under the two EXTRICATION OPERATIONS

suspended floor pieces and on top of the floor in


the middle of the V .

- PANCAKE - shoring is usually required under the


floors. Victims might be found under the floors.
Voids are formed by building contents and debris
wedged between floors
SH-URMLF

- CANTILEVER - this type is similar to the pancake


pattern with the added problem of some of the
floor planes extending, unsupported from the
debris pile. Shoring is usually required under and
above the floors starting at the lowest level.
Victims might be found under the floors as in the
pancake condition.

! Must consider that rubble will flow into any victim access
trench or tunnel, and close-in vertical and lateral shores
may be required

! May need support system with sheathing, spreader


beams, & shores in both vertical & horizontal directions.

35
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

SHORING FOR SPECIFIC BUILDING TYPES (continued)

36
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

SHORING FOR SPECIFIC BUILDING TYPES (continued)

# Shoring considerations related to Reinforced Concrete


Buildings (Heavy Floor)
! Will often have fairly unbroken planes that can be easily
shored w/ vertical shores.
! When floors have beams & girders intersecting at the
columns, diagonal tension, shear cracks will give
indication of potential failure.
! In flat slab (beamless) floors that are heavily loaded with
debris, a punching shear (rapid) failure is possible.
Since the cracking that indicates this type of overload
usually is best seen from the top of the slab (covered by
debris), it is very difficult to assess.
! If concrete floor plane is badly broken, a system with
sheathing, spreaders, and safe haven areas may be FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95

needed. EXTRICATION OPERATIONS

! Lean-to, V-shape, and Pancake collapse patterns may


be found in heavy floor buildings. (especially pancake)
! In floors where post-tensioned, cable reinforcing is
present, a double hazard may be present. If the cables
are loose, then the collapse will contain a mass of
closely spaced, unreinforced pieces that are difficult to
shore. If the cables are still tensioned, then they can
become lethal missiles. SH-HF&PC

# Shoring considerations related to Precast Concrete Structures


! Collapses of this type will normally contain large pieces
of lightweight concrete. Shapes like single and double
tees are difficult to shore.
! Lean-to, V-shape, and Pancake collapse patterns may
be found in precast concrete buildings. (especially lean-
to)
! Shoring of sloped surfaces will probably be required.
Large pieces may be lightly interconnected and there
will be the potential of their shifting.
! Using cranes to remove critical pieces may be the best
strategy to access voids

37
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: A — SHORING

SUMMARY FOR EMERGENCY SHORING OF STRUCTURES

# Shores need to be strong, light, portable, adjustable, and


reliably support the structure as gently as possible.

# Systems should be used that are positively interconnected,


laterally braced, and have slow, predictable failure mode

# One of the best systems is cribbing since they are :


! Made from light pieces that are adjustable & can be built
into sloped surface
! Relatively wide and stable. will spread the load.

# Have slow failure mode that will give warning

# Systems need to be tested in order to determine best methods


to resist:
! Loads on sloped surfaces above and below
! Loads during large aftershocks

# In a disaster we need to consider any viable system based on


availability of material, special contractors, and special
equipment. The basic principles of engineering will always
apply, but creative thinking and co-operation between all
members of the Task Force is essential.

38
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

MITIGATION OF STRUCTURE COLLAPSE HAZARDS FEMA US&R RESPONSE SYSTEM


RESCUE SPECIALIST TRAINING 04/95

EXTRICATION OPERATIONS

# Three basic methods UNIT OBJECTIVES

! Avoid It — barrier tape around a hazardous area # Have a basic understanding of how
to conduct a proper shoring size-up.

preventing access. # Be able to identify locations for


proper shoring placement.
! Remove It — pulling down a cracked and leaning brick # Understand the Shoring Team

chimney. concept and identify team


positions and purpose.

! Shore It — Constructing shoring systems. # Have a basic understanding of the


different types of shoring component
parts and related equipment.

SHORING SIZE-UP OH-1

# The Shoring Size-Up provides a survey of structural damage


and potential victim locations in buildings identified during the
initial building triage and Structure/Hazards Evaluation FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95

process. EXTRICATION OPERATIONS

! Identify structural hazards, damage and potential victim COLLAPSE HAZARD MITIGATION

locations. # AVOID IT —
! barrier tape around a hazardous

! Determine best method to mitigate the structural area preventing access

hazards and damage. Avoid, remove or shore. # REMOVE IT —


! pulling down a cracked and

! Determine the type and placement of shoring systems in leaning brick chimney

relation to structural hazards, damage and potential # SHORE IT —


! constructing shoring systems
victim location.

# The shoring size-up should be performed by at least a OH-2

Structural Specialist, Rescue Team Manager and/or Rescue


Squad Officer.

# The shoring size-up must be extensive, accurate and continue FEMA US&R RESPONSE SYSTEM

throughout the rescue operation. RESCUE SPECIALIST TRAINING

EXTRICATION OPERATIONS
04/95

SHORING SIZE-UP
# Identify structural hazards, damage
and potential victim locations.

SHORING SIZE-UP CONSIDERATIONS # Determine best method to mitigate the


structural hazards and damage.
! Avoid, remove or shore

# Victims # Determine the type and placement


of shoring systems in relation to

! How many victims are trapped and where are they structural hazards, damage and
potential victim location

located? # Performed by at least a Structural


Spclst, Rescue Team Manager
! Is the information coming from reliable sources and can and/or Rescue Squad Officer

#
it be confirmed? Extensive, accurate and continuous
throughout the rescue operation
OH-3

39
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

SHORING SIZE-UP CONSIDERATIONS (continued)

# Six-sided Approach
! Survey all four sides, the top and the bottom of the
entire structure paying particular attention to the
collapse area.
! The top survey is extremely important because loose or
hanging debris, structural elements and other overhead
hazards must be identified and addressed.
! Gravity being constant, will continually try to pull the
remains of the structure and its contents to the ground.
! Surveying the bottom is equally important because
shifted loads created by the collapse must be
transferred to other stable structural members or back to
stable ground. FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95

EXTRICATION OPERATIONS

# Structural Elements SIZE-UP CONSIDERATIONS

! Walls out of plumb determine building stability # A — Victims

immediately on arrival. # B — Six-sided approach

! Bearing walls are the most important structural elements


# C — Structural elements
in an unframed building and failure of any part of these
walls can cause extensive damage and further collapse. # D — Age and condition of the structure

! Identification and assessment of all beams, columns, # E — Collapse warning signs

arches, joists and other structural supporting elements


under the main debris pile or the victim’s location should OH-4

be among the top priorities of the shoring size-up.


- All severely stressed, broken, missing, bowed or
cracked supporting elements which could affect
the rescue operation must be shored up before
any personnel are committed to work in the area.
- The building elements they supported must also
be examined and resupported.

40
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

SHORING SIZE-UP CONSIDERATIONS (continued)

# Age and Condition of the Structure


! The shrinkage of structural elements over time results in
a loss of strength and the loosening of important
hangers and connecting supports which may require
more shoring.
! Supporting elements of a well-maintained building may
be utilized to help support and transfer the collapse load
throughout the structure. However, if the building’s
condition was in a state of disrepair or suspect prior to
the collapse, do not assume any structural support
exists without a thorough inspection.

# Collapse Warning Signs


! Continual surveillance of the structure from several
vantage points must be maintained from the time of
arrival to the time the last rescue personnel have
terminated their operation and exited the building.
! Surveyor transits and theodolites are excellent tools for
detecting any wall and floor movement.
! Pay particular attention to signs of a possible imminent
secondary collapse which can include shifting debris,
airborne dust, sliding plaster and unnatural sounds such
as creaking, moaning and groaning coming from the
structure.

SHORING PLACEMENT

# Two Main Objectives


! Maintain the integrity of all structurally unstable
elements
! Properly transmit or redirect the collapse loads to stable
ground or other suitable structural elements capable of
handling the additional loads.

41
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

SHORING PLACEMENT (continued)

# Shoring Placement Considerations


! All shoring operations in wood and steel framed
structures should be started at least one floor below the FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95
level in which structural damage has occurred, including EXTRICATION OPERATIONS

stressed beams, or at the lowest level if a full-scale SHORING PLACEMENT


collapse has transpired.
# All shoring operations in wood and
! All shoring operations in concrete structures should be steel framed structures shoule be
started at least one floor below and in
started at least two floors below the level in which concrete structures at least two floors
below the level in which structural
damage has occurred
structural damage has occurred.
! Shoring primary structural supporting elements such as # Shoring primary structural
supporting elements

bearing walls, girders, columns and arches will more


# The area beneath the main debris pile
effectively utilize shoring materials and existing
construction features of the building. OH-5

! The area beneath the main debris pile must be


examined and shored as needed to provide additional
support to the existing structural elements currently
sustaining the load before any personnel can be
committed to rescue operations in or on top of the debris
pile.
! The area directly underneath the victim(s) and rescue
forces must be shored up before significant debris
removal operations are attempted. Shores may need to
be retightened continually as debris is removed.
FEMA US&R RESPONSE SYSTEM
! Shoring system(s) must be located where they will not RESCUE SPECIALIST TRAINING 04/95

EXTRICATION OPERATIONS
interfere with the removal of the victim(s).
! All loads transferred to earth or other suitable structural SHORING PLACEMENT
# The area directly underneath the
element capable of handling the additional load require victim(s) and rescue forces

the shoring systems(s) to be located where they will # Shoring system(s) must be located
where they will not interfere with the
removal of the victim(s)
bear on each other. This is sometimes accomplished by
# All loads transferred to earth by
aligning the shoring systems on top of each other aligning the shoring systems on top
of each other between floors or

between floors or on opposite sides of a wall. on opposite sides of a wall

#
!
Create safe zones and safe
Access into the building may require shoring to be passageways

started from the point of entry to where the victim is


located in the structure. Several sections of shoring OH-6

may have to be constructed to create safe zones and


safe passageways.

