Monthly ...Report
Monthly ...Report
S# Project / Lot / Block / Item of ACB PVW EVE PAC MCV ISV ETC AEC VAC
CPI SPI AOI
Work (000,) (ETB) (ETB) (ETB) (ETB) (ETB) (%) (ETB) (%) (ETB) (ETB) (ETB) (%)
Calculation / Basis / Source Estimate Plan Report Report EVE - PAC MCV / PVW % EVE / PAC EVE - PVW EVE - PVW % EVE / PVW ACB / CPI ETC - PAC ACB - ETC VAC - ACB % (CPI + SPI) / 2 Status
Re. No.
Ref. No. in Metric Explanation 1 2 3 4 5 6 7 8 9 10 11 12 13
PROJECT CBE LIDETA BRANCH 283,850,688.56 1.00 3,017,003.53 1 3,017,003 301700253.5% 3017003.53 3,017,003 301700253.5% 3017003.53 93 94 283,850,594 100.0% 3017003.53 GREEN
I MAIN CONTRACT 283,850,688.56 1.00 3,017,003.53 1 3,017,003 301700253.5% 3017003.53 3,017,003 301700253.5% 3017003.53 93 94 283,850,594 100.0% 3017003.53 GREEN
A SUBSTRUCTURE 65,195,998.40 2,184,389.84 3,017,001.53 1 3,017,001 138.1% 3017001.53 832,612 38.1% 1.38 21 22 65,195,977 100.0% 1508501.46 GREEN
41,645,958.00 1 1 1 - 0.0% 1.00 - 0.0% 1.00 41,645,958 41,645,957 - 0.0% 1.00 GREEN
1 Concrete work
2,809,816.00 1 1 1 - 0.0% 1.00 - 0.0% 1.00 2,809,816 2,809,815 - 0.0% 1.00 GREEN
2 Block work
2,400,656.00 1 1 1 - 0.0% 1.00 - 0.0% 1.00 2,400,656 2,400,655 - 0.0% 1.00 GREEN
3 Roof work
1,439,731.00 1 1 1 - 0.0% 1.00 - 0.0% 1.00 1,439,731 1,439,730 - 0.0% 1.00 GREEN
4 Steel structure
2,808,068.00 1 1 1 - 0.0% 1.00 - 0.0% 1.00 2,808,068 2,808,067 - 0.0% 1.00 GREEN
5 Carpentery & Joinery
16,391,300.00 1 1 1 - 0.0% 1.00 - 0.0% 1.00 16,391,300 16,391,299 - 0.0% 1.00 GREEN
6 Conference Hall Fixture
32,666,138.56 1 1 1 - 0.0% 1.00 - 0.0% 1.00 32,666,139 32,666,138 - 0.0% 1.00 GREEN
7 Metal work
38,365,129.50 1 1 1 - 0.0% 1.00 - 0.0% 1.00 38,365,130 38,365,129 - 0.0% 1.00 GREEN
8 Finishing works
1,756,960.00 1 1 1 - 0.0% 1.00 - 0.0% 1.00 1,756,960 1,756,959 - 0.0% 1.00 GREEN
9 Painting
39,216,134.20 1 1 1 - 0.0% 1.00 - 0.0% 1.00 39,216,134 39,216,133 - 0.0% 1.00 GREEN
10 Electrical installation
6,511,020.00 1 1 1 - 0.0% 1.00 - 0.0% 1.00 6,511,020 6,511,019 - 0.0% 1.00 GREEN
11 Sanitary installation
8,857,602.00 1 1 1 - 0.0% 1.00 - 0.0% 1.00 8,857,602 8,857,601 - 0.0% 1.00 GREEN
12 Mechanical works
17,739,180.00 1 1 1 - 0.0% 1.00 - 0.0% 1.00 17,739,180 17,739,179 - 0.0% 1.00 GREEN
13 Auditory & Video installation
6,046,996.90 1 1.00 1 - 0.0% 1.00 - 0.0% 1.00 6,046,997 6,046,996 - 0.0% 1.00 GREEN
C. SITE WORK
1,263,963.60 1 1 1 - 0.0% 1.00 - 0.0% 1.00 1,263,964 1,263,963 - 0.0% 1.00 GREEN
1 Compund road and parking
794,750.00 1 1 1 - 0.0% 1.00 - 0.0% 1.00 794,750 794,749 - 0.0% 1.00 GREEN
2 Fence work
21,000.00 1 1 1 - 0.0% 1.00 - 0.0% 1.00 21,000 20,999 - 0.0% 1.00 GREEN
3 Site Green area work
3,967,283.30 1 1 1 - 0.0% 1.00 - 0.0% 1.00 3,967,283 3,967,282 - 0.0% 1.00 GREEN
4 Sanitary installation
10.Porcelain m2 - 99 565.22
Total
Tekleberhan Ambaye Construction Plc
CBE Lideta Branch Office Building
VI) Profit & Loss Analysis Month:- Yekatit 2006E.C.
Item no Description Previous This Month To date Remarks
Expenditure
A. Direct cost Total consumed
Amount deducted from total expense ( Materials issued but not used)
Quantity Quantity
Item no Description Unit Unit cost Amount Remarks
Prev. Mesk.
1 ɸ8 berga 417.11 94 39208.34
Total 161,333.14
Project:-
Client:-
Reporting Period:-
SUMMARY
Previous This month Cummulative
Item Contract Planned Executed Planned Executed Planned Executed % of Payment
No Description Amount Amount Amount % Amount Amount % Amount Amount % Contra. Certified Remark
TOTAL FOR LOT-1 & LOT-2
PODIUM-1 & PODIUM-2
1 SUB- STRUCTURE WORKS ###
A1 EXCAVATION & EARTH WORK 8,229,208.36 10,258,689.80 10,258,686.36 100% - 871,243.96 #DIV/0! 10,258,689.80 11,129,930.32 108.49% 135.25% ###
A2 SUBSTRUCTURE CONCRETE WORK 57,077,116.05 70,607,260.78 70,607,260.78 100% - 6,784,994.70 #DIV/0! 70,607,260.78 77,392,255.48 109.61% 135.59%
A3 SPECIALIZED CONCRETE PILE & WALL STRUCTURAL SHORING WORKS 21,106,180.00 20,838,000.00 20,838,000.00 100% - (110.72) 20,838,000.00 20,837,889.28 100.00% 98.73% ###
A4 SUB STRUCTURE MASONERY WORK 177,486.42 - -
A5 BLOCK WORK 323,907.95 605,042.59 - 605,042.59 -
A6 WATER PROOFING WORKS 7,364,316.01 446,900.92 - #DIV/0! 446,900.92 - 0.00% 0.00%
A7 CARPENTER & JOINERY 250,903.20 -
A8 FINISHING WORKS 9,127,828.21 - - -
A9 PAINTING WORKS 1,062,733.96
Sub Total A 104,719,680.16 102,755,894.09 101,703,947.14 - 7,656,127.94 #DIV/0! 102,755,894.09 109,360,075.08 106.43% 104.43%
2 BLOCK-A,B,C & D
SUPER STRUCTURE WORKS
B1 CONCRETE WORK 251,311,772.56 96,809,868.02 96,809,868.02 31,074,372.35 51,422,010.29 165.48% 127,884,240.37 148,231,878.31 115.91% 58.98%
B2 BLOCK WORK 15,962,918.35 2,444,671.56 175,238.00 1,782,543.00 1,346,325.08 4,227,214.56 1,521,563.08
B3 ROOFING AND WATER PROOFING WORKS 4,175,384.90 -
B4 CARPENTRY AND JOINERY 77,917,837.54 -
B5 FINISHING WORKS 113,371,371.52 879,722.52 - 879,722.52 -
B6 PAINTING 6,139,884.40 -
B7 STEEL STRUCTURE AND ROOFING 2,951,216.00 -
3 METAL WORKS FOR LOT-1 & LOT-2 -
Metal Works Total carried to summary 77,872,293.12 -
4 ELECTRICAL WORKS FOR LOT-1 & LOT-2 -
E1 DISTRIBUTION BOARDS 2,388,891.00 -
E2 CONDUITS AND PIPES 486,400.00 126,370.32 126,370.32 - #DIV/0! 126,370.32 126,370.32 100.00% 25.98%
E3 MANHOLE 36,130.00 - 0.00%
E4 FEEDER CABLES 2,906,950.00 - 0.00%
E5 LIGHT POINTS 3,232,000.00 444,495.00 444,495.00 169,800.00 444,495.00 614,295.00 19.01%
E6 SWITCHES 1,030,135.00 - 0.00%
E7 SOCKET OUTLET POINTS 2,863,458.00 - 0.00%
E8 SOCKET OUTLETS 1,888,237.00 - 0.00%
E9 BELL CALL SYSTEM 2,934,820.00 - 0.00%
E10 DATA / TELECOM POINTS/OUTLETS AND DATA / TELECOM EQUIPMENT 3,034,478.00 36,766.96 36,766.96 - 36,766.96 36,766.96 100.00% 1.21%
E11 TV SYSTEM 1,782,216.00 -
E12 FIRE ALARM SYSTEM 4,104,000.00 -
E13 CCTV SYSTEM 4,860,000.00 -
E14 PUBLIC ADDRESS SYSTEM 1,274,130.00 -
E15 LIGHT FITTING AND LAMPS 17,422,505.00 -
E16 EXIT SIGN 404,326.00 -
E17 LIFT 29,484,000.00 -
CABLE TRAY TYPE WIBE OR WQUIVALENT APPROVED (WIBE CATALOGE SPECIFCATION IS TAKEN AS GUIDE
E18 LINE AS IT HAS GOOD REPUTATION IN LARGE PROJECTS IN THIS COUNTRY.) 387,450.00 -
E19 FUSE DISTRBUTION BORDS, KWH-METERES and FEEDER CABLES (Supply and Installation by EEPCo.) 2,387,360.00 -
E20 LIGHTNING PROTECTION AND LOW VOLTAGE SYSTEM EARTHING 1,218,248.00 3,781.14 3,781.14
E21 STAND BY GENERATOR SET & Transformer 13,387,268.00 -
5 SANITERY WORKS FOR LOT-1 & LOT-2 -
S1 SANITARY EQUIPMENT (FIXTURES) 27,026,344.00 -
S2 WATER SUPPLY PIPES AND FITTINGS 11,010,029.00 -
S3 WASTE, VENT AND RAIN WATER PIPES AND ACCESSORIES 1,937,645.00 121,931.43 226,320.00 - 348,251.43 - 0.00% 0.00%
S4 WATER PROFFING WORK SPECIAL CHARACTERSTICS 6,880,582.00 1,532,441.30 1,532,441.30 - 72,262.71 1,532,441.30 1,604,704.01 104.72% 23.32%
S5 SITE WORK 6,751,968.40 - - 0.00%
S6 SUB SOIL DRAINAGE SYSTEM 3,212,706.00 2,900,803.33 2,900,803.33 - 85,004.52 2,900,803.33 2,985,807.85 102.93% 92.94%
6 SITE WORKS FOR LOT-1 & LOT-2
Site Works Total carried to summary 1,908,379.70
Sub Total B 705,943,334.49 105,297,070.44 102,025,982.93 33,083,235.35 53,099,183.74 160.50% 138,380,305.79 155,125,166.67 112.10% 21.974% - -
Grand Total A +B (With out 15%VAT) 810,663,014.65 208,052,964.53 203,729,930.07 - 33,083,235.35 60,755,311.68 183.64% 241,136,199.88 264,485,241.75 109.68% 32.63% - -
REBATE 1.5% 12,159,945.22 3,120,794.47 3,055,948.95 - 496,248.53 911,329.68 183.64% 3,617,043.00 3,967,278.63 109.68% 32.63% - -
GRAND TOTAL AFTER REBATE 798,503,069.43 204,932,170.06 200,673,981.12 - 32,586,986.82 59,843,982.00 183.64% 237,519,156.88 260,517,963.12 109.68% 32.63% - -
A. SUB-STRUCTURE
PODIUM-1
A1. EXCAVATION & EARTH WORK
1.1 Bulk excavation from stripped level in Black,soft,high plastic silty clay soil to
an average depth of 150cms and bring to a levelled surface.
