GROUP-10-PROJECT-MANAGEMENT
GROUP-10-PROJECT-MANAGEMENT
PROJECT MANAGEMENT
1.1 INTRODUCTION
Project management is fundamentally about responsibility, with the project manager
(PM) ultimately accountable for all aspects of a project, regardless of team dynamics or
challenges. This role is both challenging and rewarding.
Combining art and science, project management entails working with people and
managing data to balance project duration and cost. Projects are characterized by their
unique or non-repetitive objectives, differentiating them from routine processes. This text
broadly defines "project" to include various applications of critical path methods and network
planning techniques developed since the late 1950s.
While projects may involve routine procedures, such as accounting closures, network
planning techniques are generally used for unique, one-time efforts that require the PM's
tailored planning and judgment. Throughout a project, the PM must continuously adjust
plans and schedules to address progress, delays, or technical issues, ensuring the project
achieves its goals.
Importance
Key Components
……………
1.3 DEFINING THE PROJECT
Project Manager
In charge of a single small project can plan and schedule the project tasks without
much formal planning and information. However, when the project manager must manage
several small projects or a large complex project, a threshold is quickly reached in which the
project manager can no longer cope with the detail.
PROJECT SCOPE
- is a definition of the end result or mission of your project—a product or service for
your client/customer. Also, its definition is a document that will be published and used
by the project owner and project participants for planning and measuring project
success
PRIMARY PURPOSE
- The primary purpose is to define as clearly as possible the deliverable(s) for the end
user and to focus project plans.
THE SCOPE
- The scope should be developed under the direction of the project manager and
customer. The project manager is responsible for seeing that there is agreement with
the owner on project objectives, deliverables at each stage of the project, technical
requirements, and so forth.
- It describes what you expect to deliver to your customer when the project is
complete. Your project scope should define the results to be achieved in specific,
tangible, and measurable terms.
Project Objective
- The first step of project scope definition is to define the overall objective to meet your
customer’s need(s).
Deliverables
- The next step is to define major deliverables—the expected outputs over the life of
the project.
Milestones
Technical Requirements
- More frequently than not, a product or service will have technical requirements to
ensure proper performance.
- The limits of scope should be defined. Failure to do so can lead to false expectations
and to expending resources and time on the wrong problem. Exclusions further
define the boundary of the project by stating what is not included.
- Completion of the scope checklist ends with a review with your customer—internal or
external. The main concern here is the understanding and agreement of
expectations.
Quality and the ultimate success of a project are traditionally defined as meeting
and/or exceeding the expectations of the customer and/or upper management in terms of
cost (budget), time (schedule), and performance (scope) of the project
Is to manage the trade-offs among time, cost, and performance. To do so, project
managers must define and understand the nature of the priorities of the project.
One technique found in practice that is useful for this purpose is completing a priority matrix
for the project to identify which criterion is constrained, which should be enhanced, and
which can be accepted:
CONSTRAIN
The original parameter is fixed. The project must meet the completion date, specifications
and scope of the project, or budget.
ENHANCE
In the case of time and cost, this usually means taking advantage of opportunities to either
reduce costs or shorten the schedule. Conversely, with regard to performance, enhancing
means adding value to the project.
ACCEPT
For which criterion is it tolerable not to meet the original parameters? When trade-
offs have to be made, is it permissible for the schedule to slip, to reduce the scope
and performance of the project, or to go over budget?
In Summary
- Developing a decision priority matrix for a project before the project begins is a useful
exercise. It provides a forum for clearly establishing priorities with customers and top
management so as to create shared expectations and avoid misunderstandings. The
priority information is essential to the planning process, where adjustments can be
made in the scope, schedule, and budget allocation. Finally, the matrix is useful
midway in the project for approaching a problem that must be solved.
- Once the scope and deliverables have been identified, the work of the project can be
successively subdivided into smaller and smaller work elements. The outcome of this
hierarchical process is called the work breakdown structure (WBS)
USE OF WBS
- Helps to assure project managers that all products and work elements are identified,
to integrate the project with the current organization, and to establish a basis for
control. Basically, the WBS is an outline of the project with different levels of detail.
- The WBS defines all the elements of the project in a hierarchical framework and
establishes their relationships to the project end item(s). It also, provides
management with information appropriate to each level.
- The WBS can also be used to define communication channels and assist in
understanding and coordinating many parts of the project. The structure shows the
work and organizational units responsible and suggests where written
communication should be directed. Problems can be quickly addressed and
coordinated because the structure integrates work and responsibility.