42
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE SHORING TEAMS

To conduct shoring operations safely and efficiently two separate


teams are formed.

# The Shore Assembly Team

! Performs the actual shoring size-up and construction of


the shores.

# The Cutting Team

! Establishes the equipment area and cuts the shoring FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95

lumber. EXTRICATION OPERATIONS

THE SHORING TEAM


# Six-person squad

Assembly Team Cutting Team


# The Shore Assembly Team
1) Shoring officer 4) The Layout

2) The Measurer 5) The Cutter


! The Shoring Officer (Rescue Squad Officer) — in
3) The Shorer 6) Tools/Equipment
charge of the operation and works with the structural
specialist to determine where to place and erect the
shores. OH-7

! The Measurer — performs all the measuring required


in the erection of the shoring and relays all
measurements and lumber sizes to the “layout” of the
cutting team.

! Shorer — clears away debris and obstructions that


could interfere with constructing the shore, assists the
“measure” as needed and erects the shores.

43
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE SHORING TEAMS (continued)

# The Cutting Team

The initial responsibility of the cutting team is to secure an area


as close as possible to the collapse operation so as to minimize
the number of personnel needed to relay the materials to the
shore assembly team. The assistance of several other
personnel may be required to help expedite the movement of
lumber and tools to the collapse area.

! The Layout — in charge of setting up the cutting


station and readying the materials to be cut.
- Performs all measuring and layout of angles and
should be in direct contact with the shore
assembly team “measure” via portable radio to
eliminate problems in miscommunicating
measurements of lengths to be cut.

! The Cutter — cuts the shoring material.

! Tools and Equipment — directs the movement of


tools and equipment to be placed where they are
requested, anticipates logistical needs of the shoring
team and keeps an inventory checklist/log sheet for
easier retrieval of tools and equipment at the conclusion
of rescue operations.

# A single Rescue Squad can normally fill the six individual


shoring team positions during most shoring operations.

# Larger or more complex shoring operations may require two


complete Rescue Squads, with one squad assigned to the
Shore Assembly Team and the other assigned to the Cutting
Team.

44
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE SHORING TEAMS (continued)

# Shore Assembly Team with a complete six person Rescue


Squad:
! The Shoring Officer (Rescue Squad Officer)

! The Measurer

! Shorer
[these two work together assembling
! Shorer and erecting shores in place]

! Safety

! Runner — ensures tools, equipment and shoring FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING 04/95

materials are moved from the shoring operation primary EXTRICATION OPERATIONS

access point to the shoring site and assists in the THE SHORING TEAM

erection of shores as needed. # Six-person squad on each team

Assembly Team Cutting Team

1) Shoring officer 1) Cutting officer

2) The Measurer 2) The Layout

# Cutting Team with a complete six person Rescue Squad: 3) Shorer 3) The Feeder

! The Cutting Team Officer (Rescue Squad Officer) 4) Shorer 4) The Cutter

5) Safety 5) Tools/Equipment

! The Layout 6) Runner 6) Runner

OH-8

! The Feeder — moves and feeds measured and marked


shoring material from the Layout to the Cutter and helps
secure it when being cut.

! The Cutter

! Tool and Equipment

! Runner — ensures tools, equipment and shoring


materials are moved from the cutting area to the shoring
operation primary access point.

45
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE VERTICAL SHORE

# The main purpose of the vertical shore is to stabilize damaged floors, ceilings or roofs. It
can also be used to replace missing or unstable bearing walls or columns.

46
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE VERTICAL SHORE (continued)

# The two sizes of lumber most commonly used in vertical


shoring are 4” X 4” and “6 X 6” douglas fir. The estimated
weight of the floor and its contents will help to determine the
size of shoring materials and their spacing.
# Businesses and commercial occupancies with heavier
structural elements and greater floor height and/or loading may
require 8” X 8” or even 12” X 12” lumber. The Structures
Specialist should be used to help determine the correct size
and placement of shoring materials.

# Structural Components of the Vertical Shore


! The Sole Plate — provides a foundation for the
shoring system by supporting the weight being
transferred from above/distributes it over a wider area.
! The Header — collects the weight from above and
spreads it throughout the shoring system.
! The Posts — supports the weight being collected by
the header or spreader beam and transfers it to the sole
plate where it is distributed.
! The sole plate, header and posts should be the same
width for a more secure attachment.
! Cleats or Gusset Plates — short pieces of 2” X 4”
(Cleat) or small pieces of 3/4” plywood (Gusset Plate)
nailed to the top/bottom of posts to ease shore place-
ment and secure the posts to header and sole plate.
! Wedges — two wooden incline planes “married”
together and placed under the bottom of the post.
Simultaneously tapped together until the shoring system
is under compression and takes the weight of the
structural materials above.
! Diagonal Braces — the last items to be installed on
the vertical shore should be long enough to span its
entire length and be attached to the header, each post
and the sole plate to lock the entire shore together as
one unit and support against possible eccentric loads
applied to it.
- a 2” X 4” or 2” X 6” nailed on both sides of the
shore in opposite directions of each other to
resist lateral deflection from either side.

47
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE VERTICAL SHORE (continued)

! Mid-Point Braces — are needed when 4” X 4” posts


are greater than 10’ long or 6” X 6” posts greater than
15’ long.
- a 1” X 6” or length of 3/4” plywood at least six
inches wide nailed to the mid point of the posts
on both sides takes deflection out of the post.
- to increase the posts bearing capabilities, mid
point bracing must be in both directions with
diagonal braces long enough to connect the
header to the sole plate or two shorter diagonal
braces, one connecting the header to the mid
point braces and the other connecting the mid
point braces to the sole plate.

How to Construct the Vertical Shore

# Determine where to erect the vertical shore.


! After initial temporary shoring has been installed as
needed, clear the area of debris, down to the floor,
removing thick carpeting if necessary. A clearance of
three to four feet wide is usually adequate.
! If the vertical shore is to bear directly on soil, examine
the ground for stability. If the earth is soft, additional
supports should be installed under the sole plate to
transfer the load over a wider area.

# Lay the sole plate on the floor or ground directly under and in
line where the header will be installed.
! The sole plate should be as level as possible.

# Measure and cut the posts to the proper height.


! Place the header on top of the sole plate.
! With the end of the tape measure on top of the header
where the posts are to be installed, slide the tape up to
the bottom of the structural element to be shored and
measure in at least three places deducting the width of
the wedges to be used.

48
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE VERTICAL SHORE (continued)

# If possible, anchor the header to the area that is to be shored,


square and in line with the sole plate.

! Secure it at the lowest point and shim the structural


elements down to the header trying to keep it as level as
possible.

# Install the posts between the header and sole plate under each
structural element to be supported.
! The first two posts are installed at opposite ends at least
12” in from each end of the sole plate.
! Keep the posts in line and plumb with the header and
sole plate.

# Install a set of wedges under the bottom of each post and tap
them together simultaneously until the posts are under
compression and tight.
! Nail behind the wedges to secure them in place.

# Attach cleats or gusset plates to at least one side of the header


and posts and nail in place if not done previously.

# Attach cleats or gusset plates to at least one side of the sole


plate and posts and nail in place.
! Nails may need to be Duplex for future adjustment of the
wedges.

# Attach the diagonal braces to each side of the vertical shore.


! Mid-point braces, when needed, should be installed
prior the diagonal braces.
! The diagonal braces should be long enough to span its
entire length and be attached to the sole plate and
header and each post.
! If possible, diagonal braces should be installed in a “X”
pattern on opposite sides of the system.
! Vertical shoring systems which span a long area may
require several sets of diagonal braces to connect
multiple posts.

49
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE HORIZONTAL SHORE

The main purpose of the horizontal shore is to stabilize a damaged wall against an undamaged
wall in hallways, corridors or between buildings.

50
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE HORIZONTAL SHORE (continued)

Structural Components of the Horizontal Shore

# The Wall Plates — provide a foundation for the shoring


system by collecting the weight being transferred laterally and
spreads it throughout the shoring system.

# The Struts — supports the weight being collected by one wall


plate and transfers it to the other wall plate.
! The wall plates and struts should be the same width for
a more secure attachment.

# Cleats or Gusset Plates —


! Cleats: short pieces of (2” X 4”) nailed under the struts
to ease in their placement and prevent the struts from
being dislodged.
! Gusset Plates: small pieces of 3/4” plywood nailed on
at lest one side of the wall plates and struts to prevent
struts from being dislodged.

# Wedges — two wooden incline planes “married” together and


placed under one end of the strut.
! Simultaneously tapped together until the shoring system
is under compression and takes the weight of the
structural materials.

# Diagonal Braces — the last items to be installed on the


horizontal shore when the hallway or corridor is not used for
access or egress.
! Should be long enough to contact both the top and
bottom of the wall plates and all the struts to lock the
entire shore together as one unit and support against
possible eccentric loads applied to it.
! A 2” X 4” or 2” X 6” nailed on both sides of the wall
plates in opposite directions of each other to resist
lateral deflection from either side.

51
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE HORIZONTAL SHORE (continued)

How to Construct the Horizontal Shore

# Determine where to erect the horizontal shore

! After initial temporary shoring has been installed as


needed, clear the area of debris.

! A clearance of three to four feet wide is usually


adequate.