m3 77.0 2,218.9 170,856.8 4,718.3 363,311.5 4,718.33 363,311.47 -333.0 -25,639.5 4,718.3 363,311.5 4,385.4 337,672.0
1.2 Bulk excavation to reduce level in Gray, Stiff, high plastic silty Clay to a
depth exceeding 150cms but not exceeding 300cms. m3 93.0 2,218.9 206,359.6 4,513.9 419,791.4 -128.5 -11,954.3 4,513.9 419,791.4 4,385.3 407,837.1
4,513.89 419,791.39
1.3 Bulk excavation to reduce level in Gray, Stiff, high plastic silty Clay to a
depth exceeding 300cms but not exceeding 450cms. m3 102.0 2,218.9 226,329.8 1,738.1 177,286.1 411.4 41,965.8 1,738.1 177,286.1 2,149.5 219,251.9
1,738.10 177,286.13
1.4 Bulk excavation to reduce level in Gray, Stiff, high plastic silty Clay soil to a
depth exceeding 450cms but not exceeding 600cms. -
m3 123.0 739.6 90,975.7 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0
1.5 Bulk excavation to reduce level in Gray,fine, grained,fresh welded tuff soil
to a depth exceeding 450cms but not exceeding 600cms. -
m3 123.0 1,479.3 181,951.4 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0
1.6 Ditto as above but in black decomposed gravel and silt with boulder
materials -
m3 123.0 1,479.3 181,951.4 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0
1.7 Dito but in Soft and Weatherd rock m3 204.0 15.0 3,060.0 0.0 0.0 - - 0.0 0.0 0.0 0.0 0.0 0.0
1.8 Dito but in hard rock m3 454.0 15.0 6,810.0 3,900.0 1,770,604.5 3,900.01 1,770,604.54 485.3 220,348.6 3,900.0 1,770,604.5 4,385.4 1,990,953.1
1.9 Bulk excavation to reduce level Gray,fine, grained,fresh welded
tuff soil to a depth exceeding 600cms but not exceeding 1,465.18
750cms.
m3 127.0 2,218.9 281,802.8 1,465.2 186,078.4 186,078.42 -265.0 -33,659.7 1,465.2 186,078.4 1,200.1 152,418.7
1.10 Ditto as above but in black decomposed gravel and silt with
boulder materials or brown decomposed rock. -
m3 127.0 2,218.9 281,802.8 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0
1.11 Dito but in Soft and Weatherd rock m3 226.0 15.0 3,390.0 0.0 0.0 - - 0.0 0.0 0.0 0.0 0.0 0.0
1.12 Dito but in hard rock m 3
817.0 15.0 12,255.0 1,523.3 1,244,536.1 1,523.30 1,244,536.10 683.2 558,153.6 1,523.3 1,244,536.1 2,206.5 1,802,689.7
1.13 Bulk excavation to reduce levelGray,fine, grained,fresh welded
tuff soil to a depth exceeding 750cms but not exceeding 1,948.16
900cms.
m3 138.0 2,218.9 306,211.0 1,948.2 268,845.7 268,845.72 -1,948.2 -268,845.7 1,948.2 268,845.7 0.0 0.0
1.14 Ditto as above but in black decomposed gravel and silt with
boulder materials or brown decomposed rock. -
m 3
138.0 2,218.9 306,211.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0
1.15 Dito but in Soft and Weatherd rock m3 239.0 15.0 3,585.0 0.0 0.0 - - 0.0 0.0 0.0 0.0 0.0 0.0
1.16 Dito but in hard rock m3 980.0 15.0 14,700.0 0.0 0.0 - - 0.0 0.0 0.0 0.0 0.0 0.0
1.21 Backfill around foundations and retaining walls with granular
selected material brought from quarry -
m3 231.0 1,646.4 380,323.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.22 Back fill around foundation and retaing wall walls with granular
selected material excavated from site -
m3 150.0 500.0 75,000.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.23 Load and cart away all surplus excavated materials to a suitable pit as may
be found by the contractor and with in the accespable range of the city
adminstration.
m3 76.0 13,599.2 1,033,540.7 23,098.8 1,755,505.7 23,098.76 1,755,505.71 0.0 -2,150.7 -163,455.2 23,098.8 1,755,505.7 20,948.0 1,592,050.6
VARIATION WORKS No. 1 (PODIUM 1) 0.0 0.0 0.0
Bulk excavation to a reduce level in Hard Rock to a depth exceeding 300cms
but not exceeding 450cms. 377.0 2,235.8 842,814.7 2,235.8 842,814.7
1.24 Supply basaltic or equivalent stone for 25cm thick hard core on top of
compacted fill materials and beneath the bottom basement floor slab to be
well rolled, consolidated and blinded with crushed stone aggregates. Lean
concrete shall be measured separately.
m2 172.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
TOTAL CARRIED TO SUMMARY 3,767,116.61 ### ### - 1,159,728.18 42,905.73 ### 41,896.06 7,345,687.67 - -
A2. SUBSTRUCTURE CONCRETE WORK
2.1 Produce and place 5 cm thick lean concrete class C-15, with
minimum PPCcement content of 150 kg/m3. Price shall include
sika or equivalent cement water proofing to be added to all
foundation footings beams slab and column.
a) Under footing pads m2 1,519.00 124.98 189,844.6 1,172.7 1,781,270.5 1,172.66 1,781,270.54 - 4,081.0 6,199,099.76 1,172.7 1,781,270.5 5,253.7 7,980,370.3
b) Under grade beams m2 1,519.00 31.94 48,522.9 0.0 0.0 - - 0.0 - 0.0 0.0 0.0 0.0
c) Under floor slabs m2 1,519.00 2,796.29 4,247,564.5 3,402.7 5,168,701.3 3,402.70 5,168,701.30 - -3,402.7 (5,168,701.30) 3,402.7 5,168,701.3 0.0 0.0
2.2 Reinforced concrete in class C-30 0.0 0.0 0.0 - - - - 0.0 0.0 0.0 0.0
a) in foundation Columns m3 3,468.00 12.96 44,945.3 15.9 55,001.8 15.86 55,001.79 - -3.4 (11,721.84) 15.9 55,001.8 12.5 43,280.0
2.3 Reinforced concrete in class C-30 0.0 0.0 - - - - 0.0 0.0 0.0 0.0
a) In 500mm thick mat slab m2 1,445.00 771.76 1,115,200.0 1,470.3 2,124,525.7 1,470.26 2,124,525.70 - -11.8 (17,094.35) 1,470.3 2,124,525.7 1,458.4 2,107,431.4
b) In mat beams m3 2,890.00 320.05 924,936.4 533.0 1,540,225.5 532.95 1,540,225.50 - -24.2 (70,036.26) 533.0 1,540,225.5 508.7 1,470,189.2
c) footing pads m3 2,760.00 62.49 172,472.4 78.2 215,738.2 78.17 215,738.16 - 23.2 64,145.16 78.2 215,738.2 101.4 279,883.3
d) In Basemnt columns m3 3,468.00 177.41 615,250.9 174.9 606,527.9 174.89 606,527.87 - 89.3 309,571.71 174.9 606,527.9 264.2 916,099.6
e) In lift shaft concrete shear walls m3 3,468.00 39.79 137,983.6 57.9 200,897.6 57.93 200,897.64 - 3.2 11,236.32 57.9 200,897.6 61.2 212,134.0
f) from mat to second basement(shear wall) m3 3,468.00 419.39 1,454,450.9 442.8 1,535,533.9 442.77 1,535,533.89 - 11.1 38,515.95 442.8 1,535,533.9 453.9 1,574,049.8
g) In footing and grade beams m3 2,760.00 14.37 39,674.4 45.7 126,104.4 45.69 126,104.40 - 14.3 39,364.16 45.7 126,104.4 60.0 165,468.6
h) In suspended beams m3 2,890.00 321.24 928,385.3 301.7 871,991.0 301.73 871,991.03 - 7.7 22,372.36 301.7 871,991.0 309.5 894,363.4
i) In 180mm thick suspended slabs m3 520.20 5,291.13 2,752,444.3 4,111.3 2,138,700.9 4,111.31 2,138,700.87 - -2,243.8 (1,167,204.94) 4,111.3 2,138,700.9 1,867.5 971,495.9
j) In staircase steps & landings m3 2,890.00 12.50 36,133.6 15.0 43,251.7 14.97 43,251.74 - -1.6 (4,690.35) 15.0 43,251.7 13.3 38,561.4
h) In180mm thick basement and ground floor slabs m2 520.20 2,500.58 1,300,802.4 0.0 0.0 - - - 2,093.9 1,089,231.29 0.0 0.0 2,093.9 1,089,231.3
k) In 300mm thick Ramp slab m3 867.00 215.09 186,485.2 136.7 118,542.0 136.73 118,542.02 3.8 3,275.82 136.7 118,542.0 140.5 121,817.8
0.0 0.0 - - 0.0 0.0 0.0 0.0
2.4 Provide cut & fix in position sawn zigba wood formwork
- - -
0.0 0.0 - 0.0 0.0 0.0 0.0
a) For 500mm thick Mat slab m2 300.00 61.51 18,453.6 114.7 34,398.0 114.66 34,398.00 - -3.4 (1,032.00) 114.7 34,398.0 111.2 33,366.0
b) For Mat beam m2 300.00 1,066.82 320,047.2 1,705.0 511,502.4 1,705.01 511,502.40 - 77.6 23,277.00 1,705.0 511,502.4 1,782.6 534,779.4
c) For footing pads m2 300.00 113.08 33,924.0 193.8 58,153.8 193.85 58,153.80 - -19.6 (5,871.00) 193.8 58,153.8 174.3 52,282.8
d) In Elevation columns m2 300.00 2,027.52 608,256.0 1,413.1 423,927.6 1,413.09 423,927.55 - 398.6 119,577.00 1,413.1 423,927.6 1,811.7 543,504.6
e) In lift shaft concrete shear walls m2 300.00 330.39 99,118.2 419.2 125,768.4 419.23 125,768.40 - 88.6 26,583.00 419.2 125,768.4 507.8 152,351.4
f) from mat to second basement m2 300.00 3,470.49 1,041,148.4 2,920.4 876,108.1 2,920.36 876,108.12 - 567.6 170,266.80 2,920.4 876,108.1 3,487.9 1,046,374.9
g) For grade beam m2 300.00 115.00 34,499.5 388.0 116,414.6 388.05 116,414.64 - 157.6 47,268.87 388.0 116,414.6 545.6 163,683.5
h) In suspended beams m2 300.00 1,998.83 599,649.1 2,054.2 616,262.2 2,054.21 616,262.16 - 95.0 28,495.98 2,054.2 616,262.2 2,149.2 644,758.1
i) In 180mm thick suspended slabs m2 300.00 5,291.13 1,587,338.1 3,902.4 1,170,734.5 3,902.45 1,170,734.49 - 6.3 1,886.61 3,902.4 1,170,734.5 3,908.7 1,172,621.1
j) In staircase steps & landings m2 300.00 47.73 14,320.3 72.6 21,765.8 72.55 21,765.78 - 13.8 4,136.12 72.6 21,765.8 86.3 25,901.9
h) In150mm thick basement and ground floor slabs m2 300.00 2,500.58 750,174.4 0.0 0.0 - - - 0.0 - 0.0 0.0 0.0 0.0
k) In 300mm thick Ramp slab m2 300.00 215.09 64,527.8 195.3 58,591.4 195.30 58,591.35 - 82.0 24,603.75 195.3 58,591.4 277.3 83,195.1
0.0 0.0 - - - 0.0 0.0 0.0 0.0
0.0 0.0 - - 0.0 0.0 0.0 0.0
Prepared by--------------------------- Checked by--------------------------- Approved by---------------------------
Project:-
Reporting Period:-
mts 23,000.0 917.66 21,106,180.00 906.0 20,838,000.0 906.00 ### - 0.0 (110.72) 906.0 20,838,000.0 906.00 20,837,889.3
TOTAL CARRIED TO SUMMARY 21,106,180.00 ### ### - (110.72) 906.00 ### 906.00 ###
A5. Block work
a)20cm thick HCB wall m2 340.0 971.38 330,269.2 - 971.4 330,269.2 0.0
b) 15 cm thick HCB wall m2 235.0 83.88 19,711.8 - 83.9 19,711.8 0.0
Total carried to summary(A6)…………. 349,981.00 - - 349,981.00 -
A6. WATER PROOFING WORKS
6.3 Supply and apply two coats of masterseal 501 of BASF chemicals m2 223.0 826.89 184,396.47 1,183.0 263,813.5 - - 1,183.0 263,813.5 - -
Total carried to summary(A6)…………. 184,396.47 263,813.46 - - - - - 263,813.46 - - - -
A7. FINISHING WORKS
7.1 Apply two coats of plastering of cement sand mortar (1:3) to receive either
gypsum plaster or ceramic wall tile.
