The document outlines the operational availability and downtime of rental Gensets for September 2022, detailing a total of 30 days with a target of 4104 operational hours. It lists excessive downtime for each Genset, resulting in a total excess downtime of 1080 hours. Consequently, the payable fixed charge amounts to $59,684.21 based on a monthly rate of $81,000.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
10 views
DOWNTIME September Calculation
The document outlines the operational availability and downtime of rental Gensets for September 2022, detailing a total of 30 days with a target of 4104 operational hours. It lists excessive downtime for each Genset, resulting in a total excess downtime of 1080 hours. Consequently, the payable fixed charge amounts to $59,684.21 based on a monthly rate of $81,000.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2
Fixed charge
Available operational time
Excessive downtime Payable Fixed charge
Rental Gensets Availability - September 2022
Days = 30
GenSets No. Possible hours each Total possible hrs
6 720 4320
Allowable Down time (5%) 216
Target hours for full Fixed Charge 4104
Equipment Downtime hrs (April) Remarks
Genset 1 408 LV supply not available after incident Genset 2 48 LV supply not available after incident Genset 3 384 LV supply not available after incident Genset 4 48 LV supply not available after incident Genset 5 312 LV supply not available after incident Genset 6 96 LV supply not available after incident 1296
Excess downtime = Actual downtime - Allowable downtime