Guideline-04 Binder Spread Rate
Guideline-04 Binder Spread Rate
1 SCOPE 3 PROCEDURE
This test method sets out the procedure for 3.1 Load Cells
determining the spread rate of a binder for an
insitu stabilised pavement using either the The operator shall take an initial reading of the
calibrated load cells on the spreader, or three load cell at the commencement of spreading.
trays or a mat placed on the surface prior to At the end of the spread run a final reading of
spreading. This procedure is only applicable the load cell shall be taken. The length of run
where the binder is spread by means of a shall also be determined by the apparatus
mechanical spreader and the spread rate is noted in Section 2.
specified in kg/m2.
The width of the auger of the spreader will be
The number of samples taken per day or taken as the width of the binder spread.
project size is determined by the Project
Manager and set in the contract documents, or 3.2 Trays
otherwise, by the contractor’s quality system
manual. Place the metal trays on the pavement to be
stabilised with its long side parallel to the edge
When using lime the design spread rate must of the pavement. Ensure that the wheels of
be adjusted to allow for the equivalent calcium the mechanical spreader will not touch the
oxide content in the lime. trays.
The Association is a non-profit organisation sponsored by organisations involved in the stabilisation and road recycling
industry in Australia whose purpose is to provide information on the use and practice of pavement stabilisation. This
Guide is distributed by the Association for that purpose. Since the information provided is intended for general guidance
only and in no way replaces the services of professionals on particular projects, no legal liability can be accepted by the
Association for its use.
Page 1 of 2
4 CALCULATION OF SPREAD RATE 5 REPORTING
FROM SAMPLE
Report the spread rate of the binder to the
4.1 Load Cell nearest 0.1 kg/m2 and unless otherwise
specified, it should be within ±10% of the
Spread rate (kg/m2) of the binder is calculated target specified rate.
by the following equation:
Spread rate (kg/m2) of the binder is equal to For further information, please contact the
the weight of binder retained (kg) on the mat Secretary, AustStab, PO Box 1889, North Sydney
over area of mat (m2). 2059 or Email: [email protected]
Table 1 The binder spread rate for various compacted pavement depths, binder content and
pavement soil density.
Page 2 of 2