a) To internal wall surface,and columns m2 90.0 0.00 - 0.0 0.0
b) To RC ceiling, exposed beams,stair case soffit and sides of lift shaft walls
m2 90.0 (0.01) - - 0.0 0.0 -
7.2 Apply two coats of plastering in cement sand mortar mix ratio 1:3 to all the
basement shear walls after application of Masterflex 501 waterproofing
material.
m2 90.0 - - 0.0 0.0
Total carried to summary(A7)…………. - - - - - - -
BLOCK A
B-SUPER STRUCTURE
B1. CONCRETE WORK
1.01 Produce and place reinforced concrete class C-30, with minimum cement
content of 400kg/m3, of concrete filled in to form work and vibrated
around rod reinforcement steel. (Formwork and reinforcement measured
separately). Price shall include admixture plasticizer (RHEOBUILD LD 80) or
a) In Elevation columns m3 3,700.00 963.07 3,563,359.00 414.39 1,533,254.3 414.39 1,533,254.30 123.12 455,544.00 225.8 835,563.60 537.5 1,988,798.3 640.2 2,368,817.9
b) In lift shaft concrete and shear walls m3 3,700.00 1,080.16 3,996,592.00 490.47 1,814,755.3 490.47 1,814,755.30 136.47 504,939.00 218.0 806,737.90 626.9 2,319,694.3 708.5 2,621,493.2
c) In staircase steps and landings m3 3,160.00 102.30 323,268.00 48.17 152,201.4 48.17 152,201.40 16.08 50,812.80 36.0 113,795.05 64.2 203,014.2 84.2 265,996.5
d) In 200mm thick flat slabs m2 599.00 10,796.19 6,466,917.81 5,633.76 3,374,619.5 5,633.76 3,374,619.47 2,182.20 1,307,137.80 2,793.5 1,673,290.93 7,816.0 4,681,757.3 8,427.2 5,047,910.4
Roof slab m3 599.00 - - 0.0 - - - 0.0 - 0.0 0.0 0.0 0.0
Beams m3 2,890.00 - 25.53 73,769.9 25.53 73,769.90 - -25.5 (73,769.90) 25.5 73,769.9 0.0 0.0
1.0 Provide, cut and fix yellow panel including minimum 20mm thick marine
plywood wooden formwork with recommended spacers, braces and screw- -
adjustable steels props that should be strong enough to resist the pressure - 0.0 - - - 0.0 0.0 0.0 0.0
of fresh concrete, tightly placed to prevent leakage of cement paste and - 0.0 - - - - 0.0 0.0 0.0 0.0
a) In Elevation columns m 2
300.00 5,702.40 1,710,720.00 2,787.78 836,335.0 2,787.78 836,335.02 820.80 246,240.00 1,480.4 444,114.00 3,608.6 1,082,575.0 4,268.2 1,280,449.0
b) In lift shaft concrete and shear walls m2 300.00 7,862.31 2,358,693.00 3,598.93 1,079,679.1 3,598.93 1,079,679.10 1,057.14 317,142.00 1,896.7 568,995.30 4,656.1 1,396,821.1 5,495.6 1,648,674.4
c) In staircase steps and landings m2 300.00 429.61 128,883.00 280.62 84,185.3 280.62 84,185.30 103.02 30,906.00 257.1 77,119.30 383.6 115,091.3 537.7 161,304.6
d) In 200mm thick flat slabs m2 300.00 10,796.19 3,238,857.00 5,133.08 1,539,924.8 5,133.08 1,539,924.80 1,666.14 499,842.00 3,640.9 1,092,258.60 6,799.2 2,039,766.8 8,773.9 2,632,183.4
Roof slab m2 300.00 - - 0.0 - - - 0.0 - 0.0 0.0 0.0 0.0
Beams m2 300.00 - 192.04 57,610.8 192.04 57,610.80 - -192.0 (57,610.80) 192.0 57,610.8 0.0 0.0
Alternative I - 0.0 - - - - 0.0 0.0 0.0 0.0
(Depends on the prioritization of the client) - 0.0 - - - - 0.0 0.0 0.0 0.0
1.0 Provide and place mild steel reinforcement bars according to details
specified in the structural drawings. Price includes cutting, bending, placing -
- 0.0 - - - 0.0 0.0 0.0 0.0
in position and tying wire. Bars should be free from such coatings such as oil
and mortar before placement. - 0.0 - - - - 0.0 0.0 0.0 0.0
a) diam 8 mm deformed bar kg 37.00 14,787.66 547,143.42 882.76 32,662.0 882.76 32,661.95 343.65 12,715.05 919.3 34,014.09 1,226.4 45,377.0 1,802.1 66,676.0
b) diam 10 mm deformed bar kg 37.00 99,548.95 3,683,311.15 65,573.73 2,426,228.1 65,573.73 2,426,228.07 ### 1,123,145.73 104,989.4 3,884,609.38 95,929.0 3,549,373.8 170,563.2 6,310,837.4
c) diam 12 mm deformed bar kg 37.00 103,617.43 3,833,844.91 68,966.76 2,551,770.0 68,966.76 2,551,769.95 ### 815,551.78 56,780.2 2,100,867.34 91,008.7 3,367,321.7 125,747.0 4,652,637.3
d) diam 14 mm deformed bar kg 37.00 810,872.69 30,002,289.53 43,474.91 1,608,571.6 43,474.91 1,608,571.59 ### 464,408.83 27,485.2 1,016,952.67 56,026.5 2,072,980.4 70,960.1 2,625,524.3
e) diam 16 mm deformed bar (UP only) kg 37.00 - - 9,094.32 336,489.8 9,094.32 336,489.81 ### 615,303.71 27,645.3 1,022,875.53 25,724.1 951,793.5 36,739.6 1,359,365.3
f) diam 20 mm deformed bar (UP only) kg 37.00 - - 46,078.72 1,704,912.8 46,078.72 1,704,912.76 4,208.95 155,731.15 15,542.7 575,078.84 50,287.7 1,860,643.9 61,621.4 2,279,991.6
g) diam 24 mm deformed bar kg 37.00 80,379.36 2,974,036.32 175,309.65 6,486,456.9 ### 6,486,456.95 ### 822,272.83 36,134.1 1,336,961.44 197,533.2 7,308,729.8 211,443.7 7,823,418.4
Total carried to summary(B1)…………. 62,827,915.14 ### ### 7,421,692.68 15,451,853.25 33,115,119.14 41,145,279.71 - -
B2. BLOCK WORK
Walls shall be constructed from class 'B' hollow concrete blocks (HCB). The
blocks shall be selected for their consistency in dimensions, shapes, angles
and strength. They should be free from cracks or any other defects and the
surface characteristic of the blocks shall be in such a way that good key for
plaster is obtained on both sides.
2.0 20cm thick HCB wall, embedded in cement-sand mortar of 1:3 mix ratio.