WBS DEVELOPMENT
The distinction between a work breakdown sub deliverable and a work package lies in their
scope, duration, and resource consumption. A work breakdown sub deliverable
encompasses outcomes from multiple work packages across different departments, lacking
its own duration or direct resource consumption, with its duration inferred from underlying
work packages. In contrast, a work package represents a specific, self-contained unit of
work within the project, with defined duration and resource requirements. While work
breakdown sub deliverables are utilized for higher-level project planning and status
reporting, work packages serve as the fundamental units for planning, scheduling, and
controlling project activities, providing detailed tasks to achieve project objectives.
The Work Breakdown Structure (WBS) serves to connect organizational units responsible for
the work, leading to the creation of the Organization Breakdown Structure (OBS). The OBS
illustrates how the organization is structured to carry outwork responsibilities. Its purposes
include summarizing organization unit performance, identifying units responsible for work
packages, and linking units to cost control accounts. The OBS outlines organization sub
deliverables hierarchically, often using traditional organization structures. Even in
team-based projects, breaking down the team structure is necessary for assigning
responsibilities for budgets, time, and technical performance. Integration of WBS and OBS is
a major strength, creating project control points where work and responsibility intersect. This
intersection serves as a cost account for project management control. Progress can be
tracked vertically on deliverables and horizontally by organization responsibility during
project execution.
Responsibility Matrices
More complex RMs not only identify individual responsibilities but also clarify critical
interfaces between units and individuals that require coordination.
Responsibility matrices provide a means for all participants in a project to view their
responsibilities and agree on their assignments. They also help clarify the extent or type of
authority exercised by each participant in performing an activity in which two or more parties
have overlapping involvement. By using an RM and by defining authority, responsibility, and
communications within its framework, the relationship between different organizational units
and the work content of the project is made clear.
1. STAKEHOLDER ANALYSIS.
- Identify the target groups. Typical groups could be the customer, sponsor, project
team, project office, or anyone who needs project information to make decisions
and/or contribute to project progress.
2. INFORMATION NEEDS.
3. STAKEHOLDER ANALYSIS.
- When the information needs are identified, the next step is to determine the sources
of information. That is, where does the information reside? How will it be collected?
4. DISSEMINATION MODES.
- In today’s world, traditional status report meetings are being supplemented by email,
teleconferencing, Lotus Notes, SharePoint, and a variety of database sharing
programs to circulate information. In particular, many companies are using the Web
to create a “virtual project office” to store project information. Project management
software feeds information directly to the Web site so that different people have
immediate access to relevant project information. In some cases, appropriate
information is routed automatically to key stakeholders. Backup paper hardcopy to
specific stakeholders is still critical for many project changes and action items.
Developing a project plan involves systematically defining the actions and materials
required to accomplish particular project goals. Defining the project's goals, deliverables, and
scope comes first. Setting deadlines, designating responsibilities, identifying stakeholders,
and creating milestones are important components. A well-crafted plan also takes into
account dependencies and possible hazards, makes efficient use of resources, and
guarantees open lines of communication. To maintain the project on schedule and flexible
throughout, ongoing monitoring and modification are crucial. In the end, a thorough project
plan acts as a road map, directing the team toward the successful completion of the project
while controlling variables like scope, cost, and time.
1. Gantt Chart
● As a project management tool, a Gantt chart shows the amount of work that
has been finished over time in comparison to the amount of time that was
originally scheduled. Gantt charts are currently an industry standard for
tracking task interdependencies and time. Gantt charts are a crucial tool for
displaying the various stages, tasks, and resources associated with project
management.
The Hoover Dam and the interstate highway system are two examples of the
massive building projects that Gantt charts used to manage, revolutionizing project
management. Gantt charts were originally handwritten on paper, but as computers
proliferated in the 1980s, they grew more intricate and sophisticated. Gantt charts remain
one of the most popular project management tools available today.
The three main components of CPM are determining which activities in the project
timeline are the most crucial, figuring out task dependencies, and estimating task durations.
CPM is becoming widely used in project planning and task prioritization. It assists you in
decomposing intricate projects into manageable tasks and improving your comprehension of
the project’s overall flexibility.
PERT enables project managers to precisely forecast project completion time, costs,
and resource usage, it is helpful in project planning. Project managers can also detect
possible risks and create plans to lessen them with PERT. Project managers may guarantee
that their projects are finished on schedule and under budget by utilizing PERT.
Every task is given a unique identification by a WBS, which then arranges them in a
hierarchical framework that illustrates the connections between each task and the
deliverables that are tied to it. A work breakdown structure (WBS) serves three primary
purposes: it makes the project scope clearly understood, lists all the tasks that must be
completed, and facilitates efficient project planning and management.
5. Project Documentation
● Project scope, timetable, and risk analysis are all included in the project
documentation that is developed during the project lifetime. Project
documentation is more beneficial. Comprehension and improved risk
evaluation of the undertaking.