# Measure and cut the wall plates to the proper length.

# Measure and cut the struts to the proper length.

! Place both wall plates against the walls.

! Measure between the wall plates where the struts are to


be installed, deducting the width of the wedges to be
used.

# Place both wall plates next to each other and attach cleats to
the wall plates just below where the struts will be installed.

# Place the wall plates in the area that is to be shored, square


and in line with each other and as plumb as possible by
shiming any void spaces behind the wall plates.

# Install the struts between the wall plates. Keep the struts in
line and plumb with the wall plates.

52
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE HORIZONTAL SHORE (continued)

# Install a set of wedges under one end of each strut and tap
them together simultaneously until the struts are under
compression and tight.

! Secure the wedges in by placing the back of a shim on


top of the wedges and nail it to the wall plate or toe nail
the wedges to the wall plate.

! Nails may need to be Duplex for future adjustment of the


wedges.

# Attach cleats or gusset plates to at least one side of the wall


plates and struts.

# If possible, attach the wall plates to the walls.

# Attach the diagonal braces to each side of the horizontal shore


when not used for access or egress.

! The diagonal braces should be long enough to span its


entire length and be attached to both wall plates and
each strut.

! When used, diagonal braces should be installed in a “X”


pattern on opposite sides of the system.

53
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

WINDOW AND DOOR SHORE

# The main purpose of the window and door shore is to stabilize a window, doorway or other
access way. An extensive collapse can generate a tremendous amount of debris blocking
the primary entrances into a building and sometimes require a window entry.

54
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

WINDOW AND DOOR SHORE (continued)

# The window and door shore is usually installed in entry points


intended for use by rescue personnel to hold up or stabilize
loose headers or lintels that have lost their integrity.

# Additional load stress is usually exerted from above and


therefore, constructed similar to the vertical shore.
! If additional load stress is exerted from the side, the
window and door shore is constructed similar to the
horizontal shore.

Structural Components of the Window and Door Shore

# The Sole Plate — provides a foundation for the shoring


system by supporting the weight being transferred from above
and distributing it over a wider area.

# The Header — collects the weight from above and spreads it


throughout the shoring system.

# The Posts — supports the weight being collected by the


header and transfers it to the sole plate where it is distributed.
! The sole plate, header and posts should be the same
width for a more secure attachment.
! Buildings with large structural elements or openings
greater than four feet usually require lumber larger than
4” X 4” for the sole plate, header and posts.

# Cleats or Gusset Plates — short pieces of 2” X 4” (Cleat) or


small pieces of 3/4” plywood (Gusset Plate) nailed to both ends
of the posts and struts to ease in the placement and securing
the posts to the header and sole plate.

# Wedges — two wooden incline planes “married” together and


placed under the bottom of the posts or struts.
! Simultaneously tapped together until the shoring system
is under compression and takes the weight of the
structural materials.

55
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

WINDOW AND DOOR SHORE (continued)

# Diagonal Braces — the last items to be installed on the


window and door shore when the opening is not used for
access or egress.
! The diagonal braces should be long enough to contact
the top of the posts on one side and the bottom of the
posts on the other to lock the entire shore together as
one unit and support against possible eccentric loads
applied to it.
! A 2” X 4” or 2” X 6” nailed on both sides of the shore in
opposite directions of each other to resist lateral
deflection from either side.

# Corner Braces — used when additional support is needed or


if the opening is more than six feet wide.
! Two 45-degree angle braces with 1 1/2” return cuts on
both ends for full contact with the installed cleats.
Cleats should be a minimum of 2 ft. in length with
sixteen 16p nails.

How to Construct the Window and Door Shore

# Determine where to erect the window and door shore


! After initial temporary shoring has been installed clear
the area of debris or remaining framing material.

# Measure and cut the sole plate to the proper length deducting
the width of the wedges to be used.

# Measure and cut the header to the proper length deducting the
width of the wedges to be used.

# Measure and cut the posts to the proper height.


! Place the header on top of the sole plate.
! With the end of the tape measure on top of the header
where the posts are to be installed, slide the tape up to
the bottom of the structural element to be shored on
both sides deducting the width of the wedges to be
used.
! Use the shorter of the two measurements.

56
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

WINDOW AND DOOR SHORE (continued)

# Install the sole plate with a set of wedges at one end and tap
them together simultaneously until the sole plate is under
compression and tight.
! The sole plate should be as level as possible, use shims
as necessary under the sole plate.

# Install the header with a set of wedges at the opposite end of


the sole plate and tap them together simultaneously until the
header is under compression and tight.
! The header should be as level as possible, use shims
as necessary above the header.

# Install the posts between the header and sole plate and against
the sides of the opening.
! Install the first post under the wedge side of the header
to prevent accidental movement if the header wedges
loosen up.
! Keep the posts in line and plumb with the header and
sole plate.
! A set of wedges is installed under each post, on top of
the sole plate. The wedges are then tightened to lock
the shore in place.

# Attach cleats or gusset plates to at least one side of the header


and posts and nail in place.

# Secure the wedges by placing the back of a shim against the


sides of the wedges and nail it in place or toe nail the wedges.
! Nails may need to be Duplex for future adjustment of the
wedges.

# Install corner braces when additional support is needed or if the


opening is more than six feet wide.

# Install diagonal braces on the window and door shore when the
opening is not used for access or egress.

57
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE RAKER SHORE

The main purpose of the raker shore is to support leaning or unstable walls and columns by
transferring additional weight down the raker, to the ground or other structural supporting
members, and away from the wall or column.

58
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE RAKER SHORE (continued)

# Raker shores must always be installed in series, at least two


must be erected in any given situation and braced together with
a recommended separation of 8 feet.

# Two general styles of raker shores are the (Flying) Friction


Raker Shore and the (Full Triangle) Fixed Raker Shore.

# The (Flying) Friction Raker Shore


! May be considered for initial temporary shoring due to
its ease of construction and fewer shoring materials
when followed with a group of well braced (Full Triangle)
Fixed Raker Shores.
! Stability is increased by attaching the wall plate directly
to the wall to reduce or eliminate slippage/shifting.

# (Full Triangle) Fixed Raker Shore


! All of the structural elements are tied together, making
the shore one integral unit and provides the best method
of anchoring and bracing, but requires the most shoring
material.
! The shore itself is stable and because of its ability to
stay together this style of shoring is most often
recommended for rescue situations.

# The two types of (Full Triangle) Fixed Raker Shores are the
solid sole plate and the split sole plate.
! The Solid Sole Plate (Full Triangle) Fixed Raker Shore
(CSS O/H-13) — utilized more in urban environments
where concrete/asphalt commonly cover the ground.
! The Split Sole Plate (Full Triangle) Fixed Raker Shore
(CSS O/H-14) — utilized more in suburban
environments where open ground is available.

# Raker Shore Support Point


! The support point at which the raker shore should
intercept the buildings load is within one foot below the
center of the floor or roof joist.
! Rounding off the height of the raker shore support point
to the nearest foot will make the raker easier to measure
and cut.

59
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE RAKER SHORE

60
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE RAKER SHORE

61
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE RAKER SHORE

Determining the Raker Shore Angle and Length

# Any angle between 30 and 60 degrees will work effectively.


! The lower the angle, the more efficient the raker will be.
! Above the 45o angle, the vertical force becomes larger than the horizontal force.

62
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

THE RAKER SHORE

# The two most common angles used are 45 and 60 degrees.

! A 60 degree angle is the maximum recommended angle


used to safely erect a raker shore.

# Determining the height at which the raker shore needs to


intersect the wall will identify the angle to work best with the
available lengths of lumber.

! A 45 degree angle raker shore requires longer lumber


than a 60 degree raker shore.

# The length of a 45-degree angle raker shore: Height of the


raker shore support point in feet multiplied by 17 will give the
length of the raker, tip to tip, in inches. (8’ x 17 = 136” or 11’
4”).

# The length of a 60-degree angle raker shore: Height of the


raker shore support point in feet multiplied by 14 will give the
length of the raker, tip to tip, in inches. (8’ x 14 = 112” or 9’ 4”).

63
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

STRUCTURAL COMPONENTS OF THE RAKER SHORE

64
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

COMPONENTS OF THE RAKER SHORE (continued)

# The Wall Plate — provides a foundation for the shoring


system by collecting the weight being transferred laterally and
spreads it throughout the shoring system.

# The Sole Plate — collects the weight being transferred


laterally and distributes it to the ground or other structural
supporting member.

# The Raker — supports the weight being collected by the wall


plate and transfers it to the sole plate.
! The wall plate, sole plate and raker should be the same
width for a more secure attachment.
! Buildings with heavy structural elements or support
points taller than 12 feet usually require lumber larger
than 4” X 4” for the wall plate, sole plate and raker.

# The Top Cleat — short two foot piece of 2”X lumber nailed to
the top of the wall plate to keep the raker from riding up the wall
plate.

# The Bottom Cleat — short two to three foot piece of 2”X


lumber nailed to the top of the sole plate to keep the raker from
riding back on the sole plate.
! If possible and practical, the bottom cleat on the solid
sole plate raker shore can be long enough to return
back to a solid object, such as an adjoining wall.

# Wedges — two wooden incline planes “married” together and


placed against the bottom end of the raker and the bottom
cleat.
! Simultaneously tapped together until the shoring system
is under compression and takes the weight of the
structural materials.

# Gusset Plates — 12" X 12"pieces of 3/4” plywood nailed on


both sides of the wall plate and sole plate connection and the
top and bottom of the raker to prevent the them from being
dislodged.
! Split sole raker shores require gusset plates on both
sides of the wall plate at the top of the raker only.