Both sides shall be left for plastering. 220,054.80
m2 340.0 1,215.55 413,286.2 647.22 374.2 127,231.40 1,862.8 633,341.0 374.2 127,231.4
2.0 Ditto but 15cm thick HCB partition walls for toilets. m2 235.0 750.42 176,348.7 740.88 174,106.80 452.2 106,264.65 1,491.3 350,455.5 452.2 106,264.7
2.0 Ditto but 10cm thick HCB partition walls for toilets. m2 168.0 27.23 4,575.0 31.20 5,241.60 25.5 4,284.00 58.4 9,816.6 25.5 4,284.0
Total carried to summary(B2)…………. 594,209.90 399,403.20 237,780.05 993,613.10 237,780.05
B5 FINISHING WORKS
5.1 Apply two coats of plastering of cement sand mortar (1:3) to receive either
gypsum plaster or ceramic wall tile.
a) To internal wall surface, exposed beams and columns m2 90.0 0.00 - 0.0 0.0
b) To RC ceiling, stair case soffit and sides of lift shaft walls m2 90.0 (0.01) - 0.0 0.0
c) To receive ceramic wall tiles m2 90.0 0.00 - 0.0 0.0
5.2 Apply 78mm thick cement/sand screed flooring . The application of the
screed shall be levelled and finished with a fine texture screeding while the
concrete is fresh and it is preferable to hold the proper application of Floor
Finish with out any additional levelling. -
1.01 Produce and place reinforced concrete class C-30, with minimum cement
content of 400kg/m3, of concrete filled in to form work and vibrated
around rod reinforcement steel. (Formwork and reinforcement measured
separately). Price shall include admixture plasticizer (RHEOBUILD LD 80) or
Prepared by--------------------------- Checked by--------------------------- Approved by---------------------------
Project:-
Reporting Period:-
a) In Elevation columns m3 3,700.00 963.07 3,563,359.00 401.35 1,484,995.0 401.35 1,484,995.00 123.12 455,544.00 156.8 580,152.60 524.5 1,940,539.0 558.1 2,065,147.6
b) In lift shaft concrete and shear walls m3 3,700.00 1,080.16 3,996,592.00 432.80 1,601,343.5 432.80 1,601,343.50 136.47 504,939.00 184.7 683,556.50 569.3 2,106,282.5 617.5 2,284,900.0
c) In staircase steps and landings m3 3,160.00 102.30 323,268.00 45.85 144,886.0 45.85 144,886.00 16.08 50,812.80 27.6 87,252.62 61.9 195,698.8 73.5 232,138.6
d) In 200mm thick flat slabs m2 599.00 10,796.19 6,466,917.81 4,947.29 2,963,426.9 4,947.29 2,963,426.88 1,636.65 980,353.35 2,353.7 1,409,873.49 6,583.9 3,943,780.2 7,301.0 4,373,300.4
Beams m3 2,890.00 26.35 76,147.6 26.35 76,147.60 - -26.3 (76,147.60) 26.3 76,147.6 0.0 0.0
1.0 Provide, cut and fix yellow panel including minimum 20mm thick marine
plywood wooden formwork with recommended spacers, braces and screw-
adjustable steels props that should be strong enough to resist the pressure
of fresh concrete, tightly placed to prevent leakage of cement paste and -
smooth enough to produce fine concrete surface finishes.
-
Unit price shall include: -
- filling and spreading of coarse gravel, fine gravel, sand and selected
backfill to an average depth of 6 meters and average width of 1.2 meter.
-
- covering of geosynthetics around the gravel pack (200g) -
- TESTIDO or equivalent membrene water proofing, 4mm thick coating in
accordance with the drawing.
-
- Up right position of single brick wall to protect the membrane water
proofing, including all civil assistance works and screed work in accordance
with the detail drawing.
-
- well compacted clay soil on the top -
- All other necessary connecting pieces and civil assistance works.
-
Dia. 160 mm ml 4,647.0 147.00 683,109.00 152.4 708,083.3 152.37 708,083.33 - -5.7 (26,394.96) 152.4 708,083.3 146.69 681,688.4
- 0.0 0.0 - - - - 0.0 0.0 - 0.0
10.6.2 Ditto to item number 10.6.1 above but for internal drainage under slab as
shown on detail drawing. 0.0 0.0 0.0 0.0 0.0
- - - - - -
Dia. 160 mm ml 4,830.0 102.00 492,660.00 94.0 453,989.8 93.99 453,989.77 - 13.8 66,847.20 94.0 453,989.8 107.83 520,837.0
- 0.0 0.0 - - - - 0.0 0.0 - 0.0
10.6.3 Supply and lay rodding or cleaning eye of uPVC, PN-4 on the sub soil
drainage system as where shown on the drawings. Provide plug or screw
tube plastic cap on top to external ground level.
- 0.0 0.0 - - - - 0.0 0.0 - 0.0
Dia. 160 mm No 1,948.0 8.00 15,584.00 9.6 18,700.8 9.60 18,700.80 - 0.4 779.20 9.6 18,700.8 10.00 19,480.0
- 0.0 - - - - -
TOTAL CARRIED TO SUMMARY ...................................................
1,191,353.00 1,180,773.90 1,180,773.90 - 41,231.44 1,180,773.90 1,222,005.34
10.3 WASTE, VENT AND RAIN WATER PIPES AND -
Prepared by--------------------------- Checked by--------------------------- Approved by---------------------------
Project:-
Reporting Period:-
ml 170.0 41.99 7,139.0 41.99 7,139.04 10.7 1,822.74 42.0 7,139.0 52.72 8,961.8
TOTAL CARRIED TO SUMMARY 7,000.00 424,500.00 - 27,891.84 27,891.84 - 1,822.74 374.20 27,891.84 29,714.58 - -
PODIUM-2
A1. EXCAVATION & EARTH WORK
1.1 Bulk excavation from stripped level in Black,soft,high plastic silty clay soil to
an average depth of 150cms and bring to a levelled surface. 77.00 2,218.92 170,856.84 3,689.85 284,118.39 - (355.72)
m3 3,689.8 284,118.4 (27,390.72) 3,689.8 284,118.4 3,334.13 256,727.7
1.2 Bulk excavation to reduce level in Gray, Stiff, high plastic silty Clay to a
depth exceeding 150cms but not exceeding 300cms. 93.00 2,218.92 206,359.56 3,144.67 292,454.52 - (306.51)
m3 3,144.7 292,454.5 (28,505.28) 3,144.7 292,454.5 2,838.16 263,949.2
1.3 Bulk excavation to reduce level in Gray, Stiff, high plastic silty Clay to a
depth exceeding 300cms but not exceeding 450cms. 102.00 2,218.92 226,329.84 2,243.92 228,880.25 - (1,627.31)
m3 2,243.9 228,880.3 (165,985.55) 2,243.9 228,880.3 616.61 62,894.7
1.3 Dito but in hard rock(pp for report) m3 295.00 347.8 102,589.2 347.76 102,589.20 (347.76) (102,589.20) 347.8 102,589.2 - 0.0
1.4 Bulk excavation to reduce level in Gray, Stiff, high plastic silty Clay soil to a
depth exceeding 450cms but not exceeding 600cms. 123.00 739.64 90,975.72 4,029.03 495,570.14 - (2,608.80)
m3 4,029.0 495,570.1 (320,882.04) 4,029.0 495,570.1 1,420.23 174,688.1
1.5 Bulk excavation to reduce level in Gray,fine, grained,fresh welded tuff soil
to a depth exceeding 450cms but not exceeding 600cms. 123.00 1,479.28 181,951.44 - - -
m3 0.0 0.0 - 0.0 0.0 - 0.0
1.6 Ditto as above but in black decomposed gravel and silt with boulder
materials 123.00 1,479.28 181,951.44 - - -
m3 0.0 0.0 - 0.0 0.0 - 0.0
1.7 Dito but in Soft and Weatherd rock m3 204.00 15.00 3,060.00 0.0 0.0 - - - - 0.0 0.0 - 0.0
1.8 Dito but in hard rock m3 454.00 15.00 6,810.00 2,215.4 1,005,791.6 2,215.40 1,005,791.60 - (466.17) (211,643.12) 2,215.4 1,005,791.6 1,749.23 794,148.5
1.9 Bulk excavation to reduce level Gray,fine, grained,fresh welded
tuff soil to a depth exceeding 600cms but not exceeding 127.00 2,218.92 281,802.84 24.00 3,048.00 - 187.60
750cms.
m3 24.0 3,048.0 23,825.36 24.0 3,048.0 211.60 26,873.4
1.10 Ditto as above but in black decomposed gravel and silt with
boulder materials or brown decomposed rock. 127.00 2,218.92 281,802.84 - - - -
m3 0.0 0.0 - 0.0 0.0 - 0.0
1.11 Dito but in Soft and Weatherd rock m3 226.00 15.00 3,390.00 0.0 0.0 - - - - - 0.0 0.0 - 0.0
1.12 Dito but in hard rock m 3 817.00 15.00 12,255.00 415.6 339,508.4 415.55 339,508.39 - (415.55) (339,508.39) 415.6 339,508.4 - 0.0
1.13 Bulk excavation to reduce levelGray,fine, grained,fresh welded
tuff soil to a depth exceeding 750cms but not exceeding 138.00 2,218.92 306,210.96 24.00 3,312.00 - (24.00)
900cms.
m3 24.0 3,312.0 (3,312.00) 24.0 3,312.0 - 0.0
1.14 Ditto as above but in black decomposed gravel and silt with
boulder materials or brown decomposed rock. 138.00 2,218.92 306,210.96 - - - - -
m 3
0.0 0.0 0.0 0.0 - 0.0
1.15 Dito but in Soft and Weatherd rock m3 239.00 15.00 3,585.00 0.0 0.0 - - - - - 0.0 0.0 - 0.0
1.16 Dito but in hard rock m3 980.00 15.00 14,700.00 0.0 0.0 - - - - - 0.0 0.0 - 0.0
1.21 Backfill around foundations and retaining walls with granular
selected material brought from quarry 231.00 1,646.42 380,323.45 - - -
m3 0.0 0.0 0.0 0.0 - 0.0
1.22 Back fill around foundation and retaing wall walls with granular
selected material excavated from site 150.00 500.00 75,000.00 - - -
m3 0.0 0.0 0.0 0.0 - 0.0
1.23 Load and cart away all surplus excavated materials to a suitable pit as may
be found by the contractor and with in the accespable range of the city - (3,951.49)
adminstration.
m3 76.00 13,599.22 1,033,540.72 17,335.0 1,317,457.8 17,334.93 1,317,454.38 (300,313.32) 17,335.0 1,317,457.8 13,383.43 1,017,141.1
VARIATION WORKS No. 1 (PODIUM 2) #DIV/0! - #DIV/0! 0.0
Bulk excavation to a reduce level in Hard Rock to a depth exceeding 150cms
but not exceeding 300cms. 495.96
329.51 163,425.35 495.96 163,425.3
Bulk excavation to a reduce level in Hard Rock to a depth exceeding 300cms
but not exceeding 450cms. 2,717.52
376.96 1,024,394.69 2,717.52 1,024,394.7
1.24 Supply basaltic or equivalent stone for 25cm thick hard core on top of
compacted fill materials and beneath the bottom basement floor slab to be
well rolled, consolidated and blinded with crushed stone aggregates. Lean m2 - -
concrete shall be measured separately.
