6_OEE-002_Block1_Unit-3_compressed
6_OEE-002_Block1_Unit-3_compressed
Power cables of adequate current carrying capacity and voltage rating are
provided at the substation. Power cables are used for 33 kV, 11 kV or LT system
to carry load current.
Applications of Cable
Industry Telecom
Objectives
After studying this unit, you should be able to
Figure 3.2 : Typical XLPE (Cross Linked Polyethylene Insulated Power Cable)
(d) XLPE cables are light in weight thus easy to handle during
manufacturing and Installation.
Copper Conductor
Conductor Shield
Impregnated
Paper Insulation
Insulation
Shield
Paper & Copper
Tape Core Binder
Lead Alloy
Sheath
PVC or PE
Outer Cover
Insulated cables are usually employed for medium and low voltage. It is mainly
used for domestic and industrial lights and power installations.
In such cables the conductor are stranded around a hollow cylindrical spiral of
plain narrow metal strip. 49
Overview of Power The Oil Filled Cables are of three types :
Distribution
System (a) Single core with an oil channel within conductor.
(a) The thickness of the dielectric required decreases, which reduces the
overall size and weight of the cable.
With the growing need for long term economy, safety and reliability, overhead
conductors are now increasingly being replaced by Aerial Bunched Cables, both
in LT and HT distribution network with limited space for clearance.
Applications
Advantages
Conductor
Conductor Shield
Conductors for cables rated over 3300 volts are shielded with an
extruded, semi-conducting compound applied in tandem with and
firmly bonded to the insulation.
Insulation
Insulation Shielding
Laying-Up
Armouring
The armouring is applied over the core or inner-sheath, for the single
core cables; and over the inner-sheath, for the three core cables.
Outer-Sheath
The Single- and the three-core cables are provided with an extruded
PVC outer-sheath. The thickness of the sheath should be as
indicated in the relevant Tables.
Testing/Quality Control
Packing
Sizing of Cables
Voltage Drop
Losses
Selection of Cable
Selecting the correct type and size of cable for the desired
application is very important for any electrical project because the
performance of all equipment largely depends on the performance of
cables.
Selecting the correct type and size of cable not only ensures the
trouble-free performance but also optimized the cost of equipment,
installation and the operation as well.
Supply System
Installation Details
Cables are delivered on wood or metal drums. The outer width of the drum is
covered with wooden planks or equivalent. These planks have to be removed to
expose the cable and to be able to unwind it.
After the planking has been removed, the cable should be examined for exterior
damage, if any. To avoid damage to the protective covering and insulation,
cables should not be pulled over hard and pointed obstacles nor should it be
bent too sharply. 55
Overview of Power The cable should always be pulled off the top of the drum. In doing so, the drum
Distribution
should be placed in such a way that the painted arrow points to the opposite
System
direction of the pulling. The drum has to be propped up high enough off the
ground for the plank used for braking not to become wedged in the underneath.
Heavy drums are propped up on hydraulic jacks.
Suitable provisions should be made to brake the drum, in order that in the case
of a sudden stop further rolling and consequent unfurling and buckling of the
cable is avoided. The kinks (nooses) are particularly dangerous and should be
avoided at all costs and under any condition. A simple plank can serve as the
drum brake. When pulling, the cable is turned by hand in order to avoid
excessive tensional stress, which may damage the cables, particularly in the
case of smaller unarmoured cables.
Under no circumstances should the windings be lifted off a coil or drum laying
flat, as this would causes the cable to be twisted and damaged.
(c) In a Trough
The choice of system depends upon the nature of external conditions, load, cost
and soil condition.
A trench of suitable depth is dug out along the route of cable. A bed
of about 15 cm thickness of clean sand or soft loose earth is made at
the trench base over which the U. G. Cable is laid as such. After
laying the cable another 15 cm layer of clean sand or soft earth and
covered by bricks is provided before filling the trench with loose earth
excavated and rammed properly.
A set of pipes or duct is laid in the ground. The material used may
vary from metal, to High Density Plastic, to cement concrete or even
stone-ware. The cable is then drawn or laid in the duct or pipe. This
method is suitable for short length cable routes because of easy
drawing and least bends, for example, in a work shop/ factory and
road crossing.
56
Trough Laying Electrical
Power Cables
The trenches/channels are dug out in earth along the route in which
covered type wood/metal/clay/porcelain trough are laid. The free
space of the trough is then filled with bitumen compound and finally
covered by the top slabs or covers. After providing covers, loose
earth is filled in the trench and rammed.
Cable Faults
Detection of Fault
As we have noted, the cable is mostly laid in covered location (inside a conduit,
trench, etc.). Hence, visual inspection of the faulty location is not possible
without removing the cover. This makes it imperative to deduce the approximate
location of the fault, as thus only we can know where to remove the cover.
A cable fault locator is an equipment used to not only identify a cable fault, but
also to calculate the distance to the fault. This equipment is applied to the cable
end nearer to the suspected fault. The distance reading is used to locate fault.
As would be apparent, the cable length on a drum may not be the exact length
required along the cable path. If the drum length is more than the path length,
we may cut off the required length to lay a single un-jointed length over the
entire path. However, if the path length is more than the length of cable available
on a drum, we would need to add the extra length from a second drum. This
leads to having two pieces of cable, which need to be joined, to become the
conductor of electric power over the path.
Even in the case of a cable fault, the repair is usually carried out by cutting away
the faulty section of the cable and using another piece of similar cable as a
bridge, to join the two sections together, to have a repaired and functional cable.
In either case, jointing of the cables is required. Jointing kits are available for this
Cable Lugs
Jointing Sleeves
Scrapper Tool
59
Overview of Power
Distribution 3.6 CABLE JOINTING AND TERMINATIONS
System
As compare to overhead lines, cables have the following advantages :
Cable Jointing
A joint connecting two length of cable such that the continuity of the
conductor, the insulation and the protective covering is maintained.
or
Main Sleeve
Side Sleeve
Safety Instructions
The basic of cable jointing involves cutting the cable properly to produce
clean ends, cutting back the insulation to reveal the conductors and the
armour/screen, without allowing the conducting parts to come in contact.
First the individual conductor is joined electrically secure. Next, the
insulation on each conductor is extended over the joint. Thereafter, the
screen or the armour is extended over the joint. Last of all, the outer
sheath is completed.
This is true for all types of cable. However, the detailed instructions vary as
per the cable type and the jointing kit. The description given here is a
typical case.
Jointing Instruction
Degrease paper inner sheath next to the lead sheath and then wrap
glass bedding tape for a distance of 10 mm.
Put the heat shrinkable belting oil barrier on the glass bedding tape
already applied and shrink with help of blow lamp/torch. Avoid extra
beating.
Put the heat shrinkable stress control tube into position ensuring that
15 mm of the sleeve comes on the lead sheath and remaining on
belting oil barrier sleeve. Shrink with the help of a blow lamp/torch.
Slide the heat shrinkable oil barrier sleeve from the end of the cores
and place them at position ensuring that they go down into the crutch
of the cable as much as possible. Carefully shrink down barrier
sleeve from bottom to top ensuring that heat is uniformly applied
around each tube. Allow to cool.
Slide the breakout over the cores and pull well down into the Crutch
of the cables. Hold down out with a plier to avoid upward slippage.
Commence shrinking the boot at the centre working along them to
the top and shrink completely.
After ensuring that two conductors meet end to end at the centre of ferrule
compress the ferrule with compression die.
Compress in order from the Centre of the ferrule to the both ends of the
ferrule.
During the process of crimping, take care not to damage the insulation.
Smoothen the surface of inline connector (Ferrule) with the help of smooth
file or a sand paper.
Clean the surface of insulation and ferrule with the help of clean cloth
soaked with cleaning fluid supply with kit.
Put the insulating tube Q2 on the insulating tube Q1 and shrink it with the
help of blow lamp/torch.
Fix the main earthing connection with the help of copper braided strip from
lead to lead. Use plumbing metal for sealing gap between the steel strip
armour and lead sheath.
The continuity between armour and lead sheath shall also be achieved.
Relay the course as far as possible. Wrap two layers of G.I. mesh around
the cores with a 50% overlap. Cover the joint area upto the exposed
armour. Bind the end of G.I. mesh with the help of cotton tape and PVC
tape provided in the kit. Fold back the excess earth braid/s over the
applied G.I. mesh and tighten it with armour clamp on both sides. Cover
armour clamps and all sharp edges with the help of cotton tape or PVC
tape.
Wrap mastic-sealing tape over the worm drive clamp. Slide the heat
shrinkable adhesive lined side sleeve on one side of the G.I. wire mesh
ensuring that about 200 mm of G.I. wire mesh is covered under this and
63
Overview of Power shrink completely. Slide the second sleeve to the other side of the G.I. wire
Distribution
mesh and position it at the prescribed position and shrunk completely.
System
Cable Ends are Terminated by Providing
Insulation
While making joints and terminations, it is essential to know the size and
type of the cable in order to select appropriate kits for joints and
terminations. The kits contain the accessories required along with
instruction sheets for step-by-step procedure for making joints and
terminations. The cable and end terminations should be prepared as per
the dimensional drawing and procedure given in the instruction sheet.
Types of Terminations
A joint is considered to be the weakest link in the system. But the overall
reliability of a distribution system depends on it. Therefore, jointing
accessories and techniques have an important and critical role despite
their comparative low value in the overall investment.
Heat Shrinkable
Cold Shrinkable
The cable drums or coils, even if they are small and not heavy, should not be
dropped or thrown onto the ground from railway wagon or trucks during
unloading operations, as the cable is likely to get damaged.
A ramp or crane may be used for unloading cable drums. If neither of these is
available, a temporary ramp with inclination 1 : 3 to 1 : 4 approx. should be
constructed. The ramp must be strong enough to support the weight of the drum.
64 While rolling down the ramp, the drum should be guided by holding ropes with
the aid of winches or blocks. Additionally, a sand bed at the foot of the ramp may Electrical
Power Cables
be made to brake the rolling of cable drum.
The arrow painted on the flange of the drum indicates the direction in which the
drum should be rolled. The cable will unwind and become loose if the drum is
rolled in the opposite direction.
If the cable is not to be laid directly off the drum trailer it should be unloaded as
close as possible to where it is to be laid out later on. The drum should never be
rolled over longer distances.
The site chosen for storage of cable drums should be well-drained and should
preferably have a concrete surface/firm surface which will not cause the drums
to sink and lead to flange rot and extreme difficulty in moving the drums.
In no case should the drums be stored ‘on the flat’; that is, with flange horizontal.
Overhead covering is not essential unless the storage is for a very long period.
The cable should, however, be protected from direct rays of the sun by leaving
the battens on or by providing some form of shielding.
When for any reason, it is necessary to rewind a cable on to another drum, the
barrel of the drum should have a diameter not less than that of the original drum.
Normally cables are supplied in lengths upto 500 m on each drum. Greater
lengths make unrolling of the cable difficult. There is also the danger of the inner
end of the cable moving. If this occurs the laying will have to be stopped in order
to secure this end. The cable may kink at the transition points from one of the
layers to the next and the layers themselves may become jumbled up if this is
not done from time to time. Therefore it has to be considered whether the saving
in the jointing work will not be more than nullified by the additional work to be
carried out when installing excessive lengths.
3.8 SUMMARY
65
Overview of Power In this unit, we dealt with cables. We have learnt various things about electrical
Distribution
cables. You have been introduced to the construction of different types of cable.
System
We had also learnt the techniques of laying of cables.
Like any other item, even cables in use may fail sometimes. We have learnt
about the types of cable faults and how these are detected.
Once a fault is detected, the next step is to rectify it. This is done by creating a
cable joint. We learnt the need for joints and the method to make them. We also
learnt about some cable jointing kits.
(c) Why would we advice against keeping the cable drum with
flange horizontal?
66
Check Your Progress 4 Electrical
Power Cables
Refer to Section 3.5 of this unit.
(b) The cable is laid some 30 cm to 100 cm below the surface, to avoid
accidental access. Often the cable is laid in a conduit or cemented
trench with brick topping. This prevents damage to the cable while
digging.
(c) In this condition, the weight of the total length of the cable on the
drum impinges on the part closer to ground. This may lead to
physical damage to a section of the cable. The possibility of
deformities in this section is also pretty high. Finally, due to its own
weight, the cable coils will tend to unwind and slacken; producing
further danger of bends and kinks.
67