65
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

NAIL PATTERNS FOR RAKER AND OTHER SHORES

66
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

COMPONENTS OF THE RAKER SHORE (continued)

# Diagonal Braces —diagonal braces increase the strength of the raker by reducing the
L/D ratio.
! The diagonal braces should be long enough to reach from the wall plate and sole
plate connection to near the mid point of the raker.
! On the solid sole raker shore, a 2” X 6” or two 2” X 4” are nailed to both sides of the
wall plate and sole plate connection and mid point on the raker.
! On the split sole raker shore, a 2” X 6” or two 2” X 4” are nailed to both sides of the
wall plate and just above the bottom braces connection and mid point on the raker.

# Bottom Braces — on split sole raker shores, a 2” X 6” or two 2” X 4” are nailed just
above the ground and attached as close to the bottom of the raker as possible and the
bottom of the wall plate with a fill block near the middle for additional stability.
! Placed at the bottom of the wall plate and along the raker above the ground on the
(Flying) Friction Raker Shore.

# Horizontal Braces — horizontally connects the raker shores together near the top and
bottom of the raker to provide additional stability to the raker shore system.
! Horizontal braces attached to the mid point of the raker increase the strength of the
raker by reducing the L/D ratio.

# “X” and “V” Braces — connects the raker shores in a “X” or “V” pattern near the bottom
and middle of the raker depending on access needs and available lumber.
! Provides additional stability to the raker shore system and decreases the lateral
movement when at least a pair are used at the beginning and end of the raker
shore system.

67
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

COMPONENTS OF THE RAKER SHORE (continued)

# Backing Material —
! Plywood (Full and Half Sheets) require a minimum of 3/4” or two 1/2” sheets of
plywood nailed together.
! 2” X Lumber (2” X 8, 10” & 12”)
! Nailed to the back of the wall plate can help distribute the weight of the wall over
a wider area and prevent the wall plate from pushing through an unstable wall.
! Very useful on unreinforced masonry (URM)
! Nailed to the back of the sole plate can help distribute the weight of the wall over
a wider area and prevent the sole plate from pushing into soft or muddy soil.
! Backing material must contact the wall at the raker support point and at the bottom
of the wall plate.
! Shims may be needed to fill void spaces.
! Backing material can be used to attach the wall plate to the wall or sole plate to the
ground.

How to Construct the Raker Shore

# Determine where to erect the raker shores and the height of its support points.
! After initial temporary shoring has been installed as needed, clear the area of
debris.
! Three to four feet wide and at least the height of the support point out from the wall
or column.

# Measure and cut the wall plate to the proper length, if needed.

# Measure, cut the top cleat and attach it to the top of the wall plate with at least 16-16d
nails.
! The top cleat is usually 2” X lumber two feet long for rakers at 45 degree angles or
less.
! The top cleat is usually 2” X lumber three feet long with 24 to 36-16d nails for
rakers at 60 degree angles.
! Another method for 60 degree angle rakers is to use the two foot cleat with 16-16d
nails and cut a 1” deep notch just below the location for the bottom of the cleat.
Length of the notch will be two times the width of the raker (8” for 4” X 4” and 12”
for 6” X 6”).

68
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

COMPONENTS OF THE RAKER SHORE (continued)

! The longer cleat with more nails or the notch below the two foot cleat are required
because of the greater vertical forces applied to rakers at 60 degree. angles.

# Measure and cut the raker to the proper length and angle to reach the support point.
! Solid sole raker shores need both ends of the raker to be angle cut with 1 1/2”
return cuts for full contact with the wall plate, top cleat, sole plate and wedges.
! Split sole raker shores only one end need one end of the raker to be angle cut with
a 11/2” return cut for full contact with the wall plate and top cleat.
! The other end of the raker will contact the short sole plate dug into the ground at
a 30 to 45 degree angle.

# Measure and cut the sole plate to the proper length, if needed.
! The solid sole raker shore sole plate must extend from the wall plate several feet
past the point at which the raker intersects at the floor.
! The split sole raker sole plate is approx. two ft long.

# Place the wall plate against the area to be shored and plumb up in both directions.
! If the area is bulged or cracked due to the strain exerted by the collapse debris, the
wall plate may need to be shimmed.
! Full contact must be maintained between the base of the wall plate and the area
being shored.
! Full contact must also be maintained between the wall plate and the support point
of the raker.

# Attach the sole plate to the bottom of the wall plate with gusset plates and nails on both
sides on solid sole raker shores.
! The wall plate and sole plate should be as level, plumb and at right angles to each
other.
! Attach the sole plate to the floor if possible and use shims as necessary to keep it
level.
! Split sole raker shores require a shallow hole dug at a 30 to 45 degree angle for the
sole plate and raker to push against.

69
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

COMPONENTS OF THE RAKER SHORE (continued)

# Install the raker by gently lowering it onto the wall plate and sliding it up into position under
the top cleat.

! The ends of the raker should be flush and in full contact with the wall plate, top
cleat and sole plate.
! Attach the top of the raker to the wall plate with gusset plates and nails on both
sides.

# On the solid sole raker shore, attach the bottom cleat to the sole plate just behind the base
of the raker with room left to apply wedges.
! On the split sole raker shore, the bottom cleat is attached to the short sole plate on
top of the bottom end of the raker after the raker shore is tightened with wedges.

# On the solid sole raker shore, install wedges between the bottom cleat and the base of the
raker and tighten them slightly.
! After adjusting the shims or spacers between the wall plate and the object being
shored to ensure full contact with the support point and the raker and the bottom of
the wall plate, finish tightening the wedges.

# Secure all wedges by placing a cleat against the sides of the wedges and nail it in place
or toe nail the wedges.
! Nails may need to be Duplex for future adjustment of the wedges.

# Attach Bottom Braces on Split Sole Raker Shores


! A 2” X 6” or two 2” X 4” are nailed just above the ground and attached as close to
the bottom of the raker as possible and the bottom of the wall plate with a fill block
near the middle for additional stability.

70
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

COMPONENTS OF THE RAKER SHORE (continued)

# Attach Diagonal Braces


! On the solid sole raker shore, a 2” X 6” or two 2” X 4” are nailed to both sides of the
wall plate and sole plate connection and mid point on the raker.
! On the split sole raker shore, a 2” X 6” or two 2” X 4” are nailed to both sides of the
wall plate and just above the bottom braces connection and mid point on the raker.

# Attach Horizontal Braces


! Connect the raker shores together near the top and bottom of the raker with at least
2” X 6” size material, or two 2" X 4".

# Attach“X” or “V” Braces


! All raker shore systems must be connected with either “X” or “V” bracing near the
top and bottom of the raker between at least two raker shores with at least 2” X 4”
size material.
! Attach the first brace to the rakers near the top and bottom between the upper
and lower horizontal braces.
! Attach the second brace to the upper and lower horizontal braces near the
rakers.

# After the raker shore is assembled, prevent the raker shore from sliding up the wall. (CSS
O/H-17)
! To attach the wall plate directly to a concrete and masonry wall.
- a minimum of two 1/2” drill-in anchors, lag screws or rebar should be placed
through the wall plate or four 1/2” drill-in anchors through two 9” long
channel brackets attached with two on each side of the wall plate near the
top.
- on concrete walls only, when backing material is attached to the wall plate,
the use of at least five 3” powder charge pins with washers through the
backing material on each side of the raker is acceptable.

71
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 06/98

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

COMPONENTS OF THE RAKER SHORE (continued)

72
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

COMPONENTS OF THE RAKER SHORE (continued)

! To attach the wall plate directly to a wood framed wall.


- a minimum of two 1/2” lag screws should be
placed through the wall plate directly into the wall
studs.
- when plywood backing material is attached to the
wall plate, the use of at least 8-16d nails through
the backing material directly into the wall studs
on each side of the raker is acceptable.
! Another method is to attach a engineered ledger (2” x 6”
minimum) to the wall above the wall plate.

# After the solid sole raker shore is assembled, prevent the sole
plate from sliding back away from the wall.
! To attach the sole plate directly to concrete, asphalt or
dirt. Drill a minimum of two 1” holes through the sole
plate, concrete or asphalt and pound 1” steel pickets or
rebar directly into the ground.
! To attach the sole plate to concrete and masonry.
- a minimum of two 1/2” drill-in anchors, lag screws
or rebar should be placed through the sole plate
or four 1/2” drill-in anchors through two 9” long
channel brackets attached with two on each side
of the sole plate.
- on concrete only, when backing material is
attached to the sole plate, the use of at least five
3” powder charge pins with washers through the
backing material on each side of the sole plate is
acceptable.
! An anchor can be secured to the ground or floor behind
the sole plate to prevent the sole plate from backing
away from the wall.
- timber anchors should be as least 4” X 4” size
lumber.
- steel anchors or channel brackets should be at
least 1/4” thick.
- concrete curbs, walls and other nearby secure
structures may also be used.

73
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: B — CONSTRUCTING SHORING SYSTEMS

COMPONENTS OF THE RAKER SHORE (continued)

How to Pre-Construct the Raker Shore

# The areas to be supported by raker shores should be


considered extremely dangerous most of the time. Temporary
(Flying) Friction raker shores may need to be erected prior to
building more permanent (Full Triangle) Fixed raker shores.

# One way to reduce the amount of time spent in front of unstable


structural elements receiving a raker shore is to pre-construct
the majority of the shore in a safe location near the shoring site.
! When possible, pre-construction of raker shores should
be your first choice.

# The Split Sole Raker Shore can be pre-constructed with the


wall plate, raker and bottom braces pre-attached.
! After placing the raker shore in position, final
adjustments are made with wedges at the sole plate in
the ground and the bottom braces and raker connection.