172.00 0.0 0.0 0.0 - 0.0
TOTAL CARRIED TO SUMMARY 3,767,116.61 ### ### - (288,484.22) 33,469.16 ### 23,553.39 3,784,242.65 -
A2. SUBSTRUCTURE CONCRETE WORK
2.1 Produce and place 5 cm thick lean concrete class C-15, with
minimum PPCcement content of 150 kg/m3. Price shall include
sika or equivalent cement water proofing to be added to all
a) Under footing
foundation padsbeams slab and column.
footings m2 1,519.00 124.98 189,847.66 932.7 1,416,763.7 932.70 1,416,763.71 - 3,308.89 5,026,203.91 932.7 1,416,763.7 4,241.59 6,442,967.6
b) Under grade beams m2 1,519.00 31.94 48,522.94 0.0 0.0 - - - - - 0.0 0.0 - 0.0
c) Under floor slabs m 2
1,519.00 2,796.29 4,247,564.52 3,398.8 5,162,807.6 3,398.82 5,162,807.58 - (3,398.82) (5,162,807.58) 3,398.8 5,162,807.6 - 0.0
2.2 Reinforced concrete in class C-30 - 0.0 0.0 - - - - 0.0 0.0 - 0.0
Prepared by--------------------------- Checked by--------------------------- Approved by---------------------------
Project:-
Reporting Period:-
BLOCK C
B-SUPER STRUCTURE
B1. CONCRETE WORK
M2 90.00 3,047.99 -
b) To RC ceiling, stair case soffit and sides of lift shaft walls 274,319.5 3,048.0 274,319.5
c) To receive ceramic wall tiles M2 90.00 1,300.21 117,019.1 - 1,300.2 117,019.1
d) To roof Parapet M2 90.00 - 0.0 - 0.0 0.0
5.2
Apply two coats of plastering of cement sand mortar (1:3) to M2 90.00 -
external wall surface, exposed beams and columns 0.0 0.0 0.0
Total carried to summary(B5)…………. 879,722.52 - - - 879,722.52 -
BLOCK D
B-SUPER STRUCTURE
B1. CONCRETE WORK
5.1
Apply two coats of plastering of cement /sand mortar (1:3) to
receive either gypsum plaster or ceramic wall tile.
a) To internal wall surface, exposed beams and columns M2 90.00 0.00 - 0.0 0.0
M2 90.00 0.00 -
b) To RC ceiling, stair case soffit and sides of lift shaft walls 0.0 0.0
c) To receive ceramic wall tiles M2 90.00 (0.00) - 0.0 0.0
Total carried to summary(B5)…………. - - - - -
SANITARY INSTALATION
10.4 WATER PROFFING WORK
SPECIAL CHARACTERSTICS
10.6.1 Supply and lay purpose made uPVC, PN-6 Factory slotted plastic
pipe to BS 1194:1969 for sub soil drainage system around the
building according to where shown on the basement floor plan
and
Unitdetail
price drawing .
shall include:
- filling and spreading of coarse gravel, fine gravel, sand and
selected backfill to an average depth of 6 meters and average
width of 1.2 meter.
Ls ### 2.00 700,000.00 1.8 628,269.6 1.80 628,269.60 0.20 71,730.40 1.8 628,269.6 2.00 700,000.0
Total carried to summary(10)…………. 1,891,353.00 ### 1,720,029.4 0.0 43,773.1 1,720,029.4 1,763,802.5
Checked by...........................
Prepared by.................... Approved by..........................
21
Document No:
}¡Kw`H” ›Uv ¢”eƒ^¡i” .¾}.¾Ó.T.
Tekleberhan Ambaye Construction PLC TQF/F/021
Title: Project Profit & Loss statement Form Kind of Doc: Issue No: Page No:
Project :Federal Suprem Court Project Form A2 1of 1
Reporting Period:- Issue dates Des, 2007
%
of Revenue
%Revenue
Previous Current Month Cumulative to Comm.
1. Revenue 200,673,981.12 39,388,083.13 260,517,963.12
1.1 Work Executed /Actual as per Engineering
Report/
1.2 Income from Machinery Rent & Others -
1.3 Total Revenue 200,673,981.12 39,388,083.13 260,517,963.12
2. Costs & Expenses
2.1 Direct Cost
Net Material expense 90,191,722.33 18,771,465.86 47.7% 108,963,188.19 41.83%
2.1.2 Man Power Cost (Gross) - -
Technical Staff 53,812.21 53,812.21
Skilled 2,588,145.15 1,111,800.28 3,699,945.43
Unskilled 4,164,253.60 2,019,728.84 6,183,982.44
Piece rate -
Total ( Direct Labour & material cost ) 96,997,933.29 21,902,994.98 55.6% 118,900,928.27 45.64%
Sub-contract Expense/Site 9,380,330.77 2,938,198.81 12,318,529.58 4.73%
Sub-contract Expense/head office - -
2.1.3 Machinery Cost - -
Machinery Rent (Owned) 7,513,638.98 1,128,974.33 8,642,613.31
Machinery Rent 4,532,814.00 331,300.00 4,864,114.00
2.1.4 Fuel & Lubricants 2,155,682.36 216,639.15 2,372,321.51
2.1.5 Transport Expense 668,260.00 486,400.00 1,154,660.00
Total Direct cost 121,248,659.39 27,004,507.27 68.6% 148,253,166.67 56.91%
2.2 Over head -
Technical & Administration staff 3,846,709.05 733,220.97 4,579,930.02
Termination Payment 40,692.50 40,692.50
Other expenses (Material test, Medical, Loading &
Unloading) 933,337.18 69,489.19 1,002,826.37
Maintenance expense 11,426.42 3,894.92 15,321.34
Stationary 122,363.13 17,527.14 139,890.27
Hand Tools 47,787.07 11,465.23 59,252.30
Spare Parts 149,773.83 43,188.02 192,961.85
Perdiem & Travel 13,422.00 480.00 13,902.00
Utilities (Phone, Electricity & Water) 21,350.04 4,980.14 26,330.18
Office /Store/camp rent 652,165.66 110,357.00 762,522.66
Over Time Expense 344,077.42 11,251.92 355,329.34
Other Overhead 267,028.27 100,535.10 367,563.37
Vehicles Rent/light 1,286,050.00 185,000.00 1,471,050.00
2.1.4 Fuel & Lubricants 191,968.48 61,555.63 253,524.11
Medical Expense 28,913.23 9,856.18 38,769.41
Indirect Material 865,576.98 865,576.98
Pension Expense 271,864.33 37,924.92 309,789.25
Material Test 51,744.66 13,650.00 65,394.66
HARD SHIP ALLO. EXPENSE - -
Advartising Expense 2,114.10 2,114.10
Entertainment (Food) 1,449,626.76 380,189.36 1,829,816.12
Miscellaneous/ Entertain,Exp of Capital Nature 726,055.54 215,268.35 941,323.89
Total over head 11,324,046.65 2,009,834.07 5.1% 13,333,880.72 5.12%
Total Project (Direct cost + Over head) 132,572,706.04 29,014,341.34 161,587,047.39
Head Office over head costs -
Insurance -
Financial charges -
Total Site expense covered by Head office - -
4. Total Project & Head office Cost 132,572,706.04 29,014,341.34 73.7% 161,587,047.39 62%
5. Gross earning /Gross profit or Loss (1.4 - 4) 68,101,275.07 10,373,741.78 26.3% 98,930,915.73 38%
Reporting Period:-
a&c)for mat slab &footing pads m2 53 158.86 8419.58 (19.09) -1011.77 139.77 7407.81
m2
5 1403.19 7015.97 501.26 2506.3 1904.45 9522.27
h) for suspended beam (1st basment) m2 56 1129.93 63275.97 124.18 6954.08 1254.11 70230.048
j) for stair case steps&ladings m2 58 57.29 3323.05 (14.60) -846.8 42.69 2476.252
1.0 l) for ramp slab m2 55 76.10 4185.78 133.89 7363.95 209.99 11549.725
b)in lift shaft concrete and shear walls m2 60 3206.84 192410.40 2,281.54 136892.4 5488.38 329302.8
c)in staircase steps and landings m2 58 300.35 17420.30 235.80 13676.4 536.15 31096.7
d)in 200mm thick flat slabs m2 50 5512.41 275620.50 2,818.28 140914 8330.69 416534.5
Rozda Construction plc(formwork) Beam m2 56 120.24 6733.44 260.76 14602.56 381.00 21336
b)in lift shaft concrete and shear walls m2 60 3083.04 184982.40 1,095.00 65700 4178.04 250682.4
c)in staircase steps and landings m2 58 317.92 18439.36 114.82 6659.56 432.74 25098.92
m2
50 5269.07 263453.50 2,235.14 111757 7504.21 375210.5
d)in 200mm thick flat slabs m2 5 4740.09 23700.45 1,957.75 9788.75 6697.84 33489.2
Asmelash&Alemnesh Construction
Partnership(formwork) Beam m2 56 191.30 10712.80 101.60 5689.6 292.90 16402.4
a&c)for mat slab &footing pads m2 53 208.35 11042.55 (68.61) -3636.33 139.74 7406.22
m2
5 212.28 1061.40 3,051.24 15256.2 3263.52 16317.6
m2
5 1255.57 6277.84 548.96 2744.8 1804.53 9022.635
h) for suspended beam (1st basment) m2 56 872.92 48883.24 108.74 6089.44 981.66 54972.68
i) for suspended slab(1st basment) m2 55 2102.58 115641.98 (424.21) -23331.55 1678.37 92310.4325
m2 5 24.54 122.70 0 24.54 122.7
j) for stair case steps&ladings m2 58 134.68 7811.56 (126.39) -7330.62 8.29 480.936000000001
3.0 10.6.4) cach pit m2 65 38.60 2509.00 0 38.60 2509
Super structure 0.00 0.00 0 0.00 0
m2 5 2481.75 12408.75 1,044.00 5220 3525.75 17628.75
a)in elevation columns m2 56 2448.50 137116.00 1,655.50 92708 4104.00 229824
m2 5 1777.25 8886.25 1,577.29 7886.45 3354.54 16772.7
b)in lift shaft concrete and shear walls m2 60 2700.83 162049.80 2,474.29 148457.4 5175.12 310507.2
m2 24.50 0.00 34.34 0 58.84 0
c)in staircase steps and landings m2 58 335.44 19455.52 179.85 10431.3 515.29 29886.82
m2 5 1983.97 9919.85 560.16 2800.8 2544.13 12720.65
d)in 200mm thick flat slabs m2 50 5377.15 268857.50 2,944.55 147227.5 8321.70 416085
Prepared by------------------------ Checked by---------------------------- Approved by----------------------------
Reporting Period:-
Actual
Quantity of work Standard Consumption Actual Utilization
Item No Work Type Unit executed Consumption (Quintals /unit) Consumption Efficiency Remark