There are various uses for project documentation, including risk, cost, and planning
management. Additionally, because they lay the groundwork for the subsequent phase,
some project documents need to be prepared during a specified project phase. For instance,
before the project execution phase can start, the project management strategy needs to be
made.
3. Outline Deliverables
In order to accomplish the overall objectives of your project, specify clear
deliverables that convert the vision into manageable tasks. To track progress and
ensure responsibility, consolidate these deliverables using a Trello board or
equivalent platform, giving each one its own card. This method breaks down the
larger project objectives into tiny, achievable tasks, which not only keeps the project
on track but also promotes an organized path towards accomplishing them.
the team’s ability to deliver successfully and strengthen the robustness of the
strategy by keeping lines of communication open and being willing to make
adjustments and refinements.
Risk is any possible occurrence that could have an impact on your project, either
positively or negatively. Identifying and responding to these events either in advance of or
during their occurrence is the practice of risk management. Risk can manifest itself in a
variety of ways, including illness among employees, bad weather, unforeseen expenses, and
delays in transit. All projects involve some level of risk. Therefore, one of the most crucial
abilities that project managers should possess is the capacity to guide a project through risk.
Project risks can affect the time and resources required to bring a project to
completion. Risks can be internal (within the control of the project team) or external (outside
of the project team's control. Note the following types of risks and examples:
● Financial risks such as rising costs, inaccurate budget forecasts, increases in labor
and materials, low sales, and challenges in securing funding.
● Performance risks result from team members' missed deadlines, delays, undefined
goals, and KPIs, using insufficient or outdated market research, and scope creep
(when initial goals expand or shift away from a project’s original intentions).
● External risks occur outside of the control of the project team, such as changing
laws and regulations, market volatility, inclement weather, vendors' missed deadlines,
labor strikes, civil unrest, vandalism or damage, and supply chain issues.
● Positive risks (opportunities) are unexpected but have a positive effect on your
project, such as finishing tasks earlier than expected or under budget, outperforming
original goals, becoming more efficient with a new tool, or benefitting from a policy
change
In order to ensure that projects are completed successfully, it is critical that you
comprehend standard risk management procedures and risk reduction techniques. You may
prepare for and anticipate hazards with the aid of the risk management process, and you will
have the means to deal with them should they arise thanks to mitigation techniques.
In order to ensure that projects are completed successfully, it is critical that you
comprehend standard risk management procedures and risk reduction techniques. You may
prepare for and anticipate hazards with the aid of the risk management process, and you will
have the means to deal with them should they arise thanks to mitigation techniques.
1. IDENTIFY RISK
The first step to getting a grasp on potential risks is to know what they are. In this step, you’ll
identify individual risks that might affect your project by making a list (or spreadsheet) of
risks that might arise. Examples of common project risks include implementing a new
technology program for the project, having a poorly defined project objective or deliverable,
and not having adequate measures to protect the health and safety of project team
members.
Use your own project management expertise and consult similar past projects to see what
challenges you might expect. You’ll also want to have stakeholders, team members, and
subject matter experts generate ideas with you; they may have insight into the field that
you’ve overlooked
In the risk analysis stage, you’ll explore the probability of each risk occurring, as well
as the potential impact each risk will have on your project. You could begin putting this list of
risks in a risk register—a chart that lays out each risk, followed by information like priority
level and mitigation plans. You can record both qualitative and quantitative information.
In this stage, you’ll assign priority to risks by using the probability and impact of each
risk to determine their risk levels. This means assigning each risk a high, medium, or low
priority based on the factors you’ve determined. Evaluating your risks gives your team the
chance to see where to focus their energy in mitigating risk.
4. MITIGATE RISK
Come up with a plan to mitigate each risk and record these plans in your risk register. What
is risk mitigation? There are four common ways to mitigate risks, including avoiding them,
accepting them, reducing them, and transferring them. Deciding which approach to use for
each risk isn’t an exact science, and you’ll have to use your judgment and expertise to
determine which is best.
Avoid: Not all risks can be avoided, but it can be a good idea to do so when you can. Avoid a
risk if there is a high chance that a risk will happen. Has a partner vendor gained a
reputation for providing low-quality work? Try to find a different one. Are you event-planning
during the rainy season? Move the event indoors, or to a sunnier season.
Accept: Accepting risks can make sense if they have a low chance of happening and will
have low impact on your project. Ultimately if the risk does happen, it shouldn’t derail your
project. Say you’ve ordered sunflower arrangements for a wedding reception, but the florist
says there’s a small chance they won’t have enough and will have to replace some with
tulips. Since the probability of risk is low and having tulips instead of sunflowers won’t upend
the wedding, you might accept the risk instead of troubling yourself to find a new florist.