# The Solid Sole Raker Shore can be pre-constructed with the


wall plate, raker and sole plate pre-attached.
! After placing the raker shore in position, final
adjustments are made with wedges at the bottom cleat
on the sole plate.

74
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: C — VERTICAL AND LATERAL SHORING

WORK STATION SET UP & OPERATION

# The Vertical and Lateral Shore Work Station is one of three


work stations for Emergency Shoring. The other two work
stations are:
! The Raker Shore Work Station
! The Equipment and Cutting Work Station

# Vertical and Lateral Shoring Systems will be pre-constructed as


described in the “Constructing Shoring Systems” curriculum
prior to students arriving at the work station.
! The vertical and lateral shoring systems will be used to
further explain proper terminology, shoring material
placement and construction techniques.

# After conducting a thorough explanation of each vertical and


lateral shoring system the students will be divided into two half
squads.
! Half the shoring systems will be assigned to each half
squad to dismantle and reconstruct.
! When both half squads have finished, they will switch
shoring sites to dismantle and reconstruct the other half
of the shoring systems just reconstructed by the other
squad.
! When both half squads have finished with the other half
of the shoring systems, a final walk through with the
instructor will be conducted to answer any questions
and critique the shoring.
! Make any corrections to the shoring systems prior to the
start of the next squad rotation.

PRE-CONSTRUCTED VERTICAL AND LATERAL SHORING


SYSTEMS

The Vertical and Lateral Shoring Systems to pre-construct are:

# Vertical Shore with lumber and a minimum of three posts,


diagonal braces and gusset plates or cleats connecting the
header to the posts.

75
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: C — VERTICAL AND LATERAL SHORING

PRE-CONSTRUCTED VERTICAL AND LATERAL SHORING


SYSTEMS (continued)

# Ellis Shores with a minimum of two posts with gusset plates or


cleats connecting the header and sole plate to the posts.

! Ellis Clamp positions on posts:


- top clamp is attached 2” below top of the lower
post with two nails.
- bottom clamp is attached 12” below top clamp on
the lower post with two nails.
! Slide the upper post under the clamps and manually
raise to proper height and pull down on the top clamp.
! Attach the shore-jack to the lower post under the upper
post and lift on the handle.
! While pressure is being applied to the shore-jack, tap
downward on the unsecured end plate of the top clamp
and then tap downward on the unsecured end plate of
the bottom clamp with a hammer to lock the clamps in
place.
! For training purposes, do not nail the clamps to the
upper post. This will aid in a quicker dismantle and
reconstruction, but nailing the upper post is stressed
during the instruction of the Ellis Clamp system.
! Gusset plates or cleats connecting the header and sole
plate to the posts can be done before or after the shores
are in place.
! Diagonal braces are mentioned but not attached.

# Post Screw Jack (when available) with a minimum of two posts


with gusset plates or cleats connecting the header to the posts.
! Diagonal braces are mentioned but not attached.

# Hi-Lift Jacks with Extension Tubes (when available), using two


jacks to support the header and 3 X 3 Crosstie Crib Beds for
additional height as needed.

# Pipe Shores (when available) with a minimum of two shores


and 3 X 3 Crosstie Crib Beds for additional height as needed.
When available, a combination of 1 pipe shore and pneumatic
shore supporting the header is preferred for training purposes.

76
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: C — VERTICAL AND LATERAL SHORING

PRE-CONSTRUCTED VERTICAL AND LATERAL SHORING


SYSTEMS (continued)

# Pneumatic Shore (when available) with a minimum of two


shores and 3 X 3 Crosstie Crib Beds for additional height as
needed. When available, a combination of one pneumatic
shore and one pipe shore supporting the header is preferred
for training purposes.

# Window and/or Door Shore with lumber.


! Diagonal braces are mentioned but not attached.

# Horizontal Shore with two struts, using at least one lumber strut
with gusset plates or cleats connecting the strut to the wall
plates and one pipe screw jack.
! Cleats should be attached to the wall plates under the
struts where appropriate.
! Diagonal braces are mentioned but not attached.

# Laced Post System with a minimum of four 4” X 4” posts and 4”


X 4” headers and sole plates. (Build as a static display and
dismantle and rebuild during class ONLY if time permits.)
! Four posts 3’ - 4’ apart each way.
! Built in two half sections then laced together in a square
pattern.
! Lacing material is 2” X 4” lumber, nailed with two or
three Duplex 16p nails at each end.

Explain and demonstrate how to measure shoring materials while


deducting for wedges, the proper use of wedges and maximum
thickness while maintaining full contact with perpendicular shoring
materials.

# When possible, round off shoring material measurements to the


nearest inch to ease in marking and cutting.

# When using 4” X 4” X 18” wedges deduct the width of the


wedge from the length of the shoring material being measured.

77
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: C — VERTICAL AND LATERAL SHORING

PRE-CONSTRUCTED VERTICAL AND LATERAL SHORING


SYSTEMS (continued)

# When using 2” X 4” X 12” wedges deduct the width of the


wedge from the length of the shoring material being measured.

# 4” X 4” X 18” wedges can be moved together to a thickness of


6” while still maintaining full contact with a perpendicular 4” X
4”.

# 2” X 4” X 12” wedges can be moved together to a thickness of


2 1/4” while still maintaining full contact with a perpendicular 4”
X 4”.

SUPPLIES AND EQUIPMENT

# The use of same dimension lumber for the headers, wall plates,
sole plates, posts and struts will ease in the construction of the
shoring systems and make the braces more effective.

# The use of Duplex 16p and 8p nails will assist in the


dismantling of the shoring systems and reduce the amount of
destroyed shoring materials during the dismantling process.
! Use Duplex 8p nails with plywood gusset plates.

# Two dozen cleats and plywood gusset plates should be at the


shoring site due to the high probability of being destroyed
during the dismantling process.
! Cleats should be 2” X 4” X 12”
! Plywood gusset plates should be 12” X 12” X 3/4” thick.
! Smaller square gusset plates can easily be formed by
cutting the larger square gusset plates in half in both
directions making four 6” X 6” gusset plates.
! Triangle gusset plates (12” X 12” X 17”) can easily be
formed by cutting the larger square gusset plates in half
from one corner to the opposite diagonal corner.

78
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: C — VERTICAL AND LATERAL SHORING

SUPPLIES AND EQUIPMENT (continued)

# The following list of hardware should be at the vertical and


lateral shoring site:
! 4 Framing hammers
! 4 Single jack hammers, 3-lb.
! 4 Crow bars
! 2 Levels ( 1 @ 6” and 1 @ 3’ - 4’)
! 2 Carpenter belts w/ pencils/lumber crayons
! 2 Tape measures, 25’
! 2 Framing Square
! 1 A-Frame Ladder, 6’ minimum
! 1 Chalk Lines
! 1 Utility Razor Knife
! 25-lb. Duplex 16p nails
! 25-lb. Duplex 8p nails
! 1 Container for pulled nails, box, can, etc.
! 12 Ellis Clamps
! 2 Ellis Jacks
! 4 Ellis Post Screw Jacks
! 5 Pipe Screw Jacks, 2”
! 20’ Pipe, 2”, Schedule 40
! 2 each High Lift Jack with Ext. Tubes
! 1 SCBA Bottle, full
! 2 each Pneumatic Shore, 2’ - 6’ (when available)
! 1 Pneumatic Shore regulator & hose
! 1 set Pneumatic Shore ends & extensions

# The following list of lumber should be at the vertical and lateral


shoring site:
! 24 12” x 12” x 3/4” gusset plates
! 48 2” x 4” x 12” cleats
! 42 4” x 4” x 18” cribbing
! 24 2” x 4” x 18” cribbing
! 22 2” x 4” x 12” wedge pairs
! 24 4” x 4” x 18” wedge pairs
! 12 4” x 4” x 12’
! 36 4” x 4” x 8’
! 12 2” x 4” x 12’
! 18 2” x 4” x 8’

79
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: D — RAKER SHORING

Work Station Set Up and Operations

Raker shore systems will be properly preconstructed as described in


the Constructing Shoring Systems curriculum prior to students arriving
at the work station.

# The raker shore systems will be used to further explain proper


terminology, shoring material placement and construction
techniques.
! Proper methods to determine raker length using the
suppport point on the wall in feet, times 17 for 45o, and
times 14 for 60o, and the steel framing square will be
further explained.

# After conducting a thorough explanation of each raker shore


system, the students will be assigned to:
! Dismantle and reconstruct a solid sole raker shore and
reattach the braces.
! If time permits, dismantle and reconstruct a split sole
raker shore and reattach the braces.
! Measure and cut a raker to 45o and 60o.
! Make any corrections to the shoring systems prior to the
start of the next squad rotation.

Pre-constructed Raker Shore Systems

# The raker shore systems to preconstruct are:


! Friction (flying) raker shore.
! Fixed (full triangle) raker shore using a split sole plate.
! Fixed (full triangle) raker shore using a solid sole plate.
! Fixed (full triangle) raker shore with plywood backing
material attached to the wall plate, using two rakers to a
(simulated) second floor, with a notch and cleat at the
top support point and the solid or split sole plate
method.
! Connect all raker shore systems together with horizontal
braces.
! Two raker shores will be connected with "X" braces and
the other two raker shores will be connected to the X-
braced pair with "V" braces.

80
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: D — RAKER SHORING

Supplies and Equipment

# The use of same dimension lumber for the wall plates, rakers
and sole plates will ease in the construction of the shoring
systems and make the braces more effective.