A. Sub Structure Cement (qtl.) Cement (qtl.)
1 Lean Concrete m 3
1.83 1.50 2.182 4.00 69%
2 Concrete work for 2nd basm. floor slab (20 cm) m3 11.57 3.60 2.938 34.00 123%
3 Concrete work for 1st basm. floor slab (28 cm) m3 0.52 4.00 1.941 1.00 206%
OPC
4 Concrete work for shear wall m3 1.35 4.00 4.062 5.50 98%
5 Lintels concrete work m3 Err:509 4.00 Err:509 4.25 Err:509
B. SUPPER-STRUCTURE
1.B.2. BLOCK WORK
1 Block work (Solid) m2 Err:509 0.038 Err:509 2.25 Err:509
1.B.7 Finishing
1 Plastering work m2 172.55 0.073 0.106 18.25 69%
2 Granite floor tile m2 Err:509 0.09 Err:509 1.00 Err:509
3 Marble threshold ml Err:509 0.05 Err:509 1.00 Err:509
4 Porcelain floor tile m2 Err:509 0.036 Err:509 195.50 Err:509
5 Ceramic wall cladding m2 Err:509 0.036 Err:509 3.50 Err:509
6 Terrazzo floor tile m2 Err:509 0.220 Err:509 23.50 Err:509
Remark:-Þ1) 9.75Qtl of ppc for Xypex rework, 9.5Qtl of ppc for Correction work of slab soffit in basements & 8.5Qtl of ppc for plastering rework (sanitary pipe cover & Edge work)
is used for this month
2) The standared of cement for porcelain floor tile work is 0.036qtl/m2 which is very small & not practical. On site Cement consumption is 0.149 qtl/m2
Prepared by : Bethel Tsegaye Checked by : Etsegenet Dessalegn Approved by : Birru Mahteme
(Office Engineer) (S.Office Engineer) (Project manager)
Quantity of Actual
Item work Standard Consumption per Actual Utilization
No Work Type Unit executed Consumption unit Consumption Efficiency Remark
A. Sub Structure Sand (m3) Sand (m3)
1 Lean Concrete m3 1.83 0.48 0.698 1.28 69%
2 Concrete work for 2nd basm. Floor m3 11.57 0.52 0.470 5.44 111%
3 Concrete work for 1st basm. floor m3 0.52 0.51 0.311 0.16 164%
4 Concrete work for shear wall m3 1.35 0.51 0.650 0.88 78%
5 Lintels concrete work m3 Err:509 0.51 Err:509 0.68 Err:509
B. SUPER-STRUCTURE
1.B.2. BLOCK WORK
1 Block work (Solid) m2 Err:509 0.01 Err:509 0.72 Err:509
1.B.7 Finishing
1 Plastering work m2 172.55 0.018 0.034 5.84 53%
2 Granite floor tile m2 Err:509 0.02 Err:509 0.32 Err:509
3 Marble threshold ml Err:509 0.01 Err:509 0.32 Err:509
4 Porcelain floor tile m2 Err:509 0.008 Err:509 62.56 Err:509
5 Terrazzo floor tile m2 Err:509 0.05 Err:509 7.52 Err:509
Contract Contract Meskerem- 2007 E.C 1st ( 1-8) 2nd ( 9-16) 3rd ( 17-23) 4th ( 24 -30)
No. Description Unit Qty Rate Amount Qty Amount Qty Amount Qty Amount Qty Amount Qty Amount
B. SUPER STRUCTURE
4. Steel Structure
4.2 Spiral stair 0.00 0.00 0.00
4.2.1 Vertical mai post diam 120 L=4.08m 78.00 17.50 1,365.00 0.00 0.00 0.00 17.50 1,365.00
4.2.2 Plates 300x300x5mm kg 35.00 135.00 1.00 135.00 0.00 0.00 0.00 1.00 135.00
4.2.3 Anchor bolts diam 16mm, L=400mm kg 2.00 173.00 2.00 346.00 0.00 0.00 0.00 2.00 346.00
4.2.4 Inclined support for risers RHS 25x25x1.5mm 78.00 13.00 1,014.00 0.00 0.00 0.00 13.00 1,014.00
4.2.5 Horizontal suppor for risers RHS 25x25x1.5mm 78.00 28.00 2,184.00 0.00 0.00 0.00 28.00 2,184.00
4.2.6 Chequered safety plate threads 2mm thick 3,500.00 2.00 7,000.00 0.00 0.00 0.00 2.00 7,000.00
4.2.7 Square balusters RHS 25x25x1.5mm 78.00 13.50 1,053.00 0.00 0.00 0.00 13.50 1,053.00
TOTAL CARRIED TO SUMMARY 1,439,731.00 13,097.00 0.00 0.00 0.00 13,097.00
2 Metal Work
2.1.1 Doors
D1 size 700x2200mm No 8,411.63 1.60 13,458.61 1.60 13,458.61
D2 size 1000x2200mm No 12,016.62 1.80 21,629.92 1.80 21,629.92
D3 size 1600x2200mm No 19,226.59 0.40 7,690.64 0.40 7,690.64
D4 size 600x2200mm No 7,209.97 21.60 155,735.35 21.60 155,735.35
FD1 size 800x2200mm No 9,613.30 5.60 53,834.48 5.60 53,834.48
2.1.2 Window doors 0.00
WD6 size 7800x3100mm No 127,634.13 3.40 433,956.04 1.70 216,978.02 1.70 216,978.02
WD10 Size 5550x3100mm No 90,816.59 0.40 36,326.64 0.20 18,163.32 0.20 18,163.32
2.1.3 Windows 0.00 0.00
W1 size 1200x1000mm No 6,426.54 2.00 12,853.08 0.00 2.00 12,853.08
W2 size 600x800mm No 2,570.62 12.00 30,847.44 0.00 12.00 30,847.44
W11 size 5800x3100mm No 100,490.22 1.00 100,490.22 0.00 1.00 100,490.22
W12 size 5550x3100mm No 92,140.52 3.00 276,421.56 2.25 207,316.17 0.75 69,105.39
W13 size 8750x3100mm No 145,266.58 4.00 581,066.32 2.00 290,533.16 2.00 290,533.16
W14 size 3430x3100mm No 56,944.50 2.00 113,889.00 1.00 56,944.50 1.00 56,944.50
W16 size 1200x1900mm No 12,210.43 24.00 293,050.32 12.00 146,525.16 12.00 146,525.16
W17 size 2840x800mm No 12,167.58 4.00 48,670.32 0.00 4.00 48,670.32
W18 size 7000x800mm No 29,990.52 7.47 223,929.22 3.73 111,964.61 3.73 111,964.61
W19 size 11700x800mm No 50,127.01 2.00 100,254.02 2.00 100,254.02 0.00
W19' size 5650x800mm No 24,206.63 1.00 24,206.63 1.00 24,206.63 0.00
CW12 size 2000x2020mm No 21,636.02 6.00 129,816.12 6.00 129,816.12 0.00
2.3.1 Dia 50mm ,2mm thick Aluminium hand rail shown on archite
ml 9,501.30 188.93 1,795,087.92 94.47 897,543.96 94.47 897,543.96 0.00
Contract Contract Meskerem- 2007 E.C 1st ( 1-8) 2nd ( 9-16) 3rd ( 17-23) 4th ( 24 -30)
Transparent roofing in 6mm thick polycarbonate tinted
No. Description
glass over car parking entrance on aluminium frame Unit
2.3.2 support 0.00 0.00 0.00
a. 6mm thick polycarbonate tinted glass m2 9,182.70 120.00 1,101,924.00 60.00 550,962.00 60.00 550,962.00 0.00
b. RHS, size:70x50x3mm Kg 94.50 1,090.00 103,005.00 1,090.00 103,005.00 0.00 0.00
c. RHS, size:70x50x3mm Kg 94.50 338.00 31,941.00 338.00 31,941.00 0.00 0.00
d. Steel plate size: 300x300x6mm Pcs 654.75 34.00 22,261.50 34.00 22,261.50 0.00 0.00
e. Anchor bolt,dia.18mm Pcs 101.25 68.00 6,885.00 68.00 6,885.00 0.00 0.00
Dia. 50mm aluminum hand rail fixed to shear wall for
2.3.4 staircase rail as per the detail drawing. ml 4,452.30 128.59 572,521.26 42.86 190,840.42 42.86 190,840.42 42.86 190,840.42
Clad silver aluminum composite panel to aluminum
2.3.5 pergola frame m2 3,570.75 162.28 579,468.99 54.09 193,156.33 54.09 193,156.33 54.09 193,156.33
Supply and fix metal Guard rail made profiles, all acording
to the drawing. Price shall include oe coat of anti rust and
two coats of synthetic enamel paint and all other
2.4.4 necessary accessories. ml 3,156.30 17.50 55,235.25 17.50 55,235.25 0.00 0.00
Type D9 size; 4000 * 2440mm No 30,584.25 1.00 30,584.25 0.00 1.00 30,584.25
TOTAL CARRIED TO SUMMARY 0.00 6,957,040.10 55,235.25 1,996,595.21 3,387,553.42 1,517,656.22
8. Finishing
Tectopanel tangent or equiv. perforated acoustic gypsum
8.05 Supply 300x600x8mm glazed ceramic wall tile to toilet and
panels m2 633.00 1,957.50 1,239,097.50 134.37 263,033.15 0.00 - - 134.37 263,033.15
kitchen with cement mortar backing and joints grouted in
400x400x8mm
white thick imported
cement. Colour typeofapproved
and pattern tile shall bequality non
approved
3.1 slippery ceramic tile flooring stuck down with cement
by the engineers. m2 5,160.00 691.92 5,160.00 3,570,307.55 2,580.00 1,785,153.78 2,580.00 1,785,153.78 - -
mortar (1:3) mix and joints grouted in appropriate colour
600x600x10mm
setting thick
coat mortar. imported
Colour type approved
and pattern quality
of tile shall be
3.2 porcelain
approved tile flooring
by the stuck down with cement mortar
engieers. m2 1,042.27 743.74 416.91 310,072.08 0.00 - - 416.91 310,072.08
(1:3) mix and joints grouted in appropriate colour setting
coat mortar. Colour and pattern of tile shall be approved
3.3 by the engineers. m2 8,670.20 1,239.86 2,837.52 3,518,128.81 2,128.14 2,638,596.61 709.38 879,532.20 - -
100x8mm high porcelain tile skirting stuck with cement
3.4 mortar (1:3) mix. Price shall include one side bullnosing. ml 3,420.16 440.04 456.02 200,667.63 0.00 - 91.20 40,133.53 364.82 160,534.10
8.19 Suspended ceiling panel m2 712.00 1,200.00 964.20 1,157,039.37 0.00 - 482.10 578,519.69 482.10 578,519.69
TOTAL CARRIED TO SUMMARY 23,195,614.50 9,019,248.59 4,423,750.38 2,664,685.98 618,653.21 1,312,159.02
10.ELECTRICAL INSTALLATION
10.3.1 ESE lighting protection conductor No 44,980.00 1.00 44,980.00 - 0.00 0.00 1.00 44,980.00
10.3.2 Low voltage system earthing No 7,280.00 2.00 14,560.00 - 0.00 0.00 2.00 14,560.00
10.3.3 1x35mm2 bare copper horizontal conductor No 208.00 25.00 5,200.00 - 0.00 0.00 25.00 5,200.00
10.3.4 1x35mm2 bare copper down conductor No 208.00 180.00 37,440.00 - 0.00 0.00 180.00 37,440.00
10.3.5 1x70mm2 yellow/green conductor No 300.00 13.00 3,900.00 - 0.00 0.00 13.00 3,900.00
10.18 Trunking and trunking mountable outlets - 0.00 0.00 0.00
10.18.1 Wall mountable aluminium surfaced truncking ml 793.00 35.00 27,755.00 - 0.00 0.00 35.00 27,755.00
10.18.2 Trunking mountable double socket outlet NO 1,697.00 21.00 35,637.00 - 0.00 0.00 21.00 35,637.00
10.18.3 Trunking mountable data/tele outlet NO 1,567.00 21.00 32,907.00 - 0.00 0.00 21.00 32,907.00
10.20 GEN 2 OTIS ELEVATOR
10.20.1 An 8 person with 18 stops 1.6m/sec speed. No 0.75 5,111,960.40 0.90 4,600,764.36 0.23 1,150,191.09 0.23 1,150,191.09 0.23 1,150,191.09 0.23 1,150,191.09
1.1 LABELLING OF DEVICES AND CABLING Sum 10,125.00 1.00 10,125.00 1.00 10,125.00
TOTAL CARRIED TO SUMMARY 39,237,554.20 4,813,268.36 1,150,191.09 1,150,191.09 1,150,191.09 1,362,695.09
Contract Contract Meskerem- 2007 E.C 1st ( 1-8) 2nd ( 9-16) 3rd ( 17-23) 4th ( 24 -30)
No. 11-SANITARY INSTALLATION
Description Unit
11.1 SANITARY EQUIPMENT (FIXTURES) 0.00
11.1.1 Supply and fix R.A.K. equivalent handwash basin 0.00
11.1.2 Supply and fix R.A.K. equivalent water closet. 0.00
11.1.3 Supply and fix R.A.K. equivalent urinal. 0.00
Supply and fix R.A.K. equivalent wall mounted toilet paper
11.1.4 holder. 0.00
11.1.5 Supply and fix 6mm thick crystal glass mirror. 0.00
11.1.6 Supply and fix wall mounted towel rail. 0.00
Supply and fix R.A.K. equivalent wall mounted soap
11.1.7 holder. 0.00
11.1.8 Supply and fix floor drain. 0.00
11.1.9 Supply and fix R.A.K. equivalent janitor sink. 0.00
11.1.10 Supply and fix floor cleanout. 0.00
Dia. 100mm 0.00
Dia. 80mm 0.00
11.1.11 Supply and fix carbondioxide fire extinguisher 0.00
11.1.12 Supply and fix mechanical foam type fire extinguisher 0.00
11.1.13 Supply and fix shower tray 0.00
Supply and fix SEFFCO or equivalent recessed wall
11.1.14 mounted fire hydrant hose. 0.00
11.1.15 Supply and fix kicthen sink of doulbe bowel. 0.00
11.1.16 Supply and fix oil/water separator. 30,375.00 1.00 30,375.00 0.00 1.00 30,375.00
11.1.17 Supply and fix floor gully. 2,700.00 28.00 75,600.00 28.00 75,600.00
Supply and fix PHELEXICARE or equivalent hand wash
11.1.18 basin. - - 0.00
Contract Contract Meskerem- 2007 E.C 1st ( 1-8) 2nd ( 9-16) 3rd ( 17-23) 4th ( 24 -30)
No. 32mm Description Unit 129.00 - - 0.00 - - -
40mm 137.00 - - 0.00 - - -
50mm 165.00 - - 0.00 - - -
65mm 227.00 - - 0.00 - - -
80mm 279.00 - - 0.00 - - -
11.2.4 80mm 388.00 - - 0.00 - - -
50mm 330.00 - - 0.00 - - -
40mm 161.00 - - 0.00 - - -
11 SANITARY INSTALLATION - - 0.00 - - -
Providing laying and joining of internal UPVC PN-6 waste
11.3.1 pipe - -
Dia 50mm Outer diameter ml 1,037.00 78.00 80,886.00 - - 0.00 - - -
Dia 75mm Outer diameter ml 117.00 85.00 9,945.00 - - 0.00 - - -
Dia 110mm Outer diameter ml 1,214.00 146.00 177,244.00 - - 0.00 - - -
Dia 160mm Outer diameter ml 79.00 253.00 19,987.00 - - 0.00 - - -
11.3.2 Vent capes - - 0.00 - - -
150mm No 206.00 - - 0.00 - - -
110mm No 137.00 - - 0.00 - - -
75mm No 88.00 - - 0.00 - - -
50mm No 73.00 - - 0.00 - - -
11.3.3 Stormwater down pipe - - 0.00 - - -
110mm ml 146.00 - - 0.00 - - -
160mm ml 253.00 - - 0.00 - - -
11.3.4 Fix flat strainer - - 0.00 - - -
a). Dia.100mm No 500.00 - - 0.00 - - -
b). Dia.150mm No 700.00 - - 0.00 - - -
11.4 WATER PROOFING WORK ml - - 0.00 - - -
11.4.1 Supply and coat Bitumen emulsion elastic water proofing ml 417.00 675.00 281,475.00 - - 0.00 - - -
Supply and install TESTUDO or equivalent . For all
11.4.2 suspended slabs,terrace,etc 2,186.00 450.00 983,700.00 - - 0.00 - - -
4mm thick membrane type water proofing under
11.4.3 basement floor slab No 2,508.00 24.00 60,192.00 - - 0.00 - - -
30 Supply, lay , test and commision Nominal outer diameter 971.00 - - 0.00 - - -
Contract Contract Meskerem- 2007 E.C 1st ( 1-8) 2nd ( 9-16) 3rd ( 17-23) 4th ( 24 -30)
No. BS 6730 or equavalent Description
institution. Unit
ml 732.00 - - 0.00 - - -
Gate Valve - -
34 Supply and fix dia.15mm bronze gate valves (PN 16), Nº 204.00 - - 0.00 - - -
40 Ditto Item No 34, but for HDPE Pipe 40mm diameter Nº 757.00 - - 0.00 - - -
41 Ditto Item No 34, but for HDPE Pipe 63mm diameter Nº 2,048.00 - - 0.00 - - -
42 Ditto Item No 34, but for HDPE Pipe 75mm diameter Nº 2,055.00 - - 0.00 - - -
43 Ditto Item No 34, but for HDPE Pipe 90mm diameter Nº 3,008.00 11.26 33,863.93 0.00 - - 11.26 33,863.93
44 Supply and fix dia.40mm bronze PRV station (PN 16) , Nº 8,153.00 - - 0.00 - - -
Vent Terminal/Cape - -
Contract Contract Meskerem- 2007 E.C 1st ( 1-8) 2nd ( 9-16) 3rd ( 17-23) 4th ( 24 -30)
No. Down pipe Description Unit - - 0.00 - - -
Supply and fix 160mm diameter uPVC Down
68 pipe for ml 584.00 - - 0.00 - - -
Spout - -
Supply and fix 50mm diameter uPVC pipe for
71 balcony ml 104.00 - - 0.00 - - -
Contract Contract Meskerem- 2007 E.C 1st ( 1-8) 2nd ( 9-16) 3rd ( 17-23) 4th ( 24 -30)
No. circulation, proper functioning of float valve (ball)
Description Unit - - 0.00
and accumulation of the accidentally entering
- - 0.00
solid particles respectively .
- - 0.00
• Strong solid supporting legs(no space for water
- - 0.00
to be retained inside)
- - 0.00
• Prior to approval of the material, submittal of
- - 0.00
the detail drawings of the tank is mandatory.
- - 0.00
diameter 90mm & 75mm outlet pipe,
- - 0.00
diameter 63mm inlet pipe,
- - 0.00
diameter 63mm approved quality float valve
- - 0.00
diameter 50mm drainage pipe with horizontal
- - 0.00
bronze gate valve( 16 BAR )
- - 0.00
diameter 50mm over flow pipe - - 0.00
Size:-10m³
No 98,561.76 2.00 197,123.52 2.00 197,123.52
III. Fire protection system - - 0.00
Pipe laying
- - 0.00
39 Supply, lay, test and commision galvanized steel pipe
80mm diameter (internal) PN16 for fire water supply No 1,268.34 10.53 13,350.86 10.53 13,350.86
40 and
Dittodistribution
item no 39,system, (pipe line
but diameter 50mmfrom
forground water
branching
reservoir to wall mounted fire fighting equipment/hose
No 710.62 26.05 18,513.43 26.05 18,513.43
41 Ditto item no 39, but diameter 100mm for FDC
No 1,623.70 8.43 13,689.82 8.43 13,689.82
42 Ditto item no 39, but diameter 150mm for Dry riser
No 3,243.19 12.15 39,392.60 12.15 39,392.60
44 Brass Landing Valve diameter =65mm ,PN(16) for
controlling hose reels; No 4,102.26 2.12 8,717.30 2.12 8,717.30
IV. Internal waste water drainage system
- - 0.00 0.00
11.3.2 Vent caps made of UPVC, PN6 complete with all
accessories. - - 0.00 0.00
150mm
No 206.00 2.00 412.00 2.00 412.00
110mm
No 137.00 2.00 274.00 2.00 274.00
75mm
No 88.00 1.00 88.00 1.00 88.00
V. Rain drainage system
- - 0.00 0.00
Roof Drain
- - 0.00 0.00
49 Supply and fix approved quality Aluminium/Pvc dome
strainer on the roof terminal of storm water drainage - - 0.00 0.00
pipes as where80mm
Size: diameter shown on the drawing. Price shall
include all the necessary connecting pieces including - - 0.00 0.00
50 Ditto Item No.49, but 100mm diameter
No 936.81 25.00 23,420.25 25.00 23,420.25
51 Ditto Item No.49, but 150mm diameter
No 1,212.08 6.00 7,272.48 6.00 7,272.48
WATER PROOFING WORK
Gas oil Benezen Oil Grease Gas oil Benezen Oil Grease Gas oil Benezen Oil Grease
Item Equipment type
no. /Capacity/ ( Lit ) ( Lit ) ( Lit ) ( Kg) ( Lit ) ( Lit ) ( Lit ) ( Kg) ( Lit ) ( Lit ) ( Lit ) ( Kg) Remark
Title: Construction Equipment & Vehicle Monthly Issue No: A3 Page No:
report Kind of Doc:
የኮንስትራክሽን ማሽነሪና የተሸከርካሪ የስራ ክንውን ወርሃዊ Form Issue Date: Sep.2011 1 of 1
ሪፖርት
u¨\
¾W^¨<
¾e^ c¯ƒ c¯ƒ u›eÑÇÏ ›ÖnkU ÖpLL ¡^à w`
SKÁ lØ` (¾cK? Kc^uƒ (for e^ Kðuƒ (for idel w³ƒ (working (working e^ uSÖup G<’@ uTi’< ‹Ó` (utilization (Total በወሩ መጨረሻ የሚገኝበት
}.l Ç lØ`) ¯Ã’ƒ operated hrs) hrs) ¾e^ k“ƒ w³ƒ hrs) hrs) (idel hrs) (force Major) (Down hrs) factor)% rent=work+idel) ሁኔታ/ቦታ
1 3-14168 Water truck 187.5 187.5 26 208.00 84.00 108.00 8 8 36000 Working
2 Mobile mixer 400 400 22.5 180.00 45.67 134.33 72000 Working
TOTAL 1,662.50 1,662.50 316.50 ### ### ### 8.00 ### ### ,
Á²Ò˨</¾S[Í cwdu=¨< eU“ ò`T ¾eU]ƒ Lò¨< eU“ ò`T ¾–aË¡~ Lò ò`T k”
e`߃:- *]Ï“M - Kƒ.T. H>dw“ S[Í ¡õM 1— ¢ú - K–aË¡~ 2—- k] K–aË¡~ ƒ.T.¡õM
}¡Kw`H” ›Uv ¢”eƒ^¡i” .¾}.¾Ó.T
Tekleberhan Ambaye Construction PLC
Project :- Commercial Bank of Ethiopia Lideta Branch Office Building (3B+G+M+11)
Title:- Material expense for Meskerem 2008
Reporting Period:-
PODIUM-1
BLOCK-A
B-SUPER STRUCTURE
B1. CONCRETE WORK
Produce and place reinforced concrete
1.01 class C-30, with minimum cement content
of 400kg/m3,
a) In Elevationof concrete filled in to form
columns m3
work and vibrated around rod reinforcement 205.2 Cement Qtl 848.5 820.8 103%
sand m3 113.7 109.8846 103%
Aggregate m3 170.54 165.9042 103%
c) In staircase steps and landings m2 171.7 Eculyaptus(#8 & 10) pcs 33 36.057 92%
d) In 200mm thick flat slabs m2 2695.94 Eculyaptus(#8 & 10) pcs = 808.782 #VALUE!
