The document provides a detailed breakdown of costs and dimensions for various RR masonry reservoir tanks ranging from 50 m³ to 400 m³. It includes quantities of materials required for construction, such as cement, sand, and wood, along with labor estimates. Additionally, it outlines the dimensions and specifications for each tank type, including outer and inner measurements.

Uploaded by

dipu37818
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views

RTCGI

The document provides a detailed breakdown of costs and dimensions for various RR masonry reservoir tanks ranging from 50 m³ to 400 m³. It includes quantities of materials required for construction, such as cement, sand, and wood, along with labor estimates. Additionally, it outlines the dimensions and specifications for each tank type, including outer and inner measurements.

Uploaded by

dipu37818
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 64

Cost Of RR Masonry Reservoir Tanks Diamension Of RR Masonry

S. DWSS Standard By Designer S Tank Unit Length "m"


N Capacity Cost Capacity Cost .N Capacity Inner
1 50 m3 #REF! 0 0 1 50 m3 5.5
2 75 m3 #REF! 0 0 2 75 m3 6.7
3 100 m 3
#REF! 0 0 3 100 m3 7.7
4 150 m3 #REF! 0 0 4 150 m3 8.6
5 175 m 3
#REF! 0 0 1055500 5 175 m3 9.3
6 200 m3 #REF! 0 0 6 200 m3 9.9
7 225 m3 #REF! 0 0 7 225 m3 10.5
8 250 m3 0 0 8 250 m3 5.6
9 275 m 3
0 0 9 275 m3 5.8
10 300 m3 0 0 10 300 m3 6
11 350 m 3
0 0 11 350 m3
6.5
12 400 m 3
0 0 12 400 m3
7
Diamension Of RR Masonry Tank CGI Sheet Type
Length "m" Breath "m" Height "m" Roof Height
Outer Inner Outer W.L Wall m
8.6 4.6 7.7 2 2.25 1.615
9.8 5.6 8.7 2 2.25 1.93
10.8 6.5 9.6 2 2.25 2.15
12.6 7 11 2.5 2.75 2.3
13.3 7.6 11.6 2.5 2.75 2.45
13.9 8.1 12.1 2.5 2.75 2.58
14.5 8.6 12.6 2.5 2.75 2.7
16.7 9 13 2.5 3 3.335
17.1 9.5 13.5 2.5 3 3.435
17.5 10 14 2.5 3 3.535
18.5 10.8 14.8 2.5 3 3.785
19.5 11.4 15.4 2.5 3 4.035
Quantity
S. Description Unit 50m3 75m3 100m3 150m3 175m3 200m3
No.
1 Site clearence (Assuming Slop = 50) m3 24.83 36.66 48.73 76.23 89.48 102.60

2 Earthwork in excavation m3 145.68 187.57 228.10 374.22 416.56 454.12

3 Earthwork in filling m3 40.05 45.45 50.12 92.28 97.36 101.66

4 250 mm thick sand packed boulder soling m3 16.56 21.32 25.92 34.65 38.57 42.05

5 150 mm thick P.C.C 1:1.5:3 for floor m3 9.213 11.970 14.647 19.058 21.312 23.316

6 R.R. masonry in 1:4 m3 43.986 53.698 62.198 98.507 106.680 113.695

7 PCC 1:1.5:3 with 2% WPC, for m3 6.184 7.240 8.152 11.040 11.820 12.480

8 20 mm thick plaster 1:3 with m2 75.39 100.89 125.14 154.50 174.20 191.65

9 Cement punning in 1:1 m2 65.70 86.72 106.85 138.20 155.18 170.19

10 Cement pointing work in 1:3 m2 17.83 23.56 28.71 33.37 37.55 41.29

11 Wood Work For Chaukhat m3 0.108 0.108 0.108 0.108 0.108 0.108

12 Wood Work For Lintel m3 0.432 0.432 0.432 0.468 0.468 0.468

13 Wood Work For Wall Plate m3 0.121 0.142 0.160 0.167 0.179 0.190

14 Wood Work For Purlin m3 0.426 0.581 0.744 0.648 0.697 0.739

15 Wood Work For Soffit Bearer 1.5 m c/c m3 0.095 0.110 0.126 0.126 0.126 0.126

16 Wood Work For Eaves board m2 2.84 3.32 3.72 4.20 4.48 4.72

17 Wood Work For Truss m3 0.314 0.372 0.424 0.461 0.495 0.524

18 38mm thick salwood panelled shutter m2 1.35 1.35 1.35 1.35 1.35 1.35

19 Chicken mesh wire for vantilator m2 1.44 1.44 1.44 1.44 1.44 1.44
20 CGI Sheet For Roofing m2 51.40 71.55 89.65 115.29 131.26 145.61

21 Ridge Cover For Roofing m 7.10 8.30 9.30 10.50 11.20 11.80

22 Welded pipe ladder 2.25 m long No. 1.00 1.00 1.00 1.00 1.00 1.00

23 Barbed wire fencing (Type - A ) m 48.20 55.00 56.40 59.20 61.80 64.00

24 Entrence gate in barbed wire fencing (Type-A ) No. 1.00 1.00 1.00 1.00 1.00 1.00
225m3 250m3 275m3 300m3 350m3 400m3

116.01 158.48 173.14 187.43 221.78 256.76

493.29 629.59 669.47 710.50 794.02 870.87

105.97 126.23 130.06 133.88 141.53 148.33

45.68 54.28 57.71 61.25 68.45 75.08

25.410 30.375 32.370 34.425 38.610 42.465

120.728 182.030 188.648 195.206 210.254 223.843

13.140 18.471 20.622 22.888 26.056 29.204

209.74 286.92 306.02 325.61 366.32 404.33

185.80 246.80 263.20 280.00 313.40 343.60

45.09 68.95 72.68 76.50 85.93 95.67

0.108 0.144 0.144 0.144 0.144 0.144

0.468 0.585 0.585 0.585 0.585 0.585

0.201 0.695 0.729 0.763 0.817 0.857

0.781 0.756 0.790 0.824 0.878 0.918

0.126

4.96 4.48 4.68 4.88 5.20 5.44

0.558 2.258 2.323 2.390 2.555 3.629

1.35 2.70 2.70 2.70 2.70 2.70

1.44 1.44 1.44 1.44 1.44 1.44


160.46 177.15 190.29 203.88 231.77 257.67

12.40 11.20 11.70 12.20 13.00 13.60

1.00 2.00 2.00 2.00 2.00 2.00

66.20 68.40 70.20 72.00 75.60 78.80

1.00 1.00 1.00 1.00 1.00 1.00


Schedule of Materials & Labours
RUBBLE MASONRY STORAGE TANK, (50 M³)

Ref : QNT. 50. m³ Drawing No. G - 13

Cement Sand StoneGravelWood SkilledUnskilled


S.N. Description QuantityUnit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items
1 Site Clearance ### m³ 39.48
2 Earthwork in Excavation ### m³ 231.64 GI Plain Sheet (m) 8.52
3 Refilling ### m³ 10.01 Screw & Nails (No) 19.87
4 Boulder Soling With Sand ### m³ ### ### ### 57.94 Holdfast (No) 9.94
5 PCC (1:1.5:3) 9.21 m³ 73.70 3.92 7.92 9.21 36.85 Hinges (No) 8.10
6 Stone Masonry in (1:4) C/S Mortar ### m³ ### ### ### ### 219.93 Chicken Wiremesh 1.44
7 20 mm Thick C/P (1:3) with 2% WP ### m³ 14.47 1.47 ### 14.32 J-Hook (No) ###
8 3 mm Thick Cement Punning (1:1) ### m² 4.42 0.15 6.57 6.57 Bitument Washer ( ###
9 Cement Pointing (1:3) ### m² 2.21 0.11 1.78 0.25 Nails (kg) 16.43
10 Wood Work for Chaukhat 0.11 m² 0.12 3.67 0.37 CGI Sheet (sqm) 61.68
11 Wood Work for Wall Plate 0.12 m² 0.13 2.13 0.21 Bolt Nut (No.) ###
12 Wood Work for Beam, Rafters, Purli 0.43 m² 0.45 7.52 0.75 WPC (Kg) 63.95
13 Wood Work for Soffit Bearer 0.09 m² 0.10 1.67 0.17 M.S. Agnle Bar (No 18.00
14 25mm Thick Wood Work for Eaves 2.84 m² 0.08 0.41 0.04 Barbed Wire (m) ###
15 Wood Work for Lintel 0.43 m² 0.45 7.62 0.76 Bolt Nut (No.) 3.14
16 Wood Work for Truss 0.31 m³ 0.33 5.55 8.17
17 38mm thick Sal Wood Panneled Shu 1.35 m² 0.11 6.37 0.64
18 Chicken Wiremesh for Ventilator 1.44 m² 0.12
19 CGI Sheet Roofing 26 Gauge (sq.m ### m 5.65 6.43
20 GI Plain Sheet Ridge Cover Work 7.10 1.42 2.13
21 PCC (1:1.5:3) with 2% WPC 6.18 m³ 49.47 2.63 5.32 4.95 43.29
22 Welded Pipe Ladder 2.25m Long 1.00 no
23 Barbed Wire Fencing (Type-) 48.20 m 2.64 8.40
24 Entrance Gate (Type-) 1.00 Set

Total : ### ### ### ### 1.77 ### 688.47


Schedule of Materials & Labours
RUBBLE MASONRY STORAGE TANK, (75 M³)

Ref : QNT. 75. m³ Drawing No. G - 13

Cement Sand StoneGravelWood SkilledUnskilled


S.N. Description QuantityUnit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items
1 Site Clearance ### m³ 58.29
2 Earthwork in Excavation ### m³ 298.24 GI Plain Sheet (m) 9.96
3 Refilling ### m³ 11.36 Screw & Nails (No) 19.87
4 Boulder Soling With Sand ### m³ ### ### ### 74.60 Holdfast (No) 9.94
5 PCC (1:1.5:3) ### m³ 95.76 5.09 ### ### 47.88 Hinges (No) 8.10
6 Stone Masonry in (1:4) C/S Mortar ### m³ ### ### ### ### 268.49 Chicken Wiremesh 1.44
7 20 mm Thick C/P (1:3) with 2% WP ### m³ 19.37 1.97 ### 19.17 J-Hook (No) ###
8 3 mm Thick Cement Punning (1:1) ### m² 5.83 0.20 8.67 8.67 Bitument Washer ( ###
9 Cement Pointing (1:3) ### m² 2.93 0.15 2.36 0.33 Nails (kg) 21.69
10 Wood Work for Chaukhat 0.11 m² 0.12 3.67 0.37 CGI Sheet (sqm) 85.86
11 Wood Work for Wall Plate 0.14 m² 0.15 2.51 0.25 Bolt Nut (No.) ###
12 Wood Work for Beam, Rafters, Purli 0.58 m² 0.61 ### 1.02 WPC (Kg) 77.29
13 Wood Work for Soffit Bearer 0.11 m² 0.12 1.95 0.19 M.S. Agnle Bar (No 20.00
14 25mm Thick Wood Work for Eaves 3.32 m² 0.09 0.47 0.05 Barbed Wire (m) ###
15 Wood Work for Lintel 0.43 m² 0.45 7.62 0.76 Bolt Nut (No.) 3.72
16 Wood Work for Truss 0.37 m³ 0.39 6.57 9.68
17 38mm thick Sal Wood Panneled Shu 1.35 m² 0.11 6.37 0.64
18 Chicken Wiremesh for Ventilator 1.44 m² 0.12
19 CGI Sheet Roofing 26 Gauge (sq.m ### m 7.87 8.94
20 GI Plain Sheet Ridge Cover Work 8.30 1.66 2.49
21 PCC (1:1.5:3) with 2% WPC 7.24 m³ 57.92 3.08 6.23 5.79 50.68
22 Welded Pipe Ladder 2.25m Long 1.00 no
23 Barbed Wire Fencing (Type-) 55.00 m 3.02 9.58
24 Entrance Gate (Type-) 1.00 Set

Total : ### ### ### ### 2.04 ### 862.23


Schedule of Materials & Labours
RUBBLE MASONRY STORAGE TANK, (100 M³)

Ref : QNT. 100. m³ Drawing No. G - 13

Cement Sand StoneGravelWood SkilledUnskilled


S.N. Description QuantityUnit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items
1 Site Clearance ### m³ 77.48
2 Earthwork in Excavation ### m³ 362.67 GI Plain Sheet (m) 11.16
3 Refilling ### m³ 12.53 Screw & Nails (No) 19.87
4 Boulder Soling With Sand ### m³ ### ### ### 90.72 Holdfast (No) 9.94
5 PCC (1:1.5:3) ### m³ ### 6.23 ### ### 58.59 Hinges (No) 8.10
6 Stone Masonry in (1:4) C/S Mortar ### m³ ### ### ### ### 310.99 Chicken Wiremesh 1.44
7 20 mm Thick C/P (1:3) with 2% WP ### m³ 24.03 2.44 ### 23.78 J-Hook (No) ###
8 3 mm Thick Cement Punning (1:1) ### m² 7.18 0.25 ### 10.69 Bitument Washer ( ###
9 Cement Pointing (1:3) ### m² 3.57 0.18 2.87 0.40 Nails (kg) 26.72
10 Wood Work for Chaukhat 0.11 m² 0.12 3.67 0.37 CGI Sheet (sqm) ###
11 Wood Work for Wall Plate 0.16 m² 0.17 2.83 0.28 Bolt Nut (No.) ###
12 Wood Work for Beam, Rafters, Purli 0.74 m² 0.78 ### 1.31 WPC (Kg) 89.24
13 Wood Work for Soffit Bearer 0.13 m² 0.13 2.22 0.22 M.S. Agnle Bar (No 21.00
14 25mm Thick Wood Work for Eaves 3.72 m² 0.10 0.53 0.05 Barbed Wire (m) ###
15 Wood Work for Lintel 0.43 m² 0.45 7.62 0.76 Bolt Nut (No.) 4.24
16 Wood Work for Truss 0.42 m³ 0.45 7.49 11.03
17 38mm thick Sal Wood Panneled Shu 1.35 m² 0.11 6.37 0.64
18 Chicken Wiremesh for Ventilator 1.44 m² 0.12
19 CGI Sheet Roofing 26 Gauge (sq.m ### m 9.86 11.21
20 GI Plain Sheet Ridge Cover Work 9.30 1.86 2.79
21 PCC (1:1.5:3) with 2% WPC 8.15 m³ 65.22 3.46 7.01 6.52 57.07
22 Welded Pipe Ladder 2.25m Long 1.00 no
23 Barbed Wire Fencing (Type-) 56.40 m 3.09 9.83
24 Entrance Gate (Type-) 1.00 Set
Total : ### ### ### ### 2.32 ### ###