Reduce: Reducing risk means changing elements in your plan to minimize the risk’s
probability of happening or potential impact on your project. Medium and high risks are good
candidates to reduce. Reducing usually requires some effort or investment. For example, a
project manager could hire new team members if the team is falling behind on work. This
might also mean including risk-reduction tactics in your project plan. Time buffers for
complex or time-sensitive tasks can allow you some flexibility if work starts to fall behind.
Having a contingency budget can help absorb unexpected costs if they arise.
Transfer: Transferring risks entails shifting the risk to another party outside of your project.
This can mean obtaining an insurance policy, or outsourcing parts of the work to a third
party. The risk might still occur, but the direct impact on your project will be absorbed by
somebody outside of your project.
5. MONITOR RISK
In the last step, set up a process to monitor each risk as your project begins.
Assigning team members to keep an eye on specific risks and mitigate them ensures you’ll
have a constant sense of where the risks are and how likely they are to happen, so you'll be
ready to tackle them if they occur.
Tools can provide you with structure for your team’s thoughts and efforts, and serve
as a point of reference throughout a project. Here are a few you might consider using in your
risk management process.
Risk management plan: A risk management plan is generally a living document that
contains all information related to risk in your project. This can contain an executive
summary, your risk register, mitigation plans, risk owners, and any other information
pertaining to risk. Project managers may update the document as the project progresses and
needs fluctuate.
Risk register: A risk register is a chart that contains all the risks associated with a project,
as well as their priority levels, mitigation plans, and other important details. A risk register
might also be called a risk matrix. You can find project management software that can help
you compile risk registers, or else create your own in a spreadsheet.
The use of scheduling methods in engineering operations (whether some form of bar
chart or network analysis) is covered by many books, for example, Wild (1984). However,
with either batch or continuous production the scheduling requirements are somewhat
simpler. By definition a project is not a recurrent activity, thus the time and cost associated
with each activity is an estimate, and consequently there is an important need for information
that monitors the progress of the project. Books on project management such as Lock
(1977) and Harrison (1985) give comprehensive treatments of scheduling techniques, but
with less emphasis on the project monitoring aspects, and the integration of financial control.
Before dealing with specific techniques it is worth remembering that there are two extreme
types of project, though most fall somewhere between the two:
BAR CHARTS - Bar charts are long established and easy both to construct and to interpret,
yet they are also very versatile. With a bar chart, each activity has a separate bar, the length
of which corresponds to the activity duration. The horizontal position of the bar also identifies
the start and finish times.
COMPUTER BASED SYSTEMS - The computer program will also be able to check the logic
in the network; it will be able to identify activities not connected to two events, more than one
activity connected to the same events, loops and dangles. Errors that are plausible cannot of
course be identified by a computer.
The bill of quantities is a document prepared by the cost consultant that provides project
specific measured quantities of the items of work identified by the drawings and
specifications in the tender documentation. The quantities may be measured in number,
length, area, volume, weight or time. Preparing a bill of quantities requires that the design is
complete and a specification has been prepared.
The Bill of Quantities (BOQ) is a comprehensive document that provides a detailed list of
materials, quantities, and associated costs required for a construction project. It serves as a
tendering and procurement tool, enabling accurate estimation of project costs and facilitating
the bidding process.
Components of BOQ
1.) Item Description: A clear and concise description of each item or activity involved in
the project.
2.) Unit of Measurement: The specific unit (e.g., meters, kilograms, hours) used to
measure the quantities of each item.
3.) Quantity: The estimated or measured quantity required for each item.
4.) Rate: The unit price or cost per quantity of each item.
5.) Amount: The calculated cost for each item (quantity multiplied by the rate).
Preparing a BOQ
Before we get into the step-by-step method of drafting a bill of quantities, it’s imperative that
we learn about the different types of bills of quantities or we would rather term them as
different stages for a bill of quantities.
°Preliminary Bill of Quantities (PBQ) – This bill estimates the initial project costs,
covering concepts like site preparation and early-stage construction activities.
°Revised Bill of Quantities (RBQ) – RBQs are updated versions of the original
BoQ, reflecting changes in the project scope or design.
°Firm Bill of Quantities (FBQ) - A firm bill of quantities (FBQ) is a finalised and
agreed-upon version of the BoQ, used for tendering and contract execution.
°Review the project documents thoroughly and itemise all materials and labour
required.Categorise items as either materials or labour and provide concise, yet
detailed descriptions for clarity.
°Based on the project specifications, start with quantifying all the items required in
the projects and their associated costs. Calculate the total costs involved. This will
also help you calculate the total man hours required to complete the project.
°Review and cross-check your BoQ thoroughly to ensure accuracy and consistency.
This is a crucial step to avoid any errors. It’s best practice to get more eyes to review
your bill of quantities, leaving zero space for any discrepancies.
°Ensure that your Bill of Quantities adheres to the relevant standards and guidelines
in the UK, such as the New Rules of Measurement (NRM) