Side effects of Current-Limiting Reactors on power system
Side effects of Current-Limiting Reactors on power system
a r t i c l e i n f o a b s t r a c t
Article history: Air-cored Current-Limiting Reactor (CLR) has already been widely applied to limit the magnitude of fault
Received 16 December 2010 current in power systems in many countries, Brazil for example, and meanwhile the CLR has made a sig-
Accepted 11 July 2012 nificant contribution to the severity of transient overvoltages in power systems, such as transient recov-
Available online 26 October 2012
ery voltage (TRV), switching overvoltage (SOV), and temporary overvoltage (TOV). The present paper here
did a lot of simulations on the application of CLR for a real-life transmission line, suggesting that with
Keywords: equipment parameters of originally draft, TRV would have exceeded the circuit breakers’ TRV ratings
Current-Limiting Reactor
and necessary measures should be taken to decrease TRV. Digital simulations were made with PSCAD/
Transient recovery voltage
Switching overvoltage
EMTDC software and the results implied that the magnitude of the SOV and the TOV increased up to
Temporary overvoltage or even exceeded the safe limits with the CLR installed. Relevant studies are strongly recommended
before the CLR is applied to ensure the safety of equipment and transmission system.
Ó 2012 Published by Elsevier Ltd.
1. Introduction transient recovery voltage (TRV) across the circuit breaker con-
tacts, associated with the interruption of the circuit current [3,4].
With the development of power system, the short-circuit cur- The switching overvoltage (SOV) and the temporary overvoltage
rent levels are increasing rapidly. In some substations, the fault (TOV) will increase as well because of the lumped inductance. In
current has been close to or even exceeded the capacity of the cir- this presented research, various simulations on those overvoltages
cuit breakers. Decreasing the short-circuit current levels can not were carried out with PSCAD/EMTDC, and the results are discussed
only prevent important equipment from being broken down by in the following sections.
large fault current, but also reduce electromagnetic interference
caused by fault current. The most common solutions to high fault
2. Side effects of the CLR on the TRV
current levels are [1]: up-rating of switchgear and other equip-
ment; splitting the grid and introducing higher voltage connec-
During the short-circuit current interruption process, at current
tions (AC or DC); introducing higher impedance transformers and
zero when current is interrupted, the system oscillates in accor-
series reactors; and using complex strategies like sequential net-
dance with its natural frequency. This system-generated voltage,
work tripping. Nevertheless, these alternatives may bring other
called the TRV, is impressed across the opening breaker contacts
problems such as loss of power system security and reliability,
and stresses the gap insulation. If the TRV has a high rate of rise
high costs, and increase of power losses. The applications of air-
in the first few microseconds following current interruption, it
cored Current-Limiting Reactor (CLR) in Brazil [1] and Canada [2]
may reestablish a current flow sufficient to heat the arc column
implied that CLR had significant effects on decreasing fault current,
and restore conduction. If the heating exceeds the breakers capa-
thus, up to now, the usage of CLR is a widely adopted solution in
bility to remove heat and cool the arc channel, then reignition
the world.
occurs.
The guidance factors for the CLR dimensioning, which could
When the CLR is inserted into the circuit, for instance, to limit
even make the CLR application unfeasible were the voltage drop,
the short-circuit current, the rise rate of TRV tends to drastically
the joule losses and the high magnetic fluxes (higher distances/
increase because of its very large surge impedance. Fortunately,
clearances required). On the other hand, despite these disadvan-
installing a suitable capacitor across the reactor may easily solve
tages, their effects could be economically compensated when
this problem [5–8]. Capacitors are necessary in some cases and
avoiding equipment substitution.
usually an in-depth computer analysis must be performed to make
It is demonstrated that the presence of a lumped inductance in
sure the circuit breaker characteristics are not exceeded [9–11].
an electric circuit will lead to an increase in the severity of the
In China, the CLR is installed for the first time on 500 kV
Sijing–Huangdu transmission line shown in Fig. 1 and Table 1
⇑ Corresponding author. Tel.: +86 10 62772197; fax: +86 10 62784709. [12]. Intensive investigations show that the TRV of this line
E-mail address: [email protected] (S. Chen). may lead to the circuit breaker failures. The specified TRV was a
Shipai
Huangdu a
Sijing
Nanqiao
Huxi
b
Table 1
Transmission line parameters of equivalence power network.
four-parameter TRV to reflect the initial part due to the series reac-
tor and the later part due to the overall bus and transformer
arrangement, the parameters of TRV are listed in Table 2 [13,14]. Fig. 2. (a) TRV at HD. (b) TRV at SJ (dash red line: the limit of TRV, dot green line:
single phase fault at HD, dash dot blue line: single phase fault in the middle, solid
2.1. TRV caused by single phase short-circuit black line: single phase fault at SJ). (For interpretation of the references to colour in
this figure legend, the reader is referred to the web version of this article.)
The magnitude and shape of the TRV vary with the type of
grounding and the point where the fault takes place. Single phase
short-circuit is the most frequently encountered problem in the
power system, thus TRV caused by it is of great importance to
a
the safety of circuit breakers. The calculated TRV at different loca-
tions of the transmission line are shown in Fig. 2a for Huangdu
(HD) substation and in Fig. 2b for Sijing (SJ) substation.
Fig. 2 illustrates the oscillograph of voltage versus time during
an interruption. Notice the TRV at both substations exceed the lim-
it while single phase fault takes place. Especially at Sijing substa-
tion, the steepness of TRV is much larger than the limit.
Table 2
Standard value of TRV with four-parameters in 500 kV.
Rated voltage (kV) Test method First off coefficient Amplitude factor First reference voltage (kV) Time1 (ls) Amplitude of TRV (kV) Time2 (ls)
550 Outlet terminal fault 1.3 1.4 438 219 817 876
Short line fault 1 1.4 337 168 629 672
342 S. Chen et al. / Electrical Power and Energy Systems 45 (2013) 340–345
simple addition of surge capacitors. In the original project draft, tions and further analysis was performed to determine the
60 nF capacitors were planned to be installed at SJ substation to re- minimum capacitance required for the circuit breakers to mitigate
duce the TRV. The effects of the CLR and the surge capacitors on the TRV resulting from faults. In this case, the method that 1 lF
TRV are studied and the results in different conditions are shown and 0.8 lF parallel capacitors installed at HD and SJ substation
in Fig. 4. respectively works well and the TRV at both substations meet
To summarize, Fig. 4 demonstrates that the CLR and capacitors the limit as shown in Fig. 5.
have great effect on TRV, and the following conclusions can be
drawn:
3. Side effects of the CLR on switching overvoltages
(1) Without the CLR and the surge capacitors, TRV at HD are
3.1. Theoretical analysis
lower than the limit, while the steepness of TRV at SJ
exceeds the limit.
As the insulation level of EHVAC systems is largely determined
(2) The imposed high-frequency TRV caused by CLR installed at
by the magnitude of switching overvoltages, it is necessary to
SJ exceeds the circuit breaker TRV capability.
recalculate the voltage stresses on aging equipment still in service
(3) Capacitors installed at SJ in the original draft have some
before the CLRs are installed. Theoretical analysis had indicated
effects on decreasing the TRV at SJ. Both the amplitude and
that switching overvoltages will increase with CLR applied. For a
steepness of TRV reduce. While at HD, there is little effect
three phase transmission line, the three phases energizing switch-
and the TRV scarcely change.
ing overvoltage is [15]:
(4) With CLR and the surge capacitors in the original draft, TRV
at both substations exceeds the limit. Additional methods to uc ðtÞ ¼ U m ½ cosðxt þ uÞ
reduce TRV should be taken. qffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
2
þ ðx=x0 Þ2 sin u þ cos2 u edt cosðx0 t þ hÞ ð1Þ
For this study the focus is on controlling the component of TRV
where u = u0 arctan[(xL 1/xC)/R], tan h = x/x0 tan u, x0 ¼
to meet specified short-line fault TRV capabilities for circuit break- qffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
ers. Larger capacitors are suggested to be installed at both substa- 1=LC d2 , d = R/2L, uc is the voltage at the terminal of the trans-
a d
b e
c f
Fig. 4. Single phase fault with 60 nF capacitors installed at SJ. (a) TRV at HD while fault near HD. (b) TRV at SJ while fault near HD. (c) TRV at HD while fault in the middle. (d)
TRV at HD while fault in the middle. (e) TRV at HD while fault near SJ. (f) TRV at SJ while fault near SJ (dash red line: the limit of TRV, dash dot blue line: no THE CLR and
capacitor; dot green line: with THE CLR; solid black line: with THE CLR and capacitor). (For interpretation of the references to colour in this figure legend, the reader is referred
to the web version of this article.)
S. Chen et al. / Electrical Power and Energy Systems 45 (2013) 340–345 343
made to get the 98% probability overvoltage. The results are listed
a
in Tables 4 and 5.
These results show that adding CLR to the transmission line in-
deed increases the switching overvoltages, which is consistent
with the theory above. Since the impedance of the CLR used in
the simulations is very small compared to the impedance of the
transmission line, the rising rates of switching overvoltages are
not obviously. Three phases energizing and single phase reclosing
switching overvoltages rise by 2.01% and 1.53% respectively. The
severest switching overvoltage is 1.79 p.u., just a little lower than
the limit value (1.8 p.u.) in China.
Based on Eqs. (2) and (3), larger impedance CLR could cause
greater overvoltages on the transmission line. CLRs with other
b impedances were also used in the simulations and the results are
shown in Table 6.
As stated in Table 6, it is demonstrated that installing CLR will
lead to an increment of the switching overvoltages. The up-rates
of overvoltages depend on the impedance of CLR, especially for
the three phases energizing switching overvoltage. If the imped-
ance of CLR is larger than 20 X, the overvoltage will exceed the
limit (1.8 p.u.).
to be the highest and most accurate digital simulation environment CLR (X) 0 km 80 km 160 km 240 km 320 km 400 km
for handling such a problem. Three phase energizing
Since the amplitude of switching overvoltages depends on the 7.85 (p.u.) 1.52 1.64 1.70 1.74 1.79 1.75
switching angle, Monte Carlo Method based simulations were 20 (p.u.) 1.55 1.66 1.73 1.76 1.82 1.76
40 (p.u.) 1.60 1.70 1.76 1.81 1.86 1.76
60 (p.u.) 1.64 1.76 1.85 1.89 1.90 1.77
Table 3 Single phase reclosing
Parameters of 750 kV transmission line. 7.85 (p.u.) 1.24 1.33 1.36 1.36 1.34 1.29
20 (p.u.) 1.23 1.37 1.38 1.40 1.39 1.28
Line names Wires Length Load
40 (p.u.) 1.23 1.42 1.42 1.47 1.47 1.27
Yinchuan–Lanzhou 6 400 400 km 413 MW + 571 MVAR 60 (p.u.) 1.24 1.44 1.44 1.49 1.48 1.29
344 S. Chen et al. / Electrical Power and Energy Systems 45 (2013) 340–345
Table 7
Switching overvoltages with different calculation methods.
some case, thus intensive simulations are strongly recommended [7] Harner RH, Rodriguez J. Transient recovery voltages associated with power
system, three-phase transformer secondary faults. IEEE Trans Power App Syst
before the CLR applied to ensure the overvoltages of equipment
1972;91(5):1887–96.
and transmission lines are well within the safe limits. [8] Hedman DE, Lambert SR. Power circuit breaker transient recovery voltages.
IEEE Trans Power App Syst 1976;95(1):197–207.
[9] Steurer M, Hribernik W, Brunke JH. Calculating the transient recovery voltage
References associated with clearing transformer determined faults by means of frequency
response analysis. IEEE Trans Power Del 2004;19(1):168–73.
[10] Swindler DL, Chwartz PS, Hamer PS, et al. Transient recovery voltage
[1] Amon FJ, Fernandez PC, Rose EH et al. Brazilian successful experience in the considerations in the application of medium-voltage circuit breakers. IEEE
usage of current limiting reactors for short circuit limitation. In: International Trans Ind Appl 1997;33(2):383–8.
Power Systems Transients (IPST’ 05). Montreal, Canada; 2005. [11] Wagner CL, Smith HM. Analysis of transient recovery voltage (TRV) rating
[2] Bellei TA, Camm EH, Ransom G. Current-limiting inductors used in capacitor concepts. IEEE Trans Power App Syst 1984;103(11):3354–63.
bank applications and their impact on fault current interruption. In: [12] Chen S, Xu W, Wang Z, et al. Effects of 500 kV current-limiting inductors on
Proceedings of the IEEE power engineering society transmission and transient recovery voltage and its countermeasures. North China Electr Power
distribution conference. vol. 1, 2001. p. 603–8. 2008;5(1):11–5.
[3] Peelo DF, Polovick GS, Sawada JH, et al. Mitigation of circuit breaker transient [13] DL/T 40222007. Order technical conditions of high voltage AC circuit breakers.
recovery voltages associated with current limiting reactors. IEEE Trans Power Beijing: China Electric Power Press; 2007.
Del 1996;11(2):865–71. [14] IEC 622712100. High-voltage alternation-current circuit-breakers, 2001.
[4] Kado H, Uriu Y, Ishigooka T. Line fault test of model power system with three- [15] Zhang Weibo, He Jinliang, Gao Yuming. Overvoltage protection and insulation
phase superconducting fault current-limiting reactors. Electr Eng Jpn coordination. Beijing: Tsinghua University Press; 2002.
2007;112(4):85–90. [16] Ketabi A, Ranjbar AM, Feuillet R. Analysis and control of temporary
[5] Smith RK. Tests show ability of vacuum circuit breaker to interrupt fast overvoltages for automated restoration planning. IEEE Trans Power Del
transient recovery voltage rates of rise of transformer secondary faults. IEEE 2002;17(4):1121–7.
Trans Power Del 1995;10(1):266–73. [17] Wang W, Chen S, Yang P. Effects of current-limiting inductor on power
[6] Montillet GF, Dufournet D. Transient recovery voltages requirements for frequency overvoltages in transmission line. Power Syst Technol
system source fault interrupting by small generator circuit breakers. IEEE 2010;34(3):193–6.
Trans Power Del 2002;17(2):474–8.