# The use of Duplex 16p and 8p nails will assist in the


dismantling of the shoring systems and reduce the amount of
destroyed shoring materials during the dismantling process.

# Two dozen cleats and plywood gusset plates should be at the


shoring site due to the high probability of being destroyed
during the dismantling process.

! Cleats should be 2"X4" X 12".

! Plywood gussets should be 12" X 2" X ¾" thick.

! Smaller square gusset plates can easily be formed by


cutting the larger square gusset plates in half in both
directions making four 6" X 6" plates.

! Triangle gusset plates (12" X 12" X 17") can easily be


formed by cutting the larger square gusset plates in half
from one corner to the opposite diagonal corner.

! Using Duplex 8p nails with plywood gusset plates.

81
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: D — RAKER SHORING

Supplies and Equipment (continued)

# The following list of hardware should be at the Raker Shore


Work Station:
! 4 framing hammers
! 4 single jack hammers, 3 lb.
! 4 crow bars
! 2 levels (1 @ 6" and 1 @ 3 - 4 ft.)
! 2 carpenter belts w/ pencils/lumber crayons
! 2 tape measures, 25 ft.
! 2 steel framing squares
! 1 speed square
! 2 round point shovels
! 1 utility razor knife
! 2 cats paw nail pullers
! 1 container for pulled nails (can/box/etc.)
! 1 A-frame ladder (6 ft. min.)
! 25 lb. Duplex 16p nails
! 25 lb. Duplex 8p nails
! 1 chain saw, gasoline
! 1 rotary hammer
! 1 rotary hammer masonry bit (1" X 18")
! 200 ft. extension cords
! 20 rebar or steel pickets, 1"
! 2 4 X 8 sheets ¾" plywood
! 100 12" X 12" X ¾" gusset plates
! 36 2" X 4" X 12" wedge pairs
! 4 4" X 4" X 12" wedge pairs
! 4 6" X 6" X 16 ft. lumber
! 24 4" X 4" X 16 ft. lumber
! 30 4" X 4" X 12 ft. lumber
! 26 2" X 6" X 16 ft. lumber
! 48 2" X 4" X 12 ft. lumber

82
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: D — RAKER SHORING

The Steel Framing Square & Determining the Length of Raker


Shores

# The tongue:
! Shorter, narrower part is usually 16" long and 1½ wide.

# The body (blade):


! Usually 24" long and 2" wide.

# The Heel:
! The point where the tongue and the body meet on the
outside edge.

# The Face:
! The side with the manufacturer’s stamp.
! The side that is visible when the body is held in the left
hand and the tongue in the right hand.

# The Back:
! Opposite of the face.

The Scales and Tables

# There are seven different scales and tables on the steel


framing square:
! Four of the seven scales and tables commonly used for
rescue shoring.

# The Rafter Table:


! Found on the face of the square, on the body, starting
on the left.
! Used to determine the lengths of common, hip, valley
and jack rafters and the angles at which they must be
cut to properly fit ridge board/top plates for roof framing.
! Can be used to determine the length of the raker.

# The Brace Table:


! Found along the center of the back of the tongue, giving
lengths from 24” to 60” forming 45o angles.
! Determine the length of short rakers/corner bracing.

83
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: D — RAKER SHORING

The Scales and Tables (continued)

# The Hundredths Scale:


! Found on the back of the tongue, near the heel.
! Consists of one inch divided into one hundred parts.
! Useful to convert lengths given in hundredths.

# The Inch Scale:


! Found on both the body and the tongue along the inside
and outside edges of the square.
! Used for measuring inches and different graduations of
an inch.

Using the Steel Framing Square to Determine the Length of A


Raker

# Three Methods to determine the length of a raker with the steel


framing square:
! The Diagonal Method
! The Step-Off Method
! The Length-Per-Foot Run Method

# The Diagonal Method (Figure: 1 on Page 83)


! The least accurate of the three methods.
! Use the tongue to simulate the wall and the body to
simulate the floor.
! Use the inch markings on the outside edges as “foot
measurements”.
! Place the tape measure tip on the outside inch mark
simulating the support point on the wall and lay it across
the square until it intersects the outside inch mark on the
body simulating the contact point on the floor.
! The length of the tape measure when it is intersecting
the outside tongue and body inch marks will be the
length of the raker from tip to tip.
! Example: 9’ high support point on the wall, 12’ back from
the wall will be a 15’ long raker.

84
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: D — RAKER SHORING

Using the Steel Framing Square to Determine the Length of A


Raker (continued)

# The Step-Off Method (Figure: 2 on Page 83)


! Place the square on the raker with heel pointing up and
the body on the left side and the tongue on the right.
! Use the tongue to simulate the wall and the body to
simulate the floor.
! Use the inch markings on the outside edges as “foot
measurements”.
! Align the tongue outside edge inch mark representing
the height in feet of the support point on the wall with the
bottom edge of the raker.
! Align the outside edge inch mark on the body
representing the length in feet away from the wall the
contact point on the floor with the bottom edge of the
raker.
! Scribe a line, which will be the top cut of the raker along
the outer edge of the tongue.
! Mark the point where the outer edge inch mark of the
body contacts the bottom edge of the raker.
! Hold the square with the outer edge inch marks
remaining constant and “step” over the pencil mark to
the left and place outer edge inch mark of the tongue
next to it.
! Realign the same outer edge inch marks as before and
mark the point where the outer edge inch mark of the
body contacts the bottom edge of the raker.
! Repeat this “step” as may times as there are feet in the
length away from the wall.
! On the last “step”, scribe a line along the outer edge of
body for the bottom cut of the raker.
! Example: 9’ high support point on the wall, 12’ back from
the wall will be a 15’ long raker.
- 9” mark on the outer edge of the tongue and the
12” mark on the outer edge of the body is
“stepped” over these marks twelve times.
- Measuring the distance covered after twelve
“steps” is 15’ tip to tip.

85
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: D — RAKER SHORING

Using the Steel Framing Square to Determine the Length of A


Raker (continued)

# The Length-Per-Foot Run Method (Figure: 3 on Page 83)

! The most accurate of the three methods.

! Using the rafter table, located on the body, on the face.

! The first line under the inch graduations, the table if


broken down into inches and hundredths of an inch.

! Use the number 12 as the horizontal constant.

! When the height of the support point on the wall is eight


feet, then the pitch will be 8/12.
- When the height of the support point on the wall
is nine feet, then the pitch will be 9/12, etc., etc.

! The length-per-run table on the square, under the inch


number which corresponds to the height of the support
point on the wall in feet, will be the length of the raker in
inches and hundredths of an inch, which will stand for
the raker in feet.

! Example: 9’ high support point on the wall.


- Under the number 9 on the first line on the
length-per-foot run table is the number 15, which
represents 15” and stands for 15’ for the raker
from tip to tip.

86
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: D — RAKER SHORING

Using the Steel Framing Square to Determine the Length of A Raker (continued)

87
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: E — EQUIPMENT & CUTTING STATION

WORK STATION SET UP & OPERATION

# The Equipment and Cutting Work Station is one of three work


stations for Emergency Shoring. The other two work stations
are:
! The Vertical & Lateral Shore Work Station
! The Raker Shore Work Station

# The Equipment and Cutting Work Station will be properly set


up prior to students arriving.

# After conducting a thorough explanation and demonstration,


the squad will be provided opportunities to practice with the
tools and equipment commonly used to cut and create shoring
materials.

EQUIPMENT AND CUTTING ASSIGNMENTS

# Thoroughly explain and demonstrate the proper use and safety


of the following tools:
! Chain Saw (Gas and Electric)
! Rotary Saw
! Circular Saw (7 1/4”)
! Pipe Cutter
! Nail Gun, Pneumatic & Gas Fired (when available)
! Hilti Kwik Bolt System
! Powder charge ram sets with pins and washers
! Tape measure and Tri-Square

# Construct a cutting table and jig to secure 4” X 4”, 2” X lumber


on edge and larger dimension materials while being cut. (See
next page.)

88
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: E — EQUIPMENT & CUTTING STATION

EQUIPMENT AND CUTTING ASSIGNMENTS (continued)

89
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: E — EQUIPMENT & CUTTING STATION

EQUIPMENT AND CUTTING ASSIGNMENTS (continued)

Explain and demonstrate how to cut wedges.

# Cutting 4” X 4” X 18” wedges.


! Mark a full length 4” X 4” X 8’ every 18”.
! This will make five pair of wedges with a 6” piece left to
secure the last pair while being cut.
! Mark a diagonal line from the top edge of one 18” line to
the bottom edge of the opposite 18” line every 18”.

# Cutting Wedges with a Rotary Saw


! Score the line with the blade 1/2” deep.
! Second pass cut half way through.
! Third pass cut all the way through.
! Cut the other half of the wedge off of the remaining
4” X 4” at the 18” line.

# Cutting Wedges with a Chain Saw


! Align the blade with the diagonal line on the 4” X 4” with
the tip of the saw pointing towards the cutting table.
! Start cutting with the tip of the saw bar approximately 2”
past the edge of the 4” X 4”.
! Once the tip of the saw bar is through the full thickness
of the 4” X 4” start to drag the saw towards the opposite
end of the diagonal line.
! Once the heel of the saw is past the end of the 4” X 4”,
flatten the saw and cut the remaining part of the 4” X 4”
with the full bar.
! Cut the other half of the wedge off of the remaining 4” X
4” at the 18” line.

# Cutting Wedges with a Circular Saw


! Difficult to do unless the saw has at least a 10 1/4”
blade.
! Circular saws with blades 10 1/4” or larger need only
one pass from corner to corner along the diagonal line.
! Circular saw with blades less than 10 1/4” require
marking and cutting on both sides and do not always
align correctly.

90
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: E — EQUIPMENT & CUTTING STATION

EQUIPMENT AND CUTTING ASSIGNMENTS (continued)

# Cutting 2” X 4” X 12” wedges


! Mark a full length 2” X 4” X 8’ on edge, every 12”.
! This will make seven pair of wedges with a 12” piece left
to secure the last pair while being cut.
! Mark a diagonal line from the top edge of one 12” line to
the bottom edge of the opposite 12” line every 12”.

# Cutting Wedges with a Rotary Saw and Chain Saw


! Start the cut a little past the mark away from the corner
to prevent making the wedge too thin.

Explain and demonstrate the personnel positions at the cutting station


as described in the “Constructing Shoring Systems” curriculum.

# Explain how the Shore Assembly Team “Measure” will relay the
size and length of material to cut and that number will already
account for the thickness of the header, sole plate and wedges.
The “Cutter” simply cuts what is requested.

# Always mark the length of cut lumber on the lumber, for quicker
identification and installation of the correct piece of shoring
material.

# The cutting team will mark and cut two pair of field wedges.
! Cut one pair with a Rotary Saw
! Cut the other pair with a Chain Saw

# Explain the importance of a square cut and the strength loss


when shoring materials do not have good surface contact or
are out of plumb.
! Five degrees out of plumb can equal a 50% loss of
surface contact and strength.

91
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: E — EQUIPMENT & CUTTING STATION

EQUIPMENT AND CUTTING ASSIGNMENTS (continued)

# Explain the most common sizes of cleats and plywood gusset


plates.

! Cleats are usually 2” X 4” X 12”.


! Plywood gusset plates are usually 12” X 12” X 3/4” thick.
! Smaller square gusset plates can easily be formed by
cutting the larger square gusset plates in half in both
directions making four 6” X 6” gusset plates.
! Triangle gusset plates (12” X 12” X 17”) can easily be
formed by cutting the larger square gusset plates in half
from one corner to the opposite diagonal corner.

# Explain and demonstrate how to cut the end of the rake at 45


and 60 degrees.
! Mark the end of the rake to be cut
! 4” X 4” = 3 1/2” from the end for 45 degrees
! 4” X 4” = 6” from the end for 60 degrees
! 6” X 6” = 5 1/2” from the end for 45 degrees
! 6” X 6” = 9” from the end for 60 degrees
! Mark a diagonal line from the upper end of the lumber to
the mark on the lower edge of the lumber and cut the
end off at this angle.
! Measure 1 1/2” wide on the tapered end and mark a line
on the cut side for the relief cut to make full contact with
the end of a cleat.
! Cut this line from the cut side with a circular saw.

# The cutting team will mark and cut the end of a rake at 45
degrees and after cutting the angle end cut off the rake, they
will cut the end of the rake at 60 degrees.

92
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: E — EQUIPMENT & CUTTING STATION

EQUIPMENT AND CUTTING ASSIGNMENTS (continued)

Explain and demonstrate how to notch lumber for added stability of a


crib bed or a raker shore wall plate support point.

# Notched Cribbing
! Mark 2” from the end of the cribbing to prevent the end
piece from splitting off.
! From the 2” mark, make a second mark the true
thickness of the lumber being used for cribbing.
- 4” X 4” = 3½ ” - 6” X 6” = 5 ½”
! Adjust a circular saw to the depth of 1” and cut the two
lines and then between the two lines every 1/2” inch.
! Ensure saw is unplugged while adjusting blade depth.
! Hit the sliced pieces of lumber with a hammer towards
the remaining cribbing to break off the pieces.
! Clean out the notch with the claw end of the hammer
until smooth.
! Have one of the squad members repeat this process on
the opposite end of the cribbing.
! Notches should only be made on one side of the
cribbing to maintain the thickness/strength of lumber.

# Notched Raker Shore Wall Plate Support Point


! Used in conjunction with a top and bottom cleat when
using a 60 degree raker.
! Mark 2’ down from the top of the raker shore wall plate.
! From the 2’ mark, make a second mark two times the
size what the raker lumber is called.
- 4” X 4” = 8”
- 6” X 6” = 12”
! Adjust a circular saw to the depth of 1” and cut the two
lines and then between the two lines every 1/2” inch.
! Ensure saw is unplugged while adjusting blade depth.
! Hit the sliced pieces of lumber with a hammer towards
the remaining wall plate to break off the pieces.
! Clean out the notch with the claw end of the hammer
until smooth.
! Attach a 2’ cleat above the notch and flush with the top
of the notch.
! Demonstrate how the angle end cut of a rake will
connect in the wall plate notch.

93
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: E — EQUIPMENT & CUTTING STATION

SUPPLIES AND EQUIPMENT

# The following tools should be available at the Equipment and


Cutting Work Station:
2 Framing Hammer
2 Crow Bars
2 Carpenter Belt w/ lumber pencil
2 Tape Measure - 25'
2 Tri-Square
1 Speed Square
1 Chalk Lines
1 Utility Razor Knife
1 Container for pulled nails- can, box, etc.
1 Pipe Screw Jacks, 2"
1 Pipe, 2", Schedule 40, 1 foot section
1 Pipe Cutter, 2" capabililty
25 lbs.Nails,16 p Duplex
25 lbs.Nails, 8 p Duplex
1 Chain Saw, Gasoline
1 Chain Adjustment Tool
1 Spare Chain
1 Spare Bar (at the Base of Ops)
1 Spare Spark Plug (at the Base of Ops)
1 Rotary Saw, Gasoline w/ Carbide Tip
1 Belt Adjustment Tool
1 Spare Blade, Carbide Tip (at the Base of Ops)
1 Spare Belt (at the Base of Ops)
1 Spare Spark Plug (at the Base of Ops)
1 Gas Can, 5 gal. w/ pre-mix for saws
1 Chain Saw, Electric
1 Spare Chain
1 Chain Adjustment Tool
1 Bar oil
1 7¼" Circular Saw, Electric
1 Spare Blade, Carbide Tip, 7¼"
1 Wrench to replace blade
2 Spare Blade, carbide tip, 7¼"(at the Base of Ops)
1 110 Volt Power Supply (min. 15A, 20A preferred)
200' Extension Cords
1 Hilti Kwik Bolt
1 Hilti Ramset Tool w/ kit
10 Hilti Ramset Powder Charge strips

94
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: E — EQUIPMENT & CUTTING STATION

SUPPLIES AND EQUIPMENT (continued)

1 Box Hilti Ramset Pins, 3” w/ washers


1 Paslode Nail Gun (when available)
2 Paslode Nail Gun, gas canisters
1 casePaslode Nail Gun, 16p nails
1 casePaslode Nail Gun, 8p nails
1 Pneumatic Nail Gun
1 each Pneumatic Nail Gun hose & regulator
2 SCBA Bottle, full
1 SCBA Back Pack
1 case Pneumatic Nail Gun Nails, 16 p
1 case Pneumatic Nail Gun Nails, 8 p
1 Pneumatic Nail Gun Oil
1 case Pneumatic Nail Gun Nails,
Duplex 16 p (Duofast, Model CN 350 SP)
1 case Pneumatic Nail Gun Nails,
Duplex 8 p (Duofast, Model CN 350 SP)

# The following lumber should be available at the Equipment and


Cutting Work Station:

2 Cleats, 2” X 4” X 12”
2 Plywood gusset plates,12” X 12” X 3/4” thick
4 Plywood gusset plates, 6” X 6” X 3/4” thick
2 Triangle gusset plates, 12” X 12” X 17”
2 Wedges, 4” X 4” X 18”
2 Wedges, 2” X 4” X 12”
6 Cribbing, 4” X 4” X 18”
2 Plywood Sheets, 4’ X 8’ X 3/4” thick
6 2” X 4” X 8’
6 4” X 4” X 8’
6 Wooden Pallets

95
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: F — EMERGENCY SHORING SCENARIOS

Shoring Scenarios Set Up & Operation

The Shoring Scenarios are structured somewhat similar to the


Emergency Shoring Work Stations to duplicate familiar situations and
increase student retention of the subject matter.

# During the drill scenarios, instructors shall remain in-charge of


the same shoring work stations they taught.

# The three shoring scenarios are:


! Equipment and Cutting Station
! Raker Shore Systems
! Vertical & Lateral Shoring Systems

# The shoring scenarios are allotted 3 hours which is divided into


three individual squad assignments and one group activity with
all three squads.
! Scenario #1 Assignment 45 minutes
Break and Rotate 5 minutes

! Scenario #2 Assignment 45 minutes


Break and Rotate 5 minutes

! Scenario #3 Assignment 45 minutes


Break and Rotate 5 minutes

! Review & Critique 30 minutes

# Each squad will individually complete all three shoring


scenarios.

! The Vertical & Lateral Shoring System scenarios will be


completed in three different locations on the Emergency
Shoring site.

! The Equipment and Cutting Station and Raker Shore


System scenarios will be completed at the same location
by all three squads.

96
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: F — EMERGENCY SHORING SCENARIOS

Shoring Scenarios Set Up & Operation (continued)

# The three squads will rotate through all three scenarios in the
following order:

! A — Equipment and Cutting Station

! B — Raker Shore Systems

! C — Vertical & Lateral Shoring Systems

SQUAD HOUR 1 HOUR 2 HOUR 3

1 A B C

2 C A B

3 B C A

# The Shoring Scenarios will be properly set up prior to students


arriving.

! All required tools, equipment and supplies will be at the


Emergency Shoring scenario site.

! A location will be pre-identified for each of the three


scenario assignments.

# After conducting a thorough explanation of squad rotation,


scenario assignments and issuing the Rescue Squad Officers
a radio (when available), the squads will complete the scenario
assignments.

97
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: F — EMERGENCY SHORING SCENARIOS

Shoring Scenario Assignments

# Equipment and Cutting Station

! The instructor shall thoroughly describe to the Rescue


Squad Officer that the squad is responsible for providing
any and all tools, shoring materials and cutting for both
Shore Assembly Teams.

! The Rescue Squad Officer assigns squad members to


Cutting Team positions.

- The Cutting Team will set up the equipment and


cutting station.

- The Cutting Team will build a cutting table and


jig.

- The Cutting Team will cut shoring materials for


both Shore Assembly Teams conducting shoring
operations utilizing any of the tools, equipment
and techniques demonstrated during the
Emergency Shoring class.

- The Cutting Team will deliver requested tools,


equipment and shoring materials to both Shore
Assembly Teams.

98
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: F — EMERGENCY SHORING SCENARIOS

Shoring Scenario Assignments (continued)

# Raker Shore Systems


! The instructor shall thoroughly describe to the Rescue
Squad Officer the type of shores to be constructed and
indicate the exact location where the shores are to be
erected.
- One solid sole raker shore will be
pre-constructed and in the proper location for the
start of the raker shore system as described in
Section V, Supplies and Equipment.
- All raker shores constructed by the squads will
be connected to this original shore by braces.
! The Rescue Squad Officer assigns squad members to
Shore Assembly Team positions.
! The squad will construct the following by utilizing any of
the tools, equipment and techniques demonstrated
during the Emergency Shoring class:
- A minimum of one solid sole raker and attach it to
the pre-constructed raker shore
- The squad may construct as many raker shores
as time permits.
- All raker shores will be connected by horizontal
braces at the top and bottom of the raker shore.
- All raker shores will be laterally supported by
either “X” or “V” braces.

# Vertical & Lateral Shoring Systems


! The instructor shall thoroughly describe to the Rescue
Squad Officer the type of shores to be constructed and
indicate the exact location where the shores are to be
erected.
! The Rescue Squad Officer assigns squad members to
Shore Assembly Team positions.
! The squad will complete the following vertical and lateral
shoring systems utilizing any of the tools, equipment
and techniques demonstrated during the Emergency
Shoring class:
- One window or door shore
- One vertical shore with three posts
- One horizontal shore
- If time permits, one laced post with four posts

99
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: F — EMERGENCY SHORING SCENARIOS

Shoring Scenario Review and Critique

# The shoring scenario review and critique will be conducted by


all three instructors and all three squads at the same time.

# Each shoring scenario assignment will be reviewed, discussed


and lessons learned identified.

# The four shoring sites will be reviewed first and the equipment
and cutting station will be reviewed last.

# Each Rescue Squad Officer will be encouraged to describe any


problems encountered and how the squad overcame them and
provide any helpful hints for the entire group.

# The three instructors shall describe any positive observations


and identify corrective measures needed to improve any
improperly constructed shoring systems.

Supplies and Equipment

# All shoring equipment and materials at the Emergency Shoring


Work Station shall be brought to a central location near the
Equipment and Cutting Work Station.

# One solid sole raker shall be brought from the Raker shore
Work Station and assembled at the location where the raker
shore system will start.
! The remaining raker shores will be left pre-constructed
and in tact at the Raker Shore Work Station.

# All vertical and Lateral shoring systems will be disassembled


and brought to the Equipment and Cutting Station.

# All pre-constructed Lateral and Vertical shoring systems will be


reassembled during the Secure Work Sites and Prep for the
next day time allotment.

# The pre-constructed solid sole raker shore will be returned to


the Raker Shore Work Station and reattached to the braces
during the Secure Work Sites for the next day time allotment.

100
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: G — EMERGENCY SHORING LOGISTICS LIST

Item: Minimum number of:

Lumber 6" X 6" X 16' 4 each


4" X 4" X 16' 24
4" X 4" X 12' 42
4" X 4" X 8' . . . . . . . . . . . . . . 42
2" X 6" X 16' 36
2" X 4" X 12' 60
2" X 4" X 8' . . . . . . . . . . . . . . 24

Cribbing 4" X 4" X 18" 48


2" X 4" X 18" 24

Cleats 2" X 4" X 12" 48

Plywood
Gussets 12" X 12" X 3/4" . . . . . . . . . . . . 128

Plywood 4' X 8' X 3/4" . . . . . . . . . . . . . . 4


Sheets

Wedges 4" X 4" X 18" 30 pair


2" X 4" X 12" 60 pair

Wooden
Pallets . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 each

Radios . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

Water Jug, 5 gal. . . . . . . . . . . . . . . . . . . . 1


Cups . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 200

Dust Masks . . . . . . . . . . . . . . . . . . . . . . . . 1 Case

Single Jack Hammer, 3 lb. . . . . . . . . . . . . 8 each


Sledge Hammer, 10 lb. . . . . . . . . . . . . . . . 1
Framing Hammer . . . . . . . . . . . . . . . . . . . 10
Crow Bars . . . . . . . . . . . . . . . . . . . . . . . . . 10
Carpenter Belt w/ lumber pencil . . . . . . . . 6
Level, 3' - 4' . . . . . . . . . . . . . . . . . . . . . . . 2
Level, 6" . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Tape Measure - 25' . . . . . . . . . . . . . . . . . 6

101
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: G — EMERGENCY SHORING LOGISTICS LIST

Item: Minimum number of:

Tri-Square .............. 2
Speed Square .............. 2
Steel Framing Square . . . . . . . . . . . . . . 4
Chalk Lines .............. 2
Utility Razor Knife .............. 3
Cats Paw Nail Puller .............. 2
Container for pulled nails- can, box, ? . . . 3
Ellis Clamps .............. 12
Ellis Jacks .............. 2
Ellis Post Screw Jacks . . . . . . . . . . . . . . 4
Shovel, Round Point .............. 2
Pipe Screw Jacks, 2" .............. 6
Pipe, 2", Schedule 40, 10 foot section . . . 2
Pipe Cutter, 2" capabililty . . . . . . . . . . . . . 1
High Lift Jack with Ext. Tubes . . . . . . . . . 2 each

Nails,16 p Duplex . . . . . . . . . . . . . . 75 lbs.


Nails, 8 p Duplex . . . . . . . . . . . . . . 75 lbs.

Rotary Hammer . . . . . . . . . . . . . . 1 each


Rotary Hammer Masonry Bit, 1" X 18" . . . 1
Rebar or Steel Pickets, 1" . . . . . . . . . . . . 20

Chain Saw, Gasoline .............. 2


Chain Adjustment Tool1
Spare Chain .............. 1
Spare Bar .............. 1 (at the Base of Ops)
Spare Spark Plug .............. 1 (at the Base of Ops)

Rotary Saw, Gasoline w/ Carbide Tip . . . . 1


Belt Adjustment Tool .............. 1
Spare Blade, Carbide Tip . . . . . . . . . . . . 1 (at the Base of Ops)
Spare Belt .............. 1 (at the Base of Ops)
Spare Spark Plug .............. 1 (at the Base of Ops)

Gas Can, 5 gal. w/ pre-mix for saws . . . . . 1

102
FEMA US&R RESPONSE SYSTEM
RESCUE SPECIALIST TRAINING MANUAL 11/94

VI. EXTRICATION OPERATIONS


MODULE ONE: G — EMERGENCY SHORING LOGISTICS LIST

Item: Minimum number of:

Chain Saw, Electric .............. 1


Spare Chain .............. 1
Chain Adjustment Tool1
Bar oil .............. 1

7 1/4" Circular Saw, Electric . . . . . . . . . . . 1


Spare Blade, Carbide Tip, 7 1/4" . . . . . . . 1
Wrench to replace blade . . . . . . . . . . . . . 1
Spare Blade, Carbide Tip, 7 1/4" . . . . . . . 2 (at the Base of Ops)

110 Volt Power Supply 1 (tower outlets OK)


Extension Cords 400'

Hilti Kwik Bolt .............. 1

Hilti Ramset Tool w/ kit 1


Hilti Ramset Powder Charges . . . . . . . . . . 10 strips
Hilti Ramset Pins, 3" w/ washers . . . . . . . 1 Box

Paslode Nail Gun .............. 1 (when available)


Paslode Nail Gun, gas canisters . . . . . . . 2
Paslode Nail Gun, 16p nails . . . . . . . . . . . 1 case
Paslode Nail Gun, 8p nails . . . . . . . . . . . . 1 case

Pneumatic Nail Gun .............. 1


Pneumatic Nail Gun hose & regulator . . . 1 each
SCBA Bottle, full .............. 3
SCBA Back Pack .............. 1
Pneumatic Nail Gun Nails, 16 p . . . . . . . . 1 case
Pneumatic Nail Gun Nails, 8 p . . . . . . . . . 1 case
Pneumatic Nail Gun Oil1

Pneumatic Nail Gun Nails, Duplex 16 p . . . 1 case (Duofast M#CN350 SP)


Pneumatic Nail Gun Nails, Duplex 8 p . . . . 1 case (Duofast M#CN350 SP)

Pneumatic Shore, 2' - 6' . . . . . . . . . . . . . . 2 each (when available)


Pneumatic Shore regulator & hose . . . . . . 1
Pneumatic Shore ends & extensions,1 set

A-Frame Ladder, 6' minimum . . . . . . . . . . 2 each

103

You might also like