Nail (ᶲ 6,8,9&10) kg 267.5 593.1068 45%
e) In suspended beam(variation work) m2 127 Eculyaptus(#8 & 10) pcs 20 26.67 75%
b) In lift shaft concrete and shear walls m3 173.81 Cement Qtl 734.3 695.24 106%
e) In suspended beam(variation work) m2 101.6 Eculyaptus(#8 & 10) pcs = 21.336 #VALUE!
b) In lift shaft concrete and shear walls m3 170.61 Cement Qtl 705.5 682.44 103%
sand m3 91.14 91.361655 100%
Aggregate m3 136.68 137.938185 99%
c) In staircase steps and landings m3 21.14 Cement Qtl 88.5 84.56 105%
sand m3 11.3 11.32047 100%
Aggregate m3 16.96 17.09169 99%
d) In 200mm thick flat slabs m2 448.132 Cement Qtl 1799.5 1792.528 100%
sand m3 238.04 239.974686 99%
Aggregate m3 357.07 362.314722 99%
Provide, cut and fix yellow panel including sand m3 5.48 5.44068 101%
minimum 20mm thick marine plywood Aggregate m3 8.2 8.21436 100%
wooden formwork with recommended
spacers, braces and screw-adjustable
1.02 steels props that should be strong enough
to resist the pressure of fresh concrete,
tightly placed to prevent leakage of cement
paste and smooth enough to produce fine
concrete surface finishes.
a) In Elevation columns m2 1008 Eculyaptus(#8 & 10) pcs = 211.68 #VALUE!
Nail (ᶲ 8,9&10) kg 141.63 302.4 47%
b) In lift shaft concrete and shear walls m2 1492.26 Eculyaptus(#8 & 10) pcs = 313.3746 #VALUE!
Nail (ᶲ 8,9&10) kg 238.42 447.678 53%
c) In staircase steps and landings m2 137.36 Eculyaptus(#8 & 10) pcs = 28.8456 #VALUE!
Nail (ᶲ 8,9&10) kg 27.99 41.208 68%
d) In 200mm thick flat slabs m2 2180.66 Eculyaptus(#8 & 10) pcs = 654.198 #VALUE!
Nail (ᶲ 8,9&10) kg 317.26 479.7452 66%
e) In suspended beam(variation work) m2 101.6 Eculyaptus(#8 & 10) pcs = 21.336 #VALUE!
Nail (ᶲ 8,9&10) kg 16.35 30.48 54%
b) In lift shaft concrete and shear walls m3 150.62 Cement Qtl 636.75 602.48 106%
sand m3 81.51 80.65701 101%
Aggregate m3 122.25 121.77627 100%
b) In lift shaft concrete and shear walls m2 1348.44 Eculyaptus(#8 & 10) pcs 79 283.1724 28%
Nail (ᶲ 8,9&10) kg 203.5 404.532 50%
c) In staircase steps and landings m2 103.02 Eculyaptus(#8 & 10) pcs = 21.6342 #VALUE!
Nail (ᶲ 8,9&10) kg 12 30.906 39%
d) In 200mm thick flat slabs m2 2519.13 Eculyaptus(#8 & 10) pcs = 755.739 #VALUE!
Nail (ᶲ 8,9&10) kg 210.5 554.2086 38%
e) In suspended beam(variation work) m2 50.8 Eculyaptus(#8 & 10) pcs = 10.668 #VALUE!
Nail (ᶲ 8,9&10) kg 7.5 15.24 49%
Provide, erect or lay mild reinforcement
1.3 steel S-400 according to the details in the
structural drawings. It must be ensured that
bars are free of any lubricants, dirt, mud or
a) diam 8 mm deformed bar kg 283.26 Rebar ᶲ8 kg 283.26 297.423 95%
1.79 Black wire 1.5 kg 1.79 5.6652 32%
b) diam 10 mm deformed bar kg 14608.24 Rebar ᶲ10 kg 14608.24 15338.652 95%
101.24 Black wire 1.5 kg 101.24 292.1648 35%
c) diam 12 mm deformed bar kg 16648.96 Rebar ᶲ12 kg 16648.96 17481.408 95%
107.37 Black wire 1.5 kg 107.37 332.9792 32%
d) diam 14 mm deformed bar kg 9032.4 Rebar ᶲ14 kg 9032.4 9484.02 95%
63.02 Black wire 1.5 kg 63.02 180.648 35%
e) diam 16 mm deformed bar kg 7978.58 Rebar ᶲ16 kg 7978.58 8377.509 95%
55.17 Black wire 1.5 kg 55.17 159.5716 35%
f) diam 20 mm deformed bar kg 4946 Rebar ᶲ20 kg 4946 5193.3 95%
34.2 Black wire 1.5 kg 34.2 98.92 35%
g) diam 24 mm deformed bar kg 16048.96 Rebar ᶲ24 kg 16048.96 16851.408 95%
87.5 Black wire 1.5 kg 87.5 320.9792 27%
B2. BLOCK WORK
20cm thick HCB wall, embedded in
20.01 cement-sand mortar of 1:3 mix ratio. Both
sides shall be left for plastering. m2 242.86 HCB#20 pcs 2597 2987.178 87%
Cement Qtl 39.3 23.55742 167%
sand m3 10.03 5.82864 172%
B-SUPER STRUCTURE
B1. CONCRETE WORK
Produce and place reinforced concrete class C-30,
with minimum cement content of 400kg/m3, of
1.01 concrete filled in to form work and vibrated around
rod reinforcement steel. (Formwork and
reinforcement measured separately). Price shall
a) In Elevation columns m3 3,700.00
205.20 2,533.46 1,166.54 32%
b) In lift shaft concrete and shear walls m3 3,700.00
203.29 2,334.14 1,365.86 37%
c) In staircase steps and landings m 3
3,160.00
26.80 2,548.55 611.45 19%
d) In 200mm thick flat slabs m 2
599.00
2,759.99 413.10 185.90 31%
20.03 Ditto but 10cm thick HCB partition walls for toilets. 22.99 160.33 7.67 5%
m2 168
BLOCK-B
B-SUPER STRUCTURE
B1. CONCRETE WORK
Produce and place reinforced concrete class C-30,
1.01 with minimum cement content of 400kg/m3, of
concrete filled in to form work and vibrated around
rod reinforcement steel. (Formwork and
Prepared by---------------------------- Checked by---------------------------- Approved by----------------------------
a) In Elevation columns m3 3,700.00
137.16 2,751.77 948.23 26%
b) In lift shaft concrete and shear walls m 3
3,700.00
173.81 2,393.45 1,306.55 35%
20.02 Ditto but 15cm thick HCB partition walls for toilets. 552.73 233.51 1.49 1%
m2 235
20.03 Ditto but 10cm thick HCB partition walls for toilets. 43.40 194.16 -26.16 -16%
m2 168
Flush mounted light points fed through PVC insulated
conductors of 3x2.5mm² inside rigid PVC conduits of
5 LIGHT POINTS
20mm diameter, including screw connected junction
boxes for switches and junction boxes with covers 196.80 335.90 164.10 33%
5.1 insulating screw cap connectors No 500.00
DATA / TELECOM POINTS/OUTLETS AND
10 DATA / TELECOM EQUIPMENT
1 x 35mm² bare copper down conductor for
lightning protection system inside 32mm dia. PVC 10.72 80.47 89.53 53%
19.4 ml 170.00
conduite which is also inside concrete column to
earthing rod inside pit with all fixing accessories from
Block-C
B-SUPER STRUCTURE
20.02 Ditto but 15cm thick HCB partition walls for toilets. 1,306.75 225.99 9.01 4%
m2 235
20.03 Ditto but 10cm thick HCB partition walls for toilets. 63.25 178.32 -10.32 -6%
m2 168
Block-D
B-SUPER STRUCTURE
20.02 Ditto but 15cm thick HCB partition walls for toilets. 452.06 214.51 20.49 9%
m2 235
20.03 Ditto but 10cm thick HCB partition walls for toilets. 22.11 160.97 7.03 4%
m2 168
5 LIGHT POINTS
Flush mounted light points fed through PVC insulated
conductors of 3x2.5mm² inside rigid PVC conduits of
20mm diameter, including screw connected junction
boxes for switches and junction boxes with covers 142.80 298.66 201.34 40%
insulating screw cap connectors
5.1 No 500.00
DATA / TELECOM POINTS/OUTLETS AND
10 DATA / TELECOM EQUIPMENT
1 x 35mm² bare copper down conductor for
lightning protection system inside 32mm dia. PVC
conduite which is also inside concrete column to
earthing rod inside pit with all fixing accessories from 11.54 79.02 90.98 54%
the same source. .
19.4 ml 170.00
Reporting Period:-
Item
Description of problem Area of Problem Measures Taken Recommended Solutions
No
1 *shortage of HCB 15cm & 20cm thick. HCB work Informed to head office
2 *form work subcontractor ineffecinecy( Asmelash and alemnesh partnership). form work Replaced by another subcontractor
3 *Bar bending machine down. Rebar work *Problem solved on site. Informed to head office
Total -
Description of Problems Encounted During The Reporting Month Reporting Date: 6-Aug-15
Material Related Labor Related Equipment Related Design Related Subcontract Related Weather Related Other (Schedule & in Qty)
Total Not
S. no Project Executed Amount
in Birr Description of Not Executed Description of Not Executed Description of Not Executed Description of Not Executed Description of Not Executed Description of Not Executed Description of
Not Executed
Problems Amount in Problems Amount in Problems Amount in Problems Amount in Problems Amount in Problems Amount in Problems
Amount in Birr
Encountered Birr Encountered Birr Encountered Birr Encountered Birr Encountered Birr Encountered Birr Encountered
Project:-
Reporting Period:-
Financial Claim
Project:-
Reporting Period:-
Submission Sample
S. no Project Material for Approval Approval Status Remark
date Supplier
Note:- This data can't describe the monthly expense because it just an assumption but you can refer the peroll for the
accurate data. And on this report we attach the peroll for 15days.