Schedule of Materials & Labours


RUBBLE MASONRY STORAGE TANK, (150 M³)

Ref : QNT. 150. m³ Drawing No. G - 13

Cement Sand StoneGravelWood SkilledUnskilled


S.N. Description QuantityUnit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items
1 Site Clearance ### m³ 121.21
2 Earthwork in Excavation ### m³ 595.01 GI Plain Sheet (m) 12.60
3 Refilling ### m³ 23.07 Screw & Nails (No) 19.87
4 Boulder Soling With Sand ### m³ ### ### ### 121.27 Holdfast (No) 9.94
5 PCC (1:1.5:3) ### m³ ### 8.10 ### ### 76.23 Hinges (No) 8.10
6 Stone Masonry in (1:4) C/S Mortar ### m³ ### ### ### ### 492.54 Chicken Wiremesh 1.44
7 20 mm Thick C/P (1:3) with 2% WP ### m³ 29.66 3.01 ### 29.36 J-Hook (No) ###
8 3 mm Thick Cement Punning (1:1) ### m² 9.29 0.32 ### 13.82 Bitument Washer ( ###
9 Cement Pointing (1:3) ### m² 4.14 0.21 3.34 0.47 Nails (kg) 34.56
10 Wood Work for Chaukhat 0.11 m² 0.12 3.67 0.37 CGI Sheet (sqm) ###
11 Wood Work for Wall Plate 0.17 m² 0.18 2.95 0.29 Bolt Nut (No.) ###
12 Wood Work for Beam, Rafters, Purli 0.65 m² 0.68 ### 1.14 WPC (Kg) ###
13 Wood Work for Soffit Bearer 0.13 m² 0.13 2.22 0.22 M.S. Agnle Bar (No 22.00
14 25mm Thick Wood Work for Eaves 4.20 m² 0.12 0.60 0.06 Barbed Wire (m) ###
15 Wood Work for Lintel 0.47 m² 0.49 8.26 0.82 Bolt Nut (No.) 4.61
16 Wood Work for Truss 0.46 m³ 0.48 8.14 11.99
17 38mm thick Sal Wood Panneled Shu 1.35 m² 0.11 6.37 0.64
18 Chicken Wiremesh for Ventilator 1.44 m² 0.12
19 CGI Sheet Roofing 26 Gauge (sq.m ### m ### 14.41
20 GI Plain Sheet Ridge Cover Work ### 2.10 3.15
21 PCC (1:1.5:3) with 2% WPC ### m³ 88.32 4.69 9.49 8.83 77.28
22 Welded Pipe Ladder 2.25m Long 1.00 no
23 Barbed Wire Fencing (Type-) 59.20 m 3.25 10.32
24 Entrance Gate (Type-) 1.00 Set
Total : ### ### ### ### 2.31 ### ###

Schedule of Materials & Labours


RUBBLE MASONRY STORAGE TANK, (175 M³)

Ref : QNT. 175. m³ Drawing No. G - 13

Cement Sand StoneGravelWood SkilledUnskilled


S.N. Description QuantityUnit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items
1 Site Clearance ### m³ 142.27
2 Earthwork in Excavation ### m³ 662.33 GI Plain Sheet (m) 13.44
3 Refilling ### m³ 24.34 Screw & Nails (No) 19.87
4 Boulder Soling With Sand ### m³ ### ### ### 135.00 Holdfast (No) 9.94
5 PCC (1:1.5:3) ### m³ ### 9.06 ### ### 85.25 Hinges (No) 8.10
6 Stone Masonry in (1:4) C/S Mortar ### m³ ### ### ### ### 533.40 Chicken Wiremesh 1.44
7 20 mm Thick C/P (1:3) with 2% WP ### m³ 33.45 3.40 ### 33.10 J-Hook (No) ###
8 3 mm Thick Cement Punning (1:1) ### m² 10.43 0.36 ### 15.52 Bitument Washer ( ###
9 Cement Pointing (1:3) ### m² 4.66 0.24 3.76 0.53 Nails (kg) 38.80
10 Wood Work for Chaukhat 0.11 m² 0.12 3.67 0.37 CGI Sheet (sqm) ###
11 Wood Work for Wall Plate 0.18 m² 0.19 3.16 0.32 Bolt Nut (No.) ###
12 Wood Work for Beam, Rafters, Purli 0.70 m² 0.73 ### 1.23 WPC (Kg) ###
13 Wood Work for Soffit Bearer 0.13 m² 0.13 2.22 0.22 M.S. Agnle Bar (No 23.00
14 25mm Thick Wood Work for Eaves 4.48 m² 0.12 0.64 0.06 Barbed Wire (m) ###
15 Wood Work for Lintel 0.47 m² 0.49 8.26 0.82 Bolt Nut (No.) 4.95
16 Wood Work for Truss 0.50 m³ 0.52 8.74 12.87
17 38mm thick Sal Wood Panneled Shu 1.35 m² 0.11 6.37 0.64
18 Chicken Wiremesh for Ventilator 1.44 m² 0.12
19 CGI Sheet Roofing 26 Gauge (sq.m ### m ### 16.41
20 GI Plain Sheet Ridge Cover Work ### 2.24 3.36
21 PCC (1:1.5:3) with 2% WPC ### m³ 94.56 5.02 ### 9.46 82.74
22 Welded Pipe Ladder 2.25m Long 1.00 no
23 Barbed Wire Fencing (Type-) 61.80 m 3.39 10.77
24 Entrance Gate (Type-) 1.00 Set

Total : ### ### ### ### 2.42 ### ###

Schedule of Materials & Labours


RUBBLE MASONRY STORAGE TANK, (200 M³)

Ref : QNT. 200. m³ Drawing No. G - 13

Cement Sand StoneGravelWood SkilledUnskilled


S.N. Description QuantityUnit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items
1 Site Clearance ### m³ 163.13
2 Earthwork in Excavation ### m³ 722.05 GI Plain Sheet (m) 14.16
3 Refilling ### m³ 25.42 Screw & Nails (No) 19.87
4 Boulder Soling With Sand ### m³ ### ### ### 147.17 Holdfast (No) 9.94
5 PCC (1:1.5:3) ### m³ ### 9.91 ### ### 93.26 Hinges (No) 8.10
6 Stone Masonry in (1:4) C/S Mortar ### m³ ### ### ### ### 568.47 Chicken Wiremesh 1.44
7 20 mm Thick C/P (1:3) with 2% WP ### m³ 36.80 3.74 ### 36.41 J-Hook (No) ###
8 3 mm Thick Cement Punning (1:1) ### m² 11.44 0.39 ### 17.02 Bitument Washer ( ###
9 Cement Pointing (1:3) ### m² 5.13 0.26 4.13 0.58 Nails (kg) 42.55
10 Wood Work for Chaukhat 0.11 m² 0.12 3.67 0.37 CGI Sheet (sqm) ###
11 Wood Work for Wall Plate 0.19 m² 0.20 3.35 0.33 Bolt Nut (No.) ###
12 Wood Work for Beam, Rafters, Purli 0.74 m² 0.78 ### 1.30 WPC (Kg) ###
13 Wood Work for Soffit Bearer 0.13 m² 0.13 2.22 0.22 M.S. Agnle Bar (No 23.00
14 25mm Thick Wood Work for Eaves 4.72 m² 0.13 0.67 0.07 Barbed Wire (m) ###
15 Wood Work for Lintel 0.47 m² 0.49 8.26 0.82 Bolt Nut (No.) 5.24
16 Wood Work for Truss 0.52 m³ 0.55 9.25 13.62
17 38mm thick Sal Wood Panneled Shu 1.35 m² 0.11 6.37 0.64
18 Chicken Wiremesh for Ventilator 1.44 m² 0.12
19 CGI Sheet Roofing 26 Gauge (sq.m ### m² ### 18.20
20 GI Plain Sheet Ridge Cover Work ### m 2.36 3.54
21 PCC (1:1.5:3) with 2% WPC ### m³ 99.84 5.30 ### 9.98 87.36
22 Welded Pipe Ladder 2.25m Long 1.00 no
23 Barbed Wire Fencing (Type-) 64.00 m 3.51 11.15
24 Entrance Gate (Type-) 1.00 Set

Total : ### ### ### ### 2.51 ### ###

Schedule of Materials & Labours


RUBBLE MASONRY STORAGE TANK, (225 M³)

Ref : QNT. 225. m³ Drawing No. G - 13

Cement Sand StoneGravelWood SkilledUnskilled


S.N. Description QuantityUnit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items
1 Site Clearance ### m³ 184.46
2 Earthwork in Excavation ### m³ 784.33 GI Plain Sheet (m) 14.88
3 Refilling ### m³ 26.49 Screw & Nails (No) 19.87
4 Boulder Soling With Sand ### m³ ### ### ### 159.88 Holdfast (No) 9.94
5 PCC (1:1.5:3) ### m³ ### ### ### ### 101.64 Hinges (No) 8.10
6 Stone Masonry in (1:4) C/S Mortar ### m³ ### ### ### ### 603.64 Chicken Wiremesh 1.44
7 20 mm Thick C/P (1:3) with 2% WP ### m³ 40.27 4.09 ### 39.85 J-Hook (No) ###
8 3 mm Thick Cement Punning (1:1) ### m² 12.49 0.43 ### 18.58 Bitument Washer ( ###
9 Cement Pointing (1:3) ### m² 5.60 0.28 4.51 0.63 Nails (kg) 46.46
10 Wood Work for Chaukhat 0.11 m² 0.12 3.67 0.37 CGI Sheet (sqm) ###
11 Wood Work for Wall Plate 0.20 m² 0.21 3.55 0.35 Bolt Nut (No.) ###
12 Wood Work for Beam, Rafters, Purli 0.78 m² 0.82 ### 1.37 WPC (Kg) ###
13 Wood Work for Soffit Bearer 0.13 m² 0.13 2.22 0.22 M.S. Agnle Bar (No 24.00
14 25mm Thick Wood Work for Eaves 4.96 m² 0.14 0.71 0.07 Barbed Wire (m) ###
15 Wood Work for Lintel 0.47 m² 0.49 8.26 0.82 Bolt Nut (No.) 5.58
16 Wood Work for Truss 0.56 m³ 0.59 9.85 14.51
17 38mm thick Sal Wood Panneled Shu 1.35 m² 0.11 6.37 0.64
18 Chicken Wiremesh for Ventilator 1.44 m² 0.12
19 CGI Sheet Roofing 26 Gauge (sq.m ### m² ### 20.06
20 GI Plain Sheet Ridge Cover Work ### m 2.48 3.72
21 PCC (1:1.5:3) with 2% WPC ### m³ ### 5.58 ### ### 91.98
22 Welded Pipe Ladder 2.25m Long 1.00 no
23 Barbed Wire Fencing (Type-) 66.20 m 3.63 11.54
24 Entrance Gate (Type-) 1.00 Set

Total : ### ### ### ### 2.61 ### ###

Schedule of Materials & Labours


RUBBLE MASONRY STORAGE TANK, (250 M³)

Ref : QNT. 250. m³ Drawing No. G - 13

Cement Sand StoneGravelWood SkilledUnskilled


S.N. Description QuantityUnit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items
1 Site Clearance ### m³ 251.98
2 Earthwork in Excavation ### m³ ### GI Plain Sheet (m) 13.44
3 Refilling ### m³ 31.56 Screw & Nails (No) 26.50
4 Boulder Soling With Sand ### m³ ### ### ### 189.98 Holdfast (No) 13.25
5 PCC (1:1.5:3) ### m³ ### ### ### ### 121.50 Hinges (No) 16.20
6 Stone Masonry in (1:4) C/S Mortar 0.00 m³ 0.00 0.00 0.00 0.00 0.00 Chicken Wiremesh 1.44
7 20 mm Thick C/P (1:3) with 2% WP ### m³ 55.09 5.59 ### 54.51 J-Hook (No) ###
8 3 mm Thick Cement Punning (1:1) ### m² 16.58 0.57 ### 24.68 Bitument Washer ( ###
9 Cement Pointing (1:3) ### m² 8.56 0.43 6.90 0.96 Nails (kg) 61.73
10 Wood Work for Chaukhat 0.14 m² 0.16 4.90 0.49 CGI Sheet (sqm) ###
11 Wood Work for Wall Plate 0.70 m² 0.73 ### 1.22 Bolt Nut (No.) ###
12 Wood Work for Beam, Rafters, Purli 0.76 m² 0.79 ### 1.33 WPC (Kg) ###
13 Wood Work for Soffit Bearer 0.00 m² 0.00 0.00 0.00 M.S. Agnle Bar (No 25.00
14 25mm Thick Wood Work for Eaves 4.48 m² 0.12 0.64 0.06 Barbed Wire (m) ###
15 Wood Work for Lintel 0.59 m² 0.61 ### 1.03 Bolt Nut (No.) 22.58
16 Wood Work for Truss 2.26 m³ 2.37 ### 58.71
17 38mm thick Sal Wood Panneled Shu 2.70 m² 0.23 ### 1.27
18 Chicken Wiremesh for Ventilator 1.44 m² 0.12
19 CGI Sheet Roofing 26 Gauge (sq.m ### m ### 22.14
20 GI Plain Sheet Ridge Cover Work ### 2.24 3.36
21 PCC (1:1.5:3) with 2% WPC ### m³ ### 7.85 ### ### 129.30
22 Welded Pipe Ladder 2.25m Long 2.00 no
23 Barbed Wire Fencing (Type-) 68.40 m 3.75 11.92
24 Entrance Gate (Type-) 1.00 Set

Total : ### ### ### ### 5.02 ### ###

Schedule of Materials & Labours


RUBBLE MASONRY STORAGE TANK, (275 M³)

Ref : QNT. 275. m³ Drawing No. G - 13

Cement Sand StoneGravelWood SkilledUnskilled


S.N. Description QuantityUnit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items
1 Site Clearance ### m³ 275.29
2 Earthwork in Excavation ### m³ ### GI Plain Sheet (m) 14.04
3 Refilling ### m³ 32.52 Screw & Nails (No) 26.50
4 Boulder Soling With Sand ### m³ ### ### ### 201.99 Holdfast (No) 13.25
5 PCC (1:1.5:3) ### m³ ### ### ### ### 129.48 Hinges (No) 16.20
6 Stone Masonry in (1:4) C/S Mortar 0.00 m³ 0.00 0.00 0.00 0.00 0.00 Chicken Wiremesh 1.44
7 20 mm Thick C/P (1:3) with 2% WP ### m³ 58.76 5.97 ### 58.14 J-Hook (No) ###
8 3 mm Thick Cement Punning (1:1) ### m² 17.69 0.61 ### 26.32 Bitument Washer ( ###
9 Cement Pointing (1:3) ### m² 9.03 0.46 7.27 1.02 Nails (kg) 65.83
10 Wood Work for Chaukhat 0.14 m² 0.16 4.90 0.49 CGI Sheet (sqm) ###
11 Wood Work for Wall Plate 0.73 m² 0.77 ### 1.28 Bolt Nut (No.) ###
12 Wood Work for Beam, Rafters, Purli 0.79 m² 0.83 ### 1.39 WPC (Kg) ###
13 Wood Work for Soffit Bearer 0.00 m² 0.00 0.00 0.00 M.S. Agnle Bar (No 26.00
14 25mm Thick Wood Work for Eaves 4.68 m² 0.13 0.67 0.07 Barbed Wire (m) ###
15 Wood Work for Lintel 0.59 m² 0.61 ### 1.03 Bolt Nut (No.) 23.23
16 Wood Work for Truss 2.32 m³ 2.44 ### 60.40
17 38mm thick Sal Wood Panneled Shu 2.70 m² 0.23 ### 1.27
18 Chicken Wiremesh for Ventilator 1.44 m² 0.12
19 CGI Sheet Roofing 26 Gauge (sq.m ### m ### 23.79
20 GI Plain Sheet Ridge Cover Work ### 2.34 3.51
21 PCC (1:1.5:3) with 2% WPC ### m³ ### 8.76 ### ### 144.35
22 Welded Pipe Ladder 2.25m Long 2.00 no
23 Barbed Wire Fencing (Type-) 70.20 m 3.85 12.23
24 Entrance Gate (Type-) 1.00 Set

Total : ### ### ### ### 5.16 ### ###

Schedule of Materials & Labours


RUBBLE MASONRY STORAGE TANK, (300 M³)

Ref : QNT. 300. m³ Drawing No. G - 13

Cement Sand StoneGravelWood SkilledUnskilled


S.N. Description QuantityUnit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items
1 Site Clearance ### m³ 298.01
2 Earthwork in Excavation ### m³ ### GI Plain Sheet (m) 14.64
3 Refilling ### m³ 33.47 Screw & Nails (No) 26.50
4 Boulder Soling With Sand ### m³ ### ### ### 214.38 Holdfast (No) 13.25
5 PCC (1:1.5:3) ### m³ ### ### ### ### 137.70 Hinges (No) 16.20
6 Stone Masonry in (1:4) C/S Mortar 0.00 m³ 0.00 0.00 0.00 0.00 0.00 Chicken Wiremesh 1.44
7 20 mm Thick C/P (1:3) with 2% WP ### m³ 62.52 6.35 ### 61.87 J-Hook (No) ###
8 3 mm Thick Cement Punning (1:1) ### m² 18.82 0.64 ### 28.00 Bitument Washer ( ###
9 Cement Pointing (1:3) ### m² 9.50 0.48 7.65 1.07 Nails (kg) 70.03
10 Wood Work for Chaukhat 0.14 m² 0.16 4.90 0.49 CGI Sheet (sqm) ###
11 Wood Work for Wall Plate 0.76 m² 0.80 ### 1.34 Bolt Nut (No.) ###
12 Wood Work for Beam, Rafters, Purli 0.82 m² 0.87 ### 1.45 WPC (Kg) ###
13 Wood Work for Soffit Bearer 0.00 m² 0.00 0.00 0.00 M.S. Agnle Bar (No 26.00
14 25mm Thick Wood Work for Eaves 4.88 m² 0.13 0.70 0.07 Barbed Wire (m) ###
15 Wood Work for Lintel 0.59 m² 0.61 ### 1.03 Bolt Nut (No.) 23.90
16 Wood Work for Truss 2.39 m³ 2.51 ### 62.14
17 38mm thick Sal Wood Panneled Shu 2.70 m² 0.23 ### 1.27
18 Chicken Wiremesh for Ventilator 1.44 m² 0.12
19 CGI Sheet Roofing 26 Gauge (sq.m ### m ### 25.49
20 GI Plain Sheet Ridge Cover Work ### 2.44 3.66
21 PCC (1:1.5:3) with 2% WPC ### m³ ### 9.73 ### ### 160.22
22 Welded Pipe Ladder 2.25m Long 2.00 no
23 Barbed Wire Fencing (Type-) 72.00 m 3.95 12.55
24 Entrance Gate (Type-) 1.00 Set

Total : ### ### ### ### 5.31 ### ###

Schedule of Materials & Labours


RUBBLE MASONRY STORAGE TANK, (350 M³)

Ref : QNT. 350. m³ Drawing No. G - 13

Cement Sand StoneGravelWood SkilledUnskilled


S.N. Description QuantityUnit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items
1 Site Clearance ### m³ 352.63
2 Earthwork in Excavation ### m³ ### GI Plain Sheet (m) 15.60
3 Refilling ### m³ 35.38 Screw & Nails (No) 26.50
4 Boulder Soling With Sand ### m³ ### ### ### 239.58 Holdfast (No) 13.25
5 PCC (1:1.5:3) ### m³ ### ### ### ### 154.44 Hinges (No) 16.20
6 Stone Masonry in (1:4) C/S Mortar 0.00 m³ 0.00 0.00 0.00 0.00 0.00 Chicken Wiremesh 1.44
7 20 mm Thick C/P (1:3) with 2% WP ### m³ 70.33 7.14 ### 69.60 J-Hook (No) ###
8 3 mm Thick Cement Punning (1:1) ### m² 21.06 0.72 ### 31.34 Bitument Washer ( ###
9 Cement Pointing (1:3) ### m² 10.67 0.54 8.59 1.20 Nails (kg) 78.39
10 Wood Work for Chaukhat 0.14 m² 0.16 4.90 0.49 CGI Sheet (sqm) ###
11 Wood Work for Wall Plate 0.82 m² 0.86 ### 1.44 Bolt Nut (No.) ###
12 Wood Work for Beam, Rafters, Purli 0.88 m² 0.92 ### 1.55 WPC (Kg) ###
13 Wood Work for Soffit Bearer 0.00 m² 0.00 0.00 0.00 M.S. Agnle Bar (No 28.00
14 25mm Thick Wood Work for Eaves 5.20 m² 0.14 0.74 0.07 Barbed Wire (m) ###
15 Wood Work for Lintel 0.59 m² 0.61 ### 1.03 Bolt Nut (No.) 25.55
16 Wood Work for Truss 2.56 m³ 2.68 ### 66.43
17 38mm thick Sal Wood Panneled Shu 2.70 m² 0.23 ### 1.27
18 Chicken Wiremesh for Ventilator 1.44 m² 0.12
19 CGI Sheet Roofing 26 Gauge (sq.m ### m ### 28.97
20 GI Plain Sheet Ridge Cover Work ### 2.60 3.90
21 PCC (1:1.5:3) with 2% WPC ### m³ ### ### ### ### 182.39
22 Welded Pipe Ladder 2.25m Long 2.00 no
23 Barbed Wire Fencing (Type-) 75.60 m 4.15 13.17
24 Entrance Gate (Type-) 1.00 Set

Total : ### ### ### ### 5.60 ### ###

Schedule of Materials & Labours


RUBBLE MASONRY STORAGE TANK, (400 M³)

Ref : QNT. 400. m³ Drawing No. G - 13

Cement Sand StoneGravelWood SkilledUnskilled


S.N. Description QuantityUnit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items
1 Site Clearance ### m³ 408.25
2 Earthwork in Excavation ### m³ ### GI Plain Sheet (m) 16.32
3 Refilling ### m³ 37.08 Screw & Nails (No) 26.50
4 Boulder Soling With Sand ### m³ ### ### ### 262.78 Holdfast (No) 13.25
5 PCC (1:1.5:3) ### m³ ### ### ### ### 169.86 Hinges (No) 16.20
6 Stone Masonry in (1:4) C/S Mortar 0.00 m³ 0.00 0.00 0.00 0.00 0.00 Chicken Wiremesh 1.44
7 20 mm Thick C/P (1:3) with 2% WP ### m³ 77.63 7.88 ### 76.82 J-Hook (No) ###
8 3 mm Thick Cement Punning (1:1) ### m² 23.09 0.79 ### 34.36 Bitument Washer ( ###
9 Cement Pointing (1:3) ### m² 11.88 0.60 9.57 1.34 Nails (kg) 85.95
10 Wood Work for Chaukhat 0.14 m² 0.16 4.90 0.49 CGI Sheet (sqm) ###
11 Wood Work for Wall Plate 0.86 m² 0.90 ### 1.51 Bolt Nut (No.) ###
12 Wood Work for Beam, Rafters, Purli 0.92 m² 0.96 ### 1.62 WPC (Kg) ###
13 Wood Work for Soffit Bearer 0.00 m² 0.00 0.00 0.00 M.S. Agnle Bar (No 29.00
14 25mm Thick Wood Work for Eaves 5.44 m² 0.15 0.78 0.08 Barbed Wire (m) ###
15 Wood Work for Lintel 0.59 m² 0.61 ### 1.03 Bolt Nut (No.) 36.29
16 Wood Work for Truss 3.63 m³ 3.81 ### 94.35
17 38mm thick Sal Wood Panneled Shu 2.70 m² 0.23 ### 1.27
18 Chicken Wiremesh for Ventilator 1.44 m² 0.12
19 CGI Sheet Roofing 26 Gauge (sq.m ### m² ### 32.21
20 GI Plain Sheet Ridge Cover Work ### m 2.72 4.08
21 PCC (1:1.5:3) with 2% WPC ### m³ ### ### ### ### 204.43
22 Welded Pipe Ladder 2.25m Long 2.00 no
23 Barbed Wire Fencing (Type-) 78.80 m 4.32 13.73
24 Entrance Gate (Type-) 1.00 Set

Total : ### ### ### ### 6.82 ### ###


QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
50 M3
Drawing No : G-13
S. Description No. Length Breath Height Quantity Unit Remarks
No.
1 Site clearence (Assuming Slop = 50)
Excavation (Q=1/2 *8.6*7.7*0.75) 0.5 8.6 7.7 0.75 24.83 m3

2 Earthwork in excavation
Hard Soil 1 8.6 7.7 0.7 46.354 m3
G & B Mixed Soil 1 8.6 7.7 1 66.22 m3
Rock 1 8.6 7.7 0.5 33.11 m3
Tank ( L =l+3.1 ), ( B = b+3.1 )

3 Earthwork in filling
Along long walls (B= (0.3+0.95)/2) 2 8.6 0.63 1.95 21.13
Along short walls 2 7.7 0.63 1.95 18.92
40.05 m3

4 250 mm thick sand packed 1 8.6 7.7 0.25 16.56 m3


boulder soling

5 150 mm thick P.C.C 1:1.5:3 1 8.3 7.4 0.15 9.213 m3


for floor

6 R.R. masonry in 1:4


Rectangular Portion :
Long walls 2 6.7 0.6 2.25 18.09
(L = 1+2 * 0.6 )
Short walls 2 4.6 0.6 2.25 12.42
Gable wall 1 5.8 0.6 1.615 5.62
Triangular Portion :
Long walls 1 7.35 0.65 1.8 8.6
( L = (8+6.7)/2)
Short walls 1 6.45 0.65 1.8 7.547
( L = (7.1+5.8)/2)

Deduction
PCC for core wall 1 23.08 0.12 2 -5.539
(L=2(5.5+2*.3+2*.06+4.6+2*.3+2*.06)
PCC for pipe inlet 1 0.6 0.4 0.4 -0.096
PCC for pipe outlet 1 1.25 0.4 0.4 -0.200
PCC for washout 1 1.25 0.45 0.45 -0.253
PCC for over flow 1 0.6 0.4 0.4 -0.096
Door - opening 1 0.9 0.6 1.5 -0.810
Ventilator - opening 4 0.6 0.6 0.6 -0.864
Wooden Lintel
Door 1 1.2 0.6 0.15 -0.108
Ventilator 4 0.9 0.6 0.15 -0.324
43.986 m3

Prepared By Checked By

C:\Rijal2\Desing-Estimate\851548124.xls\RT50m3 (CHRDU)
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
50 M3
Drawing No : G-13
S. Description No. Length Breath Height Quantity Unit Remarks
No.

7 PCC 1:1.5:3 with 2% WPC, for


Inlet 1 0.6 0.4 0.4 0.096
Outlet 1 1.25 0.4 0.4 0.200
Washout 1 1.25 0.45 0.45 0.253
Over flow 1 0.6 0.4 0.4 0.096
Core Wall 1 23.08 0.12 2 5.539
6.184 m3

8 20 mm thick plaster 1:3 with


2 % WPC
Floor 1 5.5 4.6 25.3
Inner side walls 1 20.2 2.25 45.45
Gable wall 1 4.6 1.615 7.429
Deduction
Door 1 0.9 1.5 -1.35
Vantilator 4 0.6 0.6 -1.44
75.39 m2

9 Cement punning in 1:1 upto W.L.


Floor 1 5.5 4.6 25.30
(L=2*(5.5+4.6))
Inner side walls 1 20.2 2 40.40
65.70 m2

10 Cement pointing work in 1:3


on out side
Above ground
Long wall 2 6.7 0.45 6.03
Short wall 2 5.8 0.45 5.22
Gable wall 1 5.8 1.615 9.37
Deduction
Door - opening 1 0.9 1.5 -1.35
Ventilator - opening 4 0.6 0.6 -1.44
17.83 m2
11 Wood Work For Chaukhat
Door 1 4.8 0.1 0.075 0.036
Ventilator 4 2.4 0.1 0.075 0.072
0.11 m3
12 Wood Work For Lintel
Door 1 1.2 0.6 0.15 0.108
Ventilator 4 0.9 0.6 0.15 0.324
0.43 m3

C:\Rijal2\Desing-Estimate\851548124.xls\RT50m3 (CHRDU)
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
50 M3
Drawing No : G-13
S. Description No. Length Breath Height Quantity Unit Remarks
No.
Prepared By Checked By

13 Wood Work For Wall Plate 2 6.7 0.075 0.12 0.121 m3


L=Li+2x0.6
14 Wood Work For Purlin 12 7.1 0.05 0.1 0.426 m3
L=Li+2x0.6+2x0.2

15 Wood Work For Soffit Bearer 1.5 m c/c 12 1.05 0.075 0.1 0.095 m3

16 Wood Work For Eaves board (25 mm 2 7.1 0.2 2.84 m2


Thick) L=Li+2x0.6+2x0.2

17 Wood Work For Truss


Tie Beam (L=Wi+2x0.3+2x.0375) 2 5.27 0.075 0.18 0.14
King Post (1.675-.12-.18) 2 1.38 0.075 0.12 0.02
Pricipal Rafter 4 3.08 0.075 0.12 0.11
Strut 4 1.21 0.075 0.1 0.04
0.31 m3

18 38mm thick salwood panelled shutter 1 0.9 1.5 1.35 m2

19 Chicken mesh wire for vantilator 4 0.6 0.6 1.44 m2

20 CGI Sheet For Roofing 2 7.1 3.62 51.404 m2

21 Ridge Cover For Roofing 1 7.1 7.10 m

22 Welded pipe ladder 2.25 m long 1 1 No.

23 Barbed wire fencing (Type - A )


(Q=2*(l+b+14)) 5.5 4.6 48.20 m
M.S Angle Bar (No. of post ),40*40*6 mm
2.5 m long (Q=Total length / 1.5)-2) 31 No.
Length of barbed wire
(Q=(No. of post + 1)*14.74) 471.68 m

24 Entrence gate in barbed 1 1 No.


wire fencing (Type-A )

Prepared By Checked By

Note:
Quantity estimate of drain and valve chambers are not included.

C:\Rijal2\Desing-Estimate\851548124.xls\RT50m3 (CHRDU)
0
0

QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
75 M3
0 Drawing No : G-13
S. Description No. Length Breath Height Quantity Unit Remarks
No.
1 Site clearence (Assuming Slop = 50)
Excavation (Q=1/2 *9.8*8.7*0.86) 0.5 9.8 8.7 0.86 37 m3

2 Earthwork in excavation
Hard Soil 1 9.8 8.7 0.7 59.682 m3
G & B Mixed Soil 1 9.8 8.7 1 85.26 m3
Rock 1 9.8 8.7 0.5 42.63 m3
Tank ( L =l+3.1 ), ( B = b+3.1 )

3 Earthwork in filling
Along long walls (B= (0.3+0.95)/2) 2 9.8 0.63 1.95 24.08
Along short walls 2 8.7 0.63 1.95 21.38
45.45 m3

4 250 mm thick sand packed 1 9.8 8.7 0.25 21.32 m3


boulder soling

5 150 mm thick P.C.C 1:1.5:3 1 9.5 8.4 0.15 11.97 m3


for floor

6 R.R. masonry in 1:4


Rectangular Portion :
Long walls 2 7.9 0.6 2.25 21.33
(L = 1+2 * 0.6 )
Short walls 2 5.6 0.6 2.25 15.12
Gable wall 1 6.8 0.6 1.93 7.87
Triangular Portion :
Long walls 1 8.55 0.65 1.8 10.0
( L = (8+6.7)/2)
Short walls 1 7.45 0.65 1.8 8.717
( L = (7.1+5.8)/2)

Deduction
PCC for core wall 1 27.48 0.12 2 -6.595
(L=2(5.5+2*.3+2*.06+4.6+2*.3+2*.06)
PCC for pipe inlet 1 0.6 0.4 0.4 -0.096
PCC for pipe outlet 1 1.25 0.4 0.4 -0.200
PCC for washout 1 1.25 0.45 0.45 -0.253
PCC for over flow 1 0.6 0.4 0.4 -0.096
Door - opening 1 0.9 0.6 1.5 -0.810
Ventilator - opening 4 0.6 0.6 0.6 -0.864
Wooden Lintel
Door 1 1.2 0.6 0.15 -0.108
Ventilator 4 0.9 0.6 0.15 -0.324
53.698 m3

Prepared By Checked By

C:\Rijal2\Desing-Estimate\851548124.xls\RT75m3 (CHRDU)
0
0

QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
75 M3
0 Drawing No : G-13
S. Description No. Length Breath Height Quantity Unit Remarks
No.

7 PCC 1:1.5:3 with 2% WPC, for


Inlet 1 0.6 0.4 0.4 0.096
Outlet 1 1.25 0.4 0.4 0.200
Washout 1 1.25 0.45 0.45 0.253
Over flow 1 0.6 0.4 0.4 0.096
Core Wall 1 27.48 0.12 2 6.595
7.240 m3

8 20 mm thick plaster 1:3 with


2 % WPC
Floor 1 6.7 5.6 37.52
Inner side walls 1 24.6 2.25 55.35
Gable wall 1 5.6 1.93 10.81
Deduction
Door 1 0.9 1.5 -1.35
Vantilator 4 0.6 0.6 -1.44
100.89 m2

9 Cement punning in 1:1 upto W.L.


Floor 1 6.7 5.6 37.52
(L=2*(5.5+4.6))
Inner side walls 1 24.6 2 49.20
86.72 m2

10 Cement pointing work in 1:3


on out side
Above ground
Long wall 2 7.9 0.45 7.11
Short wall 2 6.8 0.45 6.12
Gable wall 1 6.8 1.93 13.12
Deduction
Door - opening 1 0.9 1.5 -1.35
Ventilator - opening 4 0.6 0.6 -1.44
23.56 m2
11 Wood Work For Chaukhat
Door 1 4.8 0.1 0.075 0.036
Ventilator 4 2.4 0.1 0.075 0.072
0.11 m3
12 Wood Work For Lintel
Door 1 1.2 0.6 0.15 0.108
Ventilator 4 0.9 0.6 0.15 0.324
0.43 m3

C:\Rijal2\Desing-Estimate\851548124.xls\RT75m3 (CHRDU)
0
0

QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
75 M3
0 Drawing No : G-13
S. Description No. Length Breath Height Quantity Unit Remarks
No.
Prepared By Checked By

13 Wood Work For Wall Plate 2 7.9 0.075 0.12 0.142 m3


L=Li+2x0.6
14 Wood Work For Purlin 14 8.3 0.05 0.1 0.581 m3
L=Li+2x0.6+2x0.2

15 Wood Work For Soffit Bearer 1.5 m c/c 14 1.05 0.075 0.1 0.110 m3

16 Wood Work For Eaves board (25 mm 2 8.3 0.2 3.32 m2


Thick) L=Li+2x0.6+2x0.2

17 Wood Work For Truss


Tie Beam (L=Wi+2x0.3+2x.0375) 2 6.27 0.075 0.18 0.17
King Post (1.675-.12-.18) 2 1.63 0.075 0.12 0.03
Pricipal Rafter 4 3.64 0.075 0.12 0.13
Strut 4 1.42 0.075 0.1 0.04
0.37 m3

18 38mm thick salwood panelled shutter 1 0.9 1.5 1.35 m2

19 Chicken mesh wire for vantilator 4 0.6 0.6 1.44 m2

20 CGI Sheet For Roofing 2 8.3 4.31 71.546 m2

21 Ridge Cover For Roofing 1 8.3 8.30 m

22 Welded pipe ladder 2.25 m long 1 1 No.

23 Barbed wire fencing (Type - A )


(Q=2*(l+b+14)) 7.9 5.6 55 m
M.S Angle Bar (No. of post ),40*40*6 mm
2.5 m long (Q=Total length / 1.5)-2) 35 No.
Length of barbed wire
(Q=(No. of post + 1)*14.74) 531 m

24 Entrence gate in barbed 1 1 No.


wire fencing (Type-A )

Prepared By Checked By

Note:
Quantity estimate of drain and valve chambers are not included.

C:\Rijal2\Desing-Estimate\851548124.xls\RT75m3 (CHRDU)
0
0

QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
100 M3
0 Drawing No : G-13
S. Description No. Length Breath Height Quantity Unit Remarks
No.
1 Site clearence (Assuming Slop = 50)
Excavation (Q=1/2 *10.8*9.6*0.94) 0.5 10.8 9.6 0.94 49 m3

2 Earthwork in excavation
Hard Soil 1 10.8 9.6 0.7 72.576 m3
G & B Mixed Soil 1 10.8 9.6 1 103.68 m3
Rock 1 10.8 9.6 0.5 51.84 m3
Tank ( L =l+3.1 ), ( B = b+3.1 )

3 Earthwork in filling
Along long walls (B= (0.3+0.95)/2) 2 10.8 0.63 1.95 26.54
Along short walls 2 9.6 0.63 1.95 23.59
50.12 m3

4 250 mm thick sand packed 1 10.8 9.6 0.25 25.92 m3


boulder soling

5 150 mm thick P.C.C 1:1.5:3 1 10.5 9.3 0.15 14.65 m3


for floor

6 R.R. masonry in 1:4


Rectangular Portion :
Long walls 2 8.9 0.6 2.25 24.03
(L = 1+2 * 0.6 )
Short walls 2 6.5 0.6 2.25 17.55
Gable wall 1 7.7 0.6 2.15 9.93
Triangular Portion :
Long walls 1 9.55 0.65 1.8 11.2
( L = (8+6.7)/2)
Short walls 1 8.35 0.65 1.8 9.770
( L = (7.1+5.8)/2)

Deduction
PCC for core wall 1 31.28 0.12 2 -7.507
(L=2(5.5+2*.3+2*.06+4.6+2*.3+2*.06)
PCC for pipe inlet 1 0.6 0.4 0.4 -0.096
PCC for pipe outlet 1 1.25 0.4 0.4 -0.200
PCC for washout 1 1.25 0.45 0.45 -0.253
PCC for over flow 1 0.6 0.4 0.4 -0.096
Door - opening 1 0.9 0.6 1.5 -0.810
Ventilator - opening 4 0.6 0.6 0.6 -0.864
Wooden Lintel
Door 1 1.2 0.6 0.15 -0.108
Ventilator 4 0.9 0.6 0.15 -0.324
62.198 m3

Prepared By Checked By

C:\Rijal2\Desing-Estimate\851548124.xls\RT100m3 (CHRDU)
0
0

QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
100 M3
0 Drawing No : G-13
S. Description No. Length Breath Height Quantity Unit Remarks
No.

7 PCC 1:1.5:3 with 2% WPC, for


Inlet 1 0.6 0.4 0.4 0.096
Outlet 1 1.25 0.4 0.4 0.200
Washout 1 1.25 0.45 0.45 0.253
Over flow 1 0.6 0.4 0.4 0.096
Core Wall 1 31.28 0.12 2 7.507
8.152 m3

8 20 mm thick plaster 1:3 with


2 % WPC
Floor 1 7.7 6.5 50.05
Inner side walls 1 28.4 2.25 63.9
Gable wall 1 6.5 2.15 13.98
Deduction
Door 1 0.9 1.5 -1.35
Vantilator 4 0.6 0.6 -1.44
125.14 m2

9 Cement punning in 1:1 upto W.L.


Floor 1 7.7 6.5 50.05
(L=2*(5.5+4.6))
Inner side walls 1 28.4 2 56.80
106.85 m2

10 Cement pointing work in 1:3


on out side
Above ground
Long wall 2 8.9 0.45 8.01
Short wall 2 7.7 0.45 6.93
Gable wall 1 7.7 2.15 16.56
Deduction
Door - opening 1 0.9 1.5 -1.35
Ventilator - opening 4 0.6 0.6 -1.44
28.71 m2
11 Wood Work For Chaukhat
Door 1 4.8 0.1 0.075 0.036
Ventilator 4 2.4 0.1 0.075 0.072
0.11 m3
12 Wood Work For Lintel
Door 1 1.2 0.6 0.15 0.108
Ventilator 4 0.9 0.6 0.15 0.324
0.43 m3

C:\Rijal2\Desing-Estimate\851548124.xls\RT100m3 (CHRDU)
0
0

QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
100 M3
0 Drawing No : G-13
S. Description No. Length Breath Height Quantity Unit Remarks
No.
Prepared By Checked By

13 Wood Work For Wall Plate 2 8.9 0.075 0.12 0.160 m3


L=Li+2x0.6
14 Wood Work For Purlin 16 9.3 0.05 0.1 0.744 m3
L=Li+2x0.6+2x0.2

15 Wood Work For Soffit Bearer 1.5 m c/c 16 1.05 0.075 0.1 0.126 m3

16 Wood Work For Eaves board (25 mm 2 9.3 0.2 3.72 m2


Thick) L=Li+2x0.6+2x0.2

17 Wood Work For Truss


Tie Beam (L=Wi+2x0.3+2x.0375) 2 7.17 0.075 0.18 0.19
King Post (1.675-.12-.18) 2 1.85 0.075 0.12 0.03
Pricipal Rafter 4 4.14 0.075 0.12 0.15
Strut 4 1.61 0.075 0.1 0.05
0.42 m3

18 38mm thick salwood panelled shutter 1 0.9 1.5 1.35 m2

19 Chicken mesh wire for vantilator 4 0.6 0.6 1.44 m2

20 CGI Sheet For Roofing 2 9.3 4.82 89.652 m2

21 Ridge Cover For Roofing 1 9.3 9.30 m

22 Welded pipe ladder 2.25 m long 1 1 No.

23 Barbed wire fencing (Type - A )


(Q=2*(l+b+14)) 7.7 6.5 56.4 m
M.S Angle Bar (No. of post ),40*40*6 mm
2.5 m long (Q=Total length / 1.5)-2) 36 No.
Length of barbed wire
(Q=(No. of post + 1)*14.74) 545 m

24 Entrence gate in barbed 1 1 No.


wire fencing (Type-A )

Prepared By Checked By

Note:
Quantity estimate of drain and valve chambers are not included.

C:\Rijal2\Desing-Estimate\851548124.xls\RT100m3 (CHRDU)
0
0

QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
150 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.
1 Site clearence (Assuming Slop = 50)
Excavation (Q=1/2 *12.6*11*1.1) 0.5 12.6 11 1.1 76.23 m3

2 Earthwork in excavation
Hard Soil 1 12.6 11 1.2 166.32 m3
G & B Mixed Soil 1 12.6 11 1 138.60 m3
Rock 1 12.6 11 0.5 69.3 m3
Tank ( L =l+3.1 ), ( B = b+3.1 )

3 Earthwork in filling
Along long walls (B= (0.3+0.95)/2) 2 12.6 0.85 2.3 49.27
Along short walls 2 11 0.85 2.3 43.01
92.28 m3

4 250 mm thick sand packed 1 12.6 11 0.25 34.65 m3


boulder soling

5 150 mm thick P.C.C 1:1.5:3 1 12.1 10.50 0.15 19.058 m3


for floor

6 R.R. masonry in 1:4


Rectangular Portion :
Long walls 2 9.9 0.65 2.75 35.39
(L = 1+2 * 0.6 )
Short walls 2 7 0.65 2.75 25.03

Triangular Portion :
Long walls 1 10.75 0.85 2.3 21.02
( L = (8+6.7)/2)
Short walls 1 9.20 0.85 2.3 17.99
( L = (7.1+5.8)/2)
Gable wall 1 8.3 0.65 2.3 12.41
Deduction
PCC for core wall 1 34.08 0.12 2.5 -10.224
(L=2(8.6+2*.3+2*.06+7+2*.3+2*.06)
PCC for pipe inlet 1 0.65 0.4 0.4 -0.104
PCC for pipe outlet 1 1.5 0.45 0.45 -0.304
PCC for washout 1 1.5 0.45 0.45 -0.304
PCC for over flow 1 0.65 0.4 0.4 -0.104
Door - opening 1 0.9 0.65 1.5 -0.878
Ventilator - opening 4 0.6 0.65 0.6 -0.936
Wooden Lintel For
Door 1 1.2 0.65 0.15 -0.117
Ventilator 4 0.9 0.65 0.15 -0.351
98.507 m3

Prepared By Checked By

C:\Rijal2\Desing-Estimate\851548124.xls\RT150m3 (CHRDU)
0
0

QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
150 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.

7 PCC 1:1.5:3 with 2% WPC, for


Inlet 1 0.65 0.4 0.4 0.104
Outlet 1 1.5 0.45 0.45 0.304
Washout 1 1.5 0.45 0.45 0.304
Over flow 1 0.65 0.4 0.4 0.104
Core Wall 1 34.08 0.12 2.5 10.224
11.040 m3

8 20 mm thick plaster 1:3 with


2 % WPC
Floor 1 8.6 7 60.2
Inner side walls 1 31.2 2.5 78
Gable wall 1 8.3 2.3 19.09
Deduction, Door 1 0.9 1.5 -1.35
Ventilator 4 0.6 0.6 -1.44
154.50 m2

9 Cement punning in 1:1 upto W.L.


Floor 1 8.6 7 60.2
(L=2*(5.5+4.6))
Inner side walls 1 31.2 2.5 78.00
138.20 m2

10 Cement pointing work in 1:3


on out side
Above ground
Long wall 2 9.9 0.45 8.91
Short wall 2 8.3 0.45 7.47
Gable wall 1 8.6 2.3 19.78
Deduction, Door 1 0.9 1.5 -1.35
Ventilator 4 0.6 0.6 -1.44
33.37 m2

11 Salwood Work For Chaukhat


Door 1 4.8 0.075 0.1 0.036
Ventilator 4 2.4 0.075 0.1 0.072
0.108 m3
12 Salwood Work For Lintel
Door 1 1.2 0.65 0.15 0.117
Ventilator 4 0.9 0.65 0.15 0.351
0.468 m3

13 Salwood Work For Wall Plate 2 9.25 0.075 0.12 0.167 m3

Prepared By Checked By

C:\Rijal2\Desing-Estimate\851548124.xls\RT150m3 (CHRDU)
0
0

QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
150 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.

14 Salwood Work For Purlin 14 9.25 0.05 0.1 0.648 m3

15 Wood Work For Soffit Bearer 1.5 m c/c 16 1.05 0.075 0.1 0.126 m3

16 Wood Work For Eaves Board 2 10.50 0.2 4.20 m2


(25 mm Thick)

17 Salwood Work For Trusses


Tie Beam 2 7.65 0.18 0.075 0.207
Principal Rafter 4 4.27 0.12 0.075 0.154
King Post 2 2 0.12 0.075 0.036
Strut 4 2.12 0.1 0.075 0.064
0.461 m3

18 38 mmThick Salwood Panelled Shutter 1 0.9 1.5 1.35 m2

19 Chicken Mesh Wire for ventilator 4 0.6 0.6 1.44 m2

20 CGI Sheet For Roofing 2 10.50 5.49 115.29 m2

21 Ridge Cover For Roof 1 10.50 10.50 m

22 Welded pipe ladder 2.25 m long 1 1 No.

23 Barbed wire fencing (Type - A )


(Q=2*(l+b+14)) 8.6 7 59.2 m
M.S Angle Bar (No. of post ),40*40*6 mm
2.5 m long (Q=Total length / 1.5)-2) 37 No.
Length of barbed wire
(Q=(No. of post + 1)*14.74) 560 m

24 Entrence gate in barbed 1 1 No.


wire fencing (Type-A )

Note:
Quantity estimate of drain and valve chambers are not included.

C:\Rijal2\Desing-Estimate\851548124.xls\RT150m3 (CHRDU)
0
0

QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
150 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.

Prepared By Checked By

C:\Rijal2\Desing-Estimate\851548124.xls\RT150m3 (CHRDU)
0
0
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
175 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.
1 Site clearence (Assuming Slop = 50)
Excavation (Q=1/2 *13.3*11.6*1.16) 0.5 13.3 11.6 1.16 89.48 m3

2 Earthwork in excavation
Hard Soil 1 13.30 11.60 1.20 185.14 m3
G & B Mixed Soil 1 13.30 11.60 1.00 154.28 m3
Rock 1 13.30 11.60 0.50 77.14 m3
Tank ( L =l+3.1 ), ( B = b+3.1 )

3 Earthwork in filling
Along long walls (B= (0.3+0.95)/2) 2 13.30 0.85 2.3 52.00
Along short walls 2 11.60 0.85 2.3 45.36
97.36 m3

4 250 mm thick sand packed 1 13.30 11.60 0.25 38.57 m3


boulder soling

5 150 mm thick P.C.C 1:1.5:3 1 12.80 11.10 0.15 21.312 m3


for floor

6 R.R. masonry in 1:4


Rectangular Portion :
Long walls 2 10.6 0.65 2.75 37.90
(L = 1+2 * 0.6 )
Short walls 2 7.6 0.65 2.75 27.17

Triangular Portion :
Long walls 1 11.45 0.85 2.3 22.39
( L = (8+6.7)/2)
Short walls 1 9.80 0.85 2.3 19.16
( L = (7.1+5.8)/2)
Gable wall 1 8.9 0.65 2.45 14.17
Deduction
PCC for core wall 1 36.68 0.12 2.5 -11.004
(L=2(8.6+2*.3+2*.06+7+2*.3+2*.06)
PCC for pipe inlet 1 0.65 0.4 0.4 -0.104
PCC for pipe outlet 1 1.5 0.45 0.45 -0.304
PCC for washout 1 1.5 0.45 0.45 -0.304
PCC for over flow 1 0.65 0.4 0.4 -0.104
Door - opening 1 0.9 0.65 1.5 -0.878
Ventilator - opening 4 0.6 0.65 0.6 -0.936
Wooden Lintel For
Door 1 1.2 0.65 0.15 -0.117
Ventilator 4 0.9 0.65 0.15 -0.351
106.680 m3

Prepared By Checked By

C:\Rijal2\Desing-Estimate\851548124.xls\RT175m3 (CHRDU)
0
0
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
175 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.

7 PCC 1:1.5:3 with 2% WPC, for


Inlet 1 0.65 0.4 0.4 0.104
Outlet 1 1.5 0.45 0.45 0.304
Washout 1 1.5 0.45 0.45 0.304
Over flow 1 0.65 0.4 0.4 0.104
Core Wall 1 36.68 0.12 2.5 11.004
11.820 m3

8 20 mm thick plaster 1:3 with


2 % WPC
Floor 1 9.3 7.6 70.68
Inner side walls 1 33.8 2.5 84.5
Gable wall 1 8.9 2.45 21.81
Deduction, Door 1 0.9 1.5 -1.35
Ventilator 4 0.6 0.6 -1.44
174.20 m2

10 Cement punning in 1:1 upto W.L.


Floor 1 9.3 7.6 70.68
(L=2*(5.5+4.6))
Inner side walls 1 33.80 2.5 84.50
155.18 m2

11 Cement pointing work in 1:3


on out side
Above ground
Long wall 2 10.6 0.45 9.54
Short wall 2 8.9 0.45 8.01
Gable wall 1 9.3 2.45 22.79
Deduction, Door 1 0.9 1.5 -1.35
Ventilator 4 0.6 0.6 -1.44
37.55 m2

12 Salwood Work For Chaukhat


Door 1 4.8 0.075 0.1 0.036
Ventilator 4 2.4 0.075 0.1 0.072
0.108 m3
Salwood Work For Lintel
Door 1 1.2 0.65 0.15 0.117
Ventilator 4 0.9 0.65 0.15 0.351
0.468 m3

13 Salwood Work For Wall Plate 2 9.95 0.075 0.12 0.179 m3

Prepared By Checked By

C:\Rijal2\Desing-Estimate\851548124.xls\RT175m3 (CHRDU)
0
0
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
175 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.

14 Salwood Work For Purlin 14 9.95 0.05 0.1 0.697 m3

15 Wood Work For Soffit Bearer 1.5 m c/c 16 1.05 0.075 0.1 0.126 m3

16 Wood Work For Eaves Board 2 11.20 0.2 4.48 m2


(25 mm Thick)

17 Salwood Work For Trusses


Tie Beam 2 8.25 0.18 0.075 0.223
Principal Rafter 4 4.61 0.12 0.075 0.166
King Post 2 2.15 0.12 0.075 0.039
Strut 4 2.22 0.1 0.075 0.067
0.495 m3

18 38 mmThick Salwood Panelled Shutter 1 0.9 1.5 1.35 m2

19 Chicken Mesh Wire for ventilator 4 0.6 0.6 1.44 m2

20 CGI Sheet For Roofing 2 11.20 5.86 131.26 m2

21 Ridge Cover For Roof 1 11.20 11.20 m

22 Welded pipe ladder 2.25 m long 1 1 No.

23 Barbed wire fencing (Type - A )


(Q=2*(l+b+14)) 9.3 7.6 61.8 m
M.S Angle Bar (No. of post ),40*40*6 mm
2.5 m long (Q=Total length / 1.5)-2) 39 No.
Length of barbed wire
(Q=(No. of post + 1)*14.74) 590 m

24 Entrence gate in barbed 1 1 No.


wire fencing (Type-A )

Note:
Quantity estimate of drain and valve chambers are not included.

C:\Rijal2\Desing-Estimate\851548124.xls\RT175m3 (CHRDU)
0
0
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
175 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.

Prepared By Checked By

C:\Rijal2\Desing-Estimate\851548124.xls\RT175m3 (CHRDU)
0
0
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
200 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.
1 Site clearence (Assuming Slop = 50)
Excavation (Q=1/2 *13.9*12.1*1.22) 0.5 13.9 12.1 1.22 102.6 m3

2 Earthwork in excavation
Hard Soil 1 13.9 12.1 1.2 201.83 m3
G & B Mixed Soil 1 13.9 12.1 1 168.19 m3
Rock 1 13.9 12.1 0.5 84.1 m3
Tank ( L =l+3.1 ), ( B = b+3.1 )

3 Earthwork in filling
Along long walls (B= (0.3+0.95)/2) 2 13.90 0.85 2.30 54.35
Along short walls 2 12.10 0.85 2.30 47.31
101.66 m3

4 250 mm thick sand packed 1 13.9 12.1 0.25 42.05 m3


boulder soling

5 150 mm thick P.C.C 1:1.5:3 1 13.4 11.60 0.15 23.316 m3


for floor

6 R.R. masonry in 1:4


Rectangular Portion :
Long walls 2 11.2 0.65 2.75 40.04
(L = 1+2 * 0.6 )
Short walls 2 8 0.65 2.75 28.96

Triangular Portion :
Long walls 1 12.05 0.85 2.3 23.56
( L = (8+6.7)/2)
Short walls 1 10.30 0.85 2.3 20.14
( L = (7.1+5.8)/2)
Gable wall 1 9.4 0.65 2.58 15.76
Deduction
PCC for core wall 1 38.88 0.12 2.5 -11.664
(L=2(8.6+2*.3+2*.06+7+2*.3+2*.06)
PCC for pipe inlet 1 0.65 0.4 0.4 -0.104
PCC for pipe outlet 1 1.5 0.45 0.45 -0.304
PCC for washout 1 1.5 0.45 0.45 -0.304
PCC for over flow 1 0.65 0.4 0.4 -0.104
Door - opening 1 0.9 0.65 1.5 -0.878
Ventilator - opening 4 0.6 0.65 0.6 -0.936
Wooden Lintel For
Door 1 1.2 0.65 0.15 -0.117
Ventilator 4 0.9 0.65 0.15 -0.351
113.695 m3

Prepared By Checked By

C:\Rijal2\Desing-Estimate\851548124.xls\RT200m3 (CHRDU)
0
0
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
200 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.

7 PCC 1:1.5:3 with 2% WPC, for


Inlet 1 0.65 0.4 0.4 0.104
Outlet 1 1.5 0.45 0.45 0.304
Washout 1 1.5 0.45 0.45 0.304
Over flow 1 0.65 0.4 0.4 0.104
Core Wall 1 38.88 0.12 2.5 11.664
12.480 m3

8 20 mm thick plaster 1:3 with


2 % WPC
Floor 1 9.9 8.1 80.19
Inner side walls 1 36 2.5 90
Gable wall 1 9.4 2.58 24.25
Deduction, Door 1 0.9 1.5 -1.35
Ventilator 4 0.6 0.6 -1.44
191.65 m2

10 Cement punning in 1:1 upto W.L.


Floor 1 9.9 8.1 80.19
(L=2*(5.5+4.6))
Inner side walls 1 36 2.5 90.00
170.19 m2

11 Cement pointing work in 1:3


on out side
Above ground
Long wall 2 11.2 0.45 10.08
Short wall 2 9.4 0.45 8.46
Gable wall 1 9.9 2.58 25.54
Deduction, Door 1 0.9 1.5 -1.35
Ventilator 4 0.6 0.6 -1.44
41.29 m2

12 Salwood Work For Chaukhat


Door 1 4.8 0.075 0.1 0.036
Ventilator 4 2.4 0.075 0.1 0.072
0.108 m3
Salwood Work For Lintel
Door 1 1.2 0.65 0.15 0.117
Ventilator 4 0.9 0.65 0.15 0.351
0.468 m3

13 Salwood Work For Wall Plate 2 10.55 0.075 0.12 0.190 m3

C:\Rijal2\Desing-Estimate\851548124.xls\RT200m3 (CHRDU)
0
0
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
200 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.
Prepared By Checked By

14 Salwood Work For Purlin 14 10.55 0.05 0.1 0.739 m3

15 Wood Work For Soffit Bearer 1.5 m c/c 16 1.05 0.075 0.1 0.126 m3

16 Wood Work For Eaves Board 2 11.80 0.2 4.72 m2


(25 mm Thick)

17 Salwood Work For Trusses


Tie Beam 2 8.75 0.18 0.075 0.236
Principal Rafter 4 4.89 0.12 0.075 0.176
King Post 2 2.28 0.12 0.075 0.041
Strut 4 2.36 0.1 0.075 0.071
0.524 m3

18 38 mmThick Salwood Panelled Shutte 1 0.9 1.5 1.35 m2

19 Chicken Mesh Wire for ventilator 4 0.6 0.6 1.44 m2

20 CGI Sheet For Roofing 2 11.80 6.17 145.61 m2

21 Ridge Cover For Roof 1 11.80 11.80 m

22 Welded pipe ladder 2.25 m long 1 1 No.

23 Barbed wire fencing (Type - A )


(Q=2*(l+b+14)) 9.9 8.1 64 m
M.S Angle Bar (No. of post ),40*40*6 mm
2.5 m long (Q=Total length / 1.5)-2) 41 No.
Length of barbed wire
(Q=(No. of post + 1)*14.74) 619 m

24 Entrence gate in barbed 1 1 No.


wire fencing (Type-A )

Note:
Quantity estimate of drain and valve chambers are not included.

C:\Rijal2\Desing-Estimate\851548124.xls\RT200m3 (CHRDU)
0
0
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
200 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.

Prepared By Checked By

C:\Rijal2\Desing-Estimate\851548124.xls\RT200m3 (CHRDU)
0
0
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
225 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.
1 Site clearence (Assuming Slop = 50)
Excavation (Q=1/2 *14.5*12.6*1.27) 0.5 14.5 12.6 1.27 116.01 m3

2 Earthwork in excavation
Hard Soil 1 14.5 12.6 1.2 219.24 m3
G & B Mixed Soil 1 14.5 12.6 1 182.7 m3
Rock 1 14.5 12.6 0.5 91.35 m3
Tank ( L =l+3.1 ), ( B = b+3.1 )

3 Earthwork in filling
Along long walls (B= (0.3+0.95)/2) 2 14.50 0.85 2.30 56.70
Along short walls 2 12.60 0.85 2.30 49.27
105.97 m3

4 250 mm thick sand packed 1 14.5 12.6 0.25 45.68 m3


boulder soling

5 150 mm thick P.C.C 1:1.5:3 1 14 12.10 0.15 25.410 m3


for floor

6 R.R. masonry in 1:4


Rectangular Portion :
Long walls 2 11.8 0.65 2.75 42.19
(L = 1+2 * 0.6 )
Short walls 2 9 0.65 2.75 30.75

Triangular Portion :
Long walls 1 12.65 0.85 2.3 24.73
( L = (8+6.7)/2)
Short walls 1 10.80 0.85 2.3 21.11
( L = (7.1+5.8)/2)
Gable wall 1 9.9 0.65 2.7 17.38
Deduction
PCC for core wall 1 41.08 0.12 2.5 -12.324
(L=2(8.6+2*.3+2*.06+7+2*.3+2*.06)
PCC for pipe inlet 1 0.65 0.4 0.4 -0.104
PCC for pipe outlet 1 1.5 0.45 0.45 -0.304
PCC for washout 1 1.5 0.45 0.45 -0.304
PCC for over flow 1 0.65 0.4 0.4 -0.104
Door - opening 1 0.9 0.65 1.5 -0.878
Ventilator - opening 4 0.6 0.65 0.6 -0.936
Wooden Lintel For
Door 1 1.2 0.65 0.15 -0.117
Ventilator 4 0.9 0.65 0.15 -0.351
120.728 m3

C:\Rijal2\Desing-Estimate\851548124.xls\RT225m3 (CHRDU)
0
0
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
225 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.
Prepared By Checked By

7 PCC 1:1.5:3 with 2% WPC, for


Inlet 1 0.65 0.4 0.4 0.104
Outlet 1 1.5 0.45 0.45 0.304
Washout 1 1.5 0.45 0.45 0.304
Over flow 1 0.65 0.4 0.4 0.104
Core Wall 1 41.08 0.12 2.5 12.324
13.140 m3

8 20 mm thick plaster 1:3 with


2 % WPC
Floor 1 10.5 8.6 90.3
Inner side walls 1 38.2 2.5 95.5
Gable wall 1 9.9 2.7 26.73
Deduction, Door 1 0.9 1.5 -1.35
Ventilator 4 0.6 0.6 -1.44
209.74 m2

10 Cement punning in 1:1 upto W.L.


Floor 1 10.5 8.6 90.3
(L=2*(5.5+4.6))
Inner side walls 1 38.2 2.5 95.50
185.80 m2

11 Cement pointing work in 1:3


on out side
Above ground
Long wall 2 11.8 0.45 10.62
Short wall 2 9.9 0.45 8.91
Gable wall 1 10.5 2.7 28.35
Deduction, Door 1 0.9 1.5 -1.35
Ventilator 4 0.6 0.6 -1.44
45.09 m2

12 Salwood Work For Chaukhat


Door 1 4.8 0.075 0.1 0.036
Ventilator 4 2.4 0.075 0.1 0.072
0.108 m3
Salwood Work For Lintel
Door 1 1.2 0.65 0.15 0.117
Ventilator 4 0.9 0.65 0.15 0.351
0.468 m3

13 Salwood Work For Wall Plate 2 11.15 0.075 0.12 0.201 m3

C:\Rijal2\Desing-Estimate\851548124.xls\RT225m3 (CHRDU)
0
0
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
225 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.
Prepared By Checked By

14 Salwood Work For Purlin 14 11.15 0.05 0.1 0.781 m3

15 Wood Work For Soffit Bearer 1.5 m c/c 16 1.05 0.075 0.1 0.126 m3

16 Wood Work For Eaves Board 2 12.40 0.2 4.96 m2


(25 mm Thick)

17 Salwood Work For Trusses


Tie Beam 2 9.25 0.18 0.075 0.25
Principal Rafter 4 5.17 0.12 0.075 0.186
King Post 2 2.48 0.12 0.075 0.045
Strut 4 2.57 0.1 0.075 0.077
0.558 m3

18 38 mmThick Salwood Panelled Shutte 1 0.9 1.5 1.35 m2

19 Chicken Mesh Wire for ventilator 4 0.6 0.6 1.44 m2

20 CGI Sheet For Roofing 2 12.40 6.47 160.46 m2

21 Ridge Cover For Roof 1 12.40 12.40 m

22 Welded pipe ladder 2.25 m long 1 1 No.

23 Barbed wire fencing (Type - A )


(Q=2*(l+b+14)) 10.5 8.6 66.2 m
M.S Angle Bar (No. of post ),40*40*6 mm
2.5 m long (Q=Total length / 1.5)-2) 42 No.
Length of barbed wire
(Q=(No. of post + 1)*14.74) 634 m

24 Entrence gate in barbed 1 1 No.


wire fencing (Type-A )

Note:
Quantity estimate of drain and valve chambers are not included.

C:\Rijal2\Desing-Estimate\851548124.xls\RT225m3 (CHRDU)
0
0
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
225 M3
0 Drawing No : G-14
S. Description No. Length Breath Height Quantity Unit Remarks
No.

Prepared By Checked By

C:\Rijal2\Desing-Estimate\851548124.xls\RT225m3 (CHRDU)
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
250 M3
Drawing No : G-15
S. Description No. Length Breath Height Quantity Unit Remarks
No.
1 Site clearence (Assuming Slop = 50)
Excavation (Q=1/2 *16.7*13*1.46) 0.5 16.7 13 1.46 158.48 m3

2 Earthwork in excavation
Hard Soil 1 16.7 13 1.4 303.94 m3
G & B Mixed Soil 1 16.7 13 1 217.1 m3
Rock 1 16.7 13 0.5 108.55 m3
Tank ( L =l+3.1 ), ( B = b+3.1 )

3 Earthwork in filling
Along long walls (B= (0.3+0.95)/2) 2 16.70 0.85 2.50 70.98
Along short walls 2 13.00 0.85 2.50 55.25
126.23 m3

4 250 mm thick sand packed 1 16.7 13 0.25 54.28 m3


boulder soling

5 150 mm thick P.C.C 1:1.5:3 1 16 12.50 0.15 30.375 m3


for floor

6 R.R. masonry in 1:4


Rectangular Portion :
Long walls 2 14.0 0.65 3 54.60
(L = 1+2 * 0.6 )
Short walls 2 9 0.65 3 35.10
Partition Wall 1 9 0.65 3 17.55
Triangular Portion :
Long walls 1 14.85 0.85 2.5 31.56
( L = (8+6.7)/2)
Short walls 1 11.15 0.85 2.5 23.69
( L = (7.1+5.8)/2)
Partition Wall 1 9 0.425 2.5 9.56
Gable wall 2 7.0 0.65 3.485 31.71
Deduction
core wall
Long walls 2 13.59 0.12 2.5 -8.154
Short walls 2 9.65 0.12 2.5 -5.790
Partition Wall 1 9.65 0.12 2.5 -2.895
PCC for pipe inlet 2 0.65 0.4 0.4 -0.208
PCC for pipe outlet 2 1.5 0.45 0.45 -0.608
PCC for washout 2 1.5 0.45 0.45 -0.608
PCC for over flow 2 0.65 0.4 0.4 -0.208
Door - opening 2 0.9 0.65 1.5 -1.755
Ventilator - opening 4 0.6 0.65 0.6 -0.936
Wooden Lintel For
Door 2 1.2 0.65 0.15 -0.234
Ventilator 4 0.9 0.65 0.15 -0.351
182.030 m3

Prepared By Checked By

7 PCC 1:1.5:3 with 2% WPC, for


Inlet 2 0.65 0.4 0.4 0.208
Outlet 2 1.5 0.45 0.45 0.608
Washout 2 1.5 0.45 0.45 0.608
Over flow 2 0.65 0.4 0.4 0.208
Core Wall 1 56.13 0.12 2.5 16.839
18.471 m3

8 20 mm thick plaster 1:3 with


2 % WPC
Floor 2 5.6 9 100.8
Inner side walls 2 29.2 2.5 146
Gable wall 2 6.35 3.485 44.26
Deduction, Door 2 0.9 1.5 -2.7
Ventilator 4 0.6 0.6 -1.44
286.92 m2

10 Cement punning in 1:1 upto W.L.


Floor 2 5.6 9 100.8
(L=2*(5.5+4.6))
Inner side walls 2 29.2 2.5 146.00
246.80 m2

11 Cement pointing work in 1:3


on out side
Above ground
Long wall 2 14 0.5 14.00
Short wall 2 10.3 0.5 10.30
Gable wall 2 7.0 3.485 48.79
Deduction, Door 2 0.9 1.5 -2.70
Ventilator 4 0.6 0.6 -1.44
68.95 m2

12 Salwood Work For Chaukhat


Door 2 4.8 0.075 0.1 0.072
Ventilator 4 2.4 0.075 0.1 0.072
0.144 m3
Salwood Work For Lintel
Door 2 1.2 0.65 0.15 0.234
Ventilator 4 0.9 0.65 0.15 0.351
0.585 m3

13 Salwood Work For Wall Plate 3 10.30 0.15 0.15 0.695 m3

Prepared By Checked By

14 Salwood Work For Purlin 18 11.20 0.05 0.075 0.756 m3

15 Wood Work For Eaves Board 2 11.20 0.2 4.48 m2


(25 mm Thick)

16 Salwood Work For Trusses


Tie Beam 3 13.35 0.1 0.15 0.601
Principal Rafter 6 7.9086 0.1 0.15 0.712
Center Strut 3 3.328 0.1 0.1 0.1
Minor Struts 6 4.992 0.1 0.1 0.3
Minor Tie 6 9.0821 0.1 0.1 0.545
2.258 m3

17 38 mmThick Salwood Panelled Shutter 2 0.9 1.5 2.70 m2

18 Chicken Mesh Wire for ventilator 4 0.6 0.6 1.44 m2

19 CGI Sheet For Roofing 2 11.20 7.9086 177.15 m2

20 Ridge Cover For Roof 1 11.20 11.20 m

21 Welded pipe ladder 2.25 m long 2 2 No.

22 Fixtures for truss


Anchor bolts 30 mm dia. 6 6 No.
Mild Steel cover plate(360x280x3) mm 3*28*.36*.28*.003*(7850kg/m3) 199.4 Kg
Mild Steel strap(52mmx6mm) 6 6 No.
Nuts & bolts 20 mm dia. 348 348 No.

23 Barbed wire fencing (Type - A )


(Q=2*(l+b+14)) 11.2 9.0 68.4 m
M.S Angle Bar (No. of post ),40*40*6 mm
2.5 m long (Q=Total length / 1.5)-2) 44 No.
Length of barbed wire
(Q=(No. of post + 1)*14.74) 663 m
24 Entrence gate in barbed 1 1 No.
wire fencing (Type-A )

Note:
Quantity estimate of drain and valve chambers are not included.

Prepared By Checked By
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
275 M3
Drawing No : G-15
S. Description No. Length Breath Height Quantity Unit Remarks
No.
1 Site clearence (Assuming Slop = 50)
Excavation (Q=1/2 *17.1*13.5*1.5) 0.5 17.1 13.5 1.5 173.14 m3

2 Earthwork in excavation
Hard Soil 1 17.1 13.5 1.4 323.19 m3
G & B Mixed Soil 1 17.1 13.5 1 230.85 m3
Rock 1 17.1 13.5 0.5 115.43 m3
Tank ( L =l+3.1 ), ( B = b+3.1 )

3 Earthwork in filling
Along long walls (B= (0.3+0.95)/2) 2 17.10 0.85 2.50 72.68
Along short walls 2 13.50 0.85 2.50 57.38
130.06 m3

4 250 mm thick sand packed 1 17.1 13.5 0.25 57.71 m3


boulder soling

5 150 mm thick P.C.C 1:1.5:3 1 17 13.00 0.15 32.370 m3


for floor

6 R.R. masonry in 1:4


Rectangular Portion :
Long walls 2 14.4 0.65 3 56.16
(L = 1+2 * 0.6 )
Short walls 2 10 0.65 3 37.05
Partition Wall 1 10 0.65 3 18.53
Triangular Portion :
Long walls 1 15.25 0.85 2.5 32.41
( L = (8+6.7)/2)
Short walls 1 11.65 0.85 2.5 24.76
( L = (7.1+5.8)/2)
Partition Wall 1 10 0.425 2.5 10.09
Gable wall 2 7.2 0.65 3.585 33.56
Deduction
core wall
Long walls 2 13.99 0.13 2.5 -9.094
Short walls 2 10.15 0.13 2.5 -6.598
Partition Wall 1 10.15 0.13 2.5 -3.299
PCC for pipe inlet 2 0.65 0.4 0.4 -0.208
PCC for pipe outlet 2 1.5 0.45 0.45 -0.608
PCC for washout 2 1.5 0.45 0.45 -0.608
PCC for over flow 2 0.65 0.4 0.4 -0.208
Door - opening 2 0.9 0.65 1.5 -1.755
Ventilator - opening 4 0.6 0.65 0.6 -0.936
Wooden Lintel For
Door 2 1.2 0.65 0.15 -0.234
Ventilator 4 0.9 0.65 0.15 -0.351
188.648 m3

Prepared By Checked By

7 PCC 1:1.5:3 with 2% WPC, for


Inlet 2 0.65 0.4 0.4 0.208
Outlet 2 1.5 0.45 0.45 0.608
Washout 2 1.5 0.45 0.45 0.608
Over flow 2 0.65 0.4 0.4 0.208
Core Wall 1 58.43 0.13 2.5 18.990
20.622 m3

8 20 mm thick plaster 1:3 with


2 % WPC
Floor 2 5.8 9.5 110.2
Inner side walls 2 30.6 2.5 153
Gable wall 2 6.55 3.585 46.96
Deduction, Door 2 0.9 1.5 -2.7
Ventilator 4 0.6 0.6 -1.44
306.02 m2

10 Cement punning in 1:1 upto W.L.


Floor 2 5.8 9.5 110.2
(L=2*(5.5+4.6))
Inner side walls 2 30.6 2.5 153.00
263.20 m2

11 Cement pointing work in 1:3


on out side
Above ground
Long wall 2 14.4 0.5 14.40
Short wall 2 10.8 0.5 10.80
Gable wall 2 7.2 3.585 51.62
Deduction, Door 2 0.9 1.5 -2.70
Ventilator 4 0.6 0.6 -1.44
72.68 m2

12 Salwood Work For Chaukhat


Door 2 4.8 0.075 0.1 0.072
Ventilator 4 2.4 0.075 0.1 0.072
0.144 m3
Salwood Work For Lintel
Door 2 1.2 0.65 0.15 0.234
Ventilator 4 0.9 0.65 0.15 0.351
0.585 m3

13 Salwood Work For Wall Plate 3 10.80 0.15 0.15 0.729 m3

Prepared By Checked By

14 Salwood Work For Purlin 18 11.70 0.05 0.075 0.790 m3

15 Wood Work For Eaves Board 2 11.70 0.2 4.68 m2


(25 mm Thick)

16 Salwood Work For Trusses


Tie Beam 3 13.75 0.1 0.15 0.619
Principal Rafter 6 8.1321 0.1 0.15 0.732
Center Strut 3 3.4277 0.1 0.1 0.103
Minor Struts 6 5.1416 0.1 0.1 0.308
Minor Tie 6 9.3542 0.1 0.1 0.561
2.323 m3

17 38 mmThick Salwood Panelled Shutter 2 0.9 1.5 2.70 m2

18 Chicken Mesh Wire for ventilator 4 0.6 0.6 1.44 m2

19 CGI Sheet For Roofing 2 11.70 8.1321 190.29 m2

20 Ridge Cover For Roof 1 11.70 11.70 m

21 Welded pipe ladder 2.25 m long 2 2 No.

22 Fixtures for truss


Anchor bolts 30 mm dia. 6 6 No.
Mild Steel cover plate(360x280x3) mm 3*28*.36*.28*.003*(7850kg/m3) 199.4 Kg
Mild Steel strap(52mmx6mm) 6 6 No.
Nuts & bolts 20 mm dia. 348 348 No.

23 Barbed wire fencing (Type - A )


(Q=2*(l+b+14)) 11.6 9.5 70.2 m
M.S Angle Bar (No. of post ),40*40*6 mm
2.5 m long (Q=Total length / 1.5)-2) 45 No.
Length of barbed wire
(Q=(No. of post + 1)*14.74) 678 m
24 Entrence gate in barbed 1 1 No.
wire fencing (Type-A )

Note:
Quantity estimate of drain and valve chambers are not included.

Prepared By Checked By
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
300 M3
Drawing No : G-15
S. Description No. Length Breath Height Quantity Unit Remarks
No.
1 Site clearence (Assuming Slop = 50)
Excavation (Q=1/2 *17.5*14*1.53) 0.5 17.5 14 1.53 187.43 m3

2 Earthwork in excavation
Hard Soil 1 17.5 14 1.4 343 m3
G & B Mixed Soil 1 17.5 14 1 245 m3
Rock 1 17.5 14 0.5 122.5 m3
Tank ( L =l+3.1 ), ( B = b+3.1 )

3 Earthwork in filling
Along long walls (B= (0.3+0.95)/2) 2 17.50 0.85 2.50 74.38
Along short walls 2 14.00 0.85 2.50 59.50
133.88 m3

4 250 mm thick sand packed 1 17.5 14 0.25 61.25 m3


boulder soling

5 150 mm thick P.C.C 1:1.5:3 1 17 13.50 0.15 34.425 m3


for floor

6 R.R. masonry in 1:4


Rectangular Portion :
Long walls 2 14.8 0.65 3 57.72
(L = 1+2 * 0.6 )
Short walls 2 10 0.65 3 39.00
Partition Wall 1 10 0.65 3 19.50
Triangular Portion :
Long walls 1 15.65 0.85 2.5 33.26
( L = (8+6.7)/2)
Short walls 1 12.15 0.85 2.5 25.82
( L = (7.1+5.8)/2)
Partition Wall 1 10 0.425 2.5 10.63
Gable wall 2 7.4 0.65 3.685 35.45
Deduction
core wall
Long walls 2 14.39 0.14 2.5 -10.073
Short walls 2 10.65 0.14 2.5 -7.455
Partition Wall 1 10.65 0.14 2.5 -3.728
PCC for pipe inlet 2 0.65 0.4 0.4 -0.208
PCC for pipe outlet 2 1.5 0.45 0.45 -0.608
PCC for washout 2 1.5 0.45 0.45 -0.608
PCC for over flow 2 0.65 0.4 0.4 -0.208
Door - opening 2 0.9 0.65 1.5 -1.755
Ventilator - opening 4 0.6 0.65 0.6 -0.936
Wooden Lintel For
Door 2 1.2 0.65 0.15 -0.234
Ventilator 4 0.9 0.65 0.15 -0.351
195.206 m3

Prepared By Checked By

7 PCC 1:1.5:3 with 2% WPC, for


Inlet 2 0.65 0.4 0.4 0.208
Outlet 2 1.5 0.45 0.45 0.608
Washout 2 1.5 0.45 0.45 0.608
Over flow 2 0.65 0.4 0.4 0.208
Core Wall 1 60.73 0.14 2.5 21.256
22.888 m3

8 20 mm thick plaster 1:3 with


2 % WPC
Floor 2 6 10 120
Inner side walls 2 32 2.5 160
Gable wall 2 6.75 3.685 49.75
Deduction, Door 2 0.9 1.5 -2.7
Ventilator 4 0.6 0.6 -1.44
325.61 m2

10 Cement punning in 1:1 upto W.L.


Floor 2 6 10 120
(L=2*(5.5+4.6))
Inner side walls 2 32 2.5 160.00
280.00 m2

11 Cement pointing work in 1:3


on out side
Above ground
Long wall 2 14.8 0.5 14.80
Short wall 2 11.3 0.5 11.30
Gable wall 2 7.4 3.685 54.54
Deduction, Door 2 0.9 1.5 -2.70
Ventilator 4 0.6 0.6 -1.44
76.50 m2

12 Salwood Work For Chaukhat


Door 2 4.8 0.075 0.1 0.072
Ventilator 4 2.4 0.075 0.1 0.072
0.144 m3
Salwood Work For Lintel
Door 2 1.2 0.65 0.15 0.234
Ventilator 4 0.9 0.65 0.15 0.351
0.585 m3

13 Salwood Work For Wall Plate 3 11.30 0.15 0.15 0.763 m3

Prepared By Checked By

14 Salwood Work For Purlin 18 12.20 0.05 0.075 0.824 m3

15 Wood Work For Eaves Board 2 12.20 0.2 4.88 m2


(25 mm Thick)

16 Salwood Work For Trusses


Tie Beam 3 14.15 0.1 0.15 0.637
Principal Rafter 6 8.3556 0.1 0.15 0.752
Center Strut 3 3.5275 0.1 0.1 0.106
Minor Struts 6 5.2912 0.1 0.1 0.317
Minor Tie 6 9.6263 0.1 0.1 0.578
2.390 m3

17 38 mmThick Salwood Panelled Shutter 2 0.9 1.5 2.70 m2

18 Chicken Mesh Wire for ventilator 4 0.6 0.6 1.44 m2

19 CGI Sheet For Roofing 2 12.20 8.3556 203.88 m2

20 Ridge Cover For Roof 1 12.20 12.20 m

21 Welded pipe ladder 2.25 m long 2 2 No.

22 Fixtures for truss


Anchor bolts 30 mm dia. 6 6 No.
Mild Steel cover plate(360x280x3) mm 3*28*.36*.28*.003*(7850kg/m3) 199.4 Kg
Mild Steel strap(52mmx6mm) 6 6 No.
Nuts & bolts 20 mm dia. 348 348 No.

23 Barbed wire fencing (Type - A )


(Q=2*(l+b+14)) 12.0 10.0 72 m
M.S Angle Bar (No. of post ),40*40*6 mm
2.5 m long (Q=Total length / 1.5)-2) 46 No.
Length of barbed wire
(Q=(No. of post + 1)*14.74) 693 m
24 Entrence gate in barbed 1 1 No.
wire fencing (Type-A )

Note:
Quantity estimate of drain and valve chambers are not included.

Prepared By Checked By
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
350 M3
Drawing No : G-15
S. Description No. Length Breath Height Quantity Unit Remarks
No.
1 Site clearence (Assuming Slop = 50)
Excavation (Q=1/2 *18.5*14.8*1.62) 0.5 18.5 14.8 1.62 221.78 m3

2 Earthwork in excavation
Hard Soil 1 18.5 14.8 1.4 383.32 m3
G & B Mixed Soil 1 18.5 14.8 1 273.8 m3
Rock 1 18.5 14.8 0.5 136.9 m3
Tank ( L =l+3.1 ), ( B = b+3.1 )

3 Earthwork in filling
Along long walls (B= (0.3+0.95)/2) 2 18.50 0.85 2.50 78.63
Along short walls 2 14.80 0.85 2.50 62.90
141.53 m3

4 250 mm thick sand packed 1 18.5 14.8 0.25 68.45 m3


boulder soling

5 150 mm thick P.C.C 1:1.5:3 1 18 14.30 0.15 38.610 m3


for floor

6 R.R. masonry in 1:4


Rectangular Portion :
Long walls 2 15.8 0.65 3 61.62
(L = 1+2 * 0.6 )
Short walls 2 11 0.65 3 42.12
Partition Wall 1 11 0.65 3 21.06
Triangular Portion :
Long walls 1 16.65 0.85 2.5 35.38
( L = (8+6.7)/2)
Short walls 1 12.95 0.85 2.5 27.52
( L = (7.1+5.8)/2)
Partition Wall 1 11 0.425 2.5 11.48
Gable wall 2 7.9 0.65 3.935 40.41
Deduction
core wall
Long walls 2 15.39 0.15 2.5 -11.543
Short walls 2 11.45 0.15 2.5 -8.588
Partition Wall 1 11.45 0.15 2.5 -4.294
PCC for pipe inlet 2 0.65 0.4 0.4 -0.208
PCC for pipe outlet 2 1.5 0.45 0.45 -0.608
PCC for washout 2 1.5 0.45 0.45 -0.608
PCC for over flow 2 0.65 0.4 0.4 -0.208
Door - opening 2 0.9 0.65 1.5 -1.755
Ventilator - opening 4 0.6 0.65 0.6 -0.936
Wooden Lintel For
Door 2 1.2 0.65 0.15 -0.234
Ventilator 4 0.9 0.65 0.15 -0.351
210.254 m3

Prepared By Checked By

7 PCC 1:1.5:3 with 2% WPC, for


Inlet 2 0.65 0.4 0.4 0.208
Outlet 2 1.5 0.45 0.45 0.608
Washout 2 1.5 0.45 0.45 0.608
Over flow 2 0.65 0.4 0.4 0.208
Core Wall 1 65.13 0.15 2.5 24.424
26.056 m3

8 20 mm thick plaster 1:3 with


2 % WPC
Floor 2 6.5 10.8 140.4
Inner side walls 2 34.6 2.5 173
Gable wall 2 7.25 3.935 57.06
Deduction, Door 2 0.9 1.5 -2.7
Ventilator 4 0.6 0.6 -1.44
366.32 m2

10 Cement punning in 1:1 upto W.L.


Floor 2 6.5 10.8 140.4
(L=2*(5.5+4.6))
Inner side walls 2 34.6 2.5 173.00
313.40 m2

11 Cement pointing work in 1:3


on out side
Above ground
Long wall 2 15.8 0.5 15.80
Short wall 2 12.1 0.5 12.10
Gable wall 2 7.9 3.935 62.17
Deduction, Door 2 0.9 1.5 -2.70
Ventilator 4 0.6 0.6 -1.44
85.93 m2

12 Salwood Work For Chaukhat


Door 2 4.8 0.075 0.1 0.072
Ventilator 4 2.4 0.075 0.1 0.072
0.144 m3
Salwood Work For Lintel
Door 2 1.2 0.65 0.15 0.234
Ventilator 4 0.9 0.65 0.15 0.351
0.585 m3

13 Salwood Work For Wall Plate 3 12.10 0.15 0.15 0.817 m3

Prepared By Checked By

14 Salwood Work For Purlin 18 13.00 0.05 0.075 0.878 m3

15 Wood Work For Eaves Board 2 13.00 0.2 5.20 m2


(25 mm Thick)

16 Salwood Work For Trusses


Tie Beam 3 15.15 0.1 0.15 0.682
Principal Rafter 6 8.9143 0.1 0.15 0.802
Center Strut 3 3.7768 0.1 0.1 0.113
Minor Struts 6 5.6651 0.1 0.1 0.34
Minor Tie 6 10.307 0.1 0.1 0.618
2.555 m3

17 38 mmThick Salwood Panelled Shutter 2 0.9 1.5 2.70 m2

18 Chicken Mesh Wire for ventilator 4 0.6 0.6 1.44 m2

19 CGI Sheet For Roofing 2 13.00 8.9143 231.77 m2

20 Ridge Cover For Roof 1 13.00 13.00 m

21 Welded pipe ladder 2.25 m long 2 2 No.

22 Fixtures for truss


Anchor bolts 30 mm dia. 6 6 No.
Mild Steel cover plate(360x280x3) mm 3*28*.36*.28*.003*(7850kg/m3) 199.4 Kg
Mild Steel strap(52mmx6mm) 6 6 No.
Nuts & bolts 20 mm dia. 348 348 No.

23 Barbed wire fencing (Type - A )


(Q=2*(l+b+14)) 13.0 10.8 75.6 m
M.S Angle Bar (No. of post ),40*40*6 mm
2.5 m long (Q=Total length / 1.5)-2) 48 No.
Length of barbed wire
(Q=(No. of post + 1)*14.74) 722 m
24 Entrence gate in barbed 1 1 No.
wire fencing (Type-A )

Note:
Quantity estimate of drain and valve chambers are not included.

Prepared By Checked By
QUANTITY ESTIMATE
RUBBLE MASNORY STORAGE TANK
400 M3
Drawing No : G-15
S. Description No. Length Breath Height Quantity Unit Remarks
No.
1 Site clearence (Assuming Slop = 50)
Excavation (Q=1/2 *19.5*15.4*1.71) 0.5 19.5 15.4 1.71 256.76 m3

2 Earthwork in excavation
Hard Soil 1 19.5 15.4 1.4 420.42 m3
G & B Mixed Soil 1 19.5 15.4 1 300.3 m3
Rock 1 19.5 15.4 0.5 150.15 m3
Tank ( L =l+3.1 ), ( B = b+3.1 )

3 Earthwork in filling
Along long walls (B= (0.3+0.95)/2) 2 19.50 0.85 2.50 82.88
Along short walls 2 15.40 0.85 2.50 65.45
148.33 m3

4 250 mm thick sand packed 1 19.5 15.4 0.25 75.08 m3


boulder soling

5 150 mm thick P.C.C 1:1.5:3 1 19 14.90 0.15 42.465 m3


for floor

6 R.R. masonry in 1:4


Rectangular Portion :
Long walls 2 16.8 0.65 3 65.52
(L = 1+2 * 0.6 )
Short walls 2 11 0.65 3 44.46
Partition Wall 1 11 0.65 3 22.23
Triangular Portion :
Long walls 1 17.65 0.85 2.5 37.51
( L = (8+6.7)/2)
Short walls 1 13.55 0.85 2.5 28.79
( L = (7.1+5.8)/2)
Partition Wall 1 11 0.425 2.5 12.11
Gable wall 2 8.4 0.65 4.185 45.70
Deduction
core wall
Long walls 2 16.39 0.16 2.5 -13.112
Short walls 2 12.05 0.16 2.5 -9.640
Partition Wall 1 12.05 0.16 2.5 -4.820
PCC for pipe inlet 2 0.65 0.4 0.4 -0.208
PCC for pipe outlet 2 1.5 0.45 0.45 -0.608
PCC for washout 2 1.5 0.45 0.45 -0.608
PCC for over flow 2 0.65 0.4 0.4 -0.208
Door - opening 2 0.9 0.65 1.5 -1.755
Ventilator - opening 4 0.6 0.65 0.6 -0.936
Wooden Lintel For
Door 2 1.2 0.65 0.15 -0.234
Ventilator 4 0.9 0.65 0.15 -0.351
223.843 m3

Prepared By Checked By

7 PCC 1:1.5:3 with 2% WPC, for


Inlet 2 0.65 0.4 0.4 0.208
Outlet 2 1.5 0.45 0.45 0.608
Washout 2 1.5 0.45 0.45 0.608
Over flow 2 0.65 0.4 0.4 0.208
Core Wall 1 68.93 0.16 2.5 27.572
29.204 m3

8 20 mm thick plaster 1:3 with


2 % WPC
Floor 2 7 11.4 159.6
Inner side walls 2 36.8 2.5 184
Gable wall 2 7.75 4.185 64.87
Deduction, Door 2 0.9 1.5 -2.7
Ventilator 4 0.6 0.6 -1.44
404.33 m2

10 Cement punning in 1:1 upto W.L.


Floor 2 7 11.4 159.6
(L=2*(5.5+4.6))
Inner side walls 2 36.8 2.5 184.00
343.60 m2

11 Cement pointing work in 1:3


on out side
Above ground
Long wall 2 16.8 0.5 16.80
Short wall 2 12.7 0.5 12.70
Gable wall 2 8.4 4.185 70.31
Deduction, Door 2 0.9 1.5 -2.70
Ventilator 4 0.6 0.6 -1.44
95.67 m2

12 Salwood Work For Chaukhat


Door 2 4.8 0.075 0.1 0.072
Ventilator 4 2.4 0.075 0.1 0.072
0.144 m3
Salwood Work For Lintel
Door 2 1.2 0.65 0.15 0.234
Ventilator 4 0.9 0.65 0.15 0.351
0.585 m3

13 Salwood Work For Wall Plate 3 12.70 0.15 0.15 0.857 m3

Prepared By Checked By

14 Salwood Work For Purlin 18 13.60 0.05 0.075 0.918 m3

15 Wood Work For Eaves Board 2 13.60 0.2 5.44 m2


(25 mm Thick)

16 Salwood Work For Trusses


Tie Beam 4 16.15 0.1 0.15 0.969
Principal Rafter 8 9.473 0.1 0.15 1.137
Center Strut 4 4.026 0.1 0.1 0.161
Minor Struts 8 6.0391 0.1 0.1 0.483
Minor Tie 8 10.987 0.1 0.1 0.879
3.629 m3

17 38 mmThick Salwood Panelled Shutter 2 0.9 1.5 2.70 m2

18 Chicken Mesh Wire for ventilator 4 0.6 0.6 1.44 m2

19 CGI Sheet For Roofing 2 13.60 9.473 257.67 m2

20 Ridge Cover For Roof 1 13.60 13.60 m

21 Welded pipe ladder 2.25 m long 2 2 No.

22 Fixtures for truss


Anchor bolts 30 mm dia. 6 6 No.
Mild Steel cover plate(360x280x3) mm 3*28*.36*.28*.003*(7850kg/m3) 199.4 Kg
Mild Steel strap(52mmx6mm) 6 6 No.
Nuts & bolts 20 mm dia. 348 348 No.

23 Barbed wire fencing (Type - A )


(Q=2*(l+b+14)) 14.0 11.4 78.8 m
M.S Angle Bar (No. of post ),40*40*6 mm
2.5 m long (Q=Total length / 1.5)-2) 51 No.
Length of barbed wire
(Q=(No. of post + 1)*14.74) 766 m
24 Entrence gate in barbed 1 1 No.
wire fencing (Type-A )

Note:
Quantity estimate of drain and valve chambers are not included.

Prepared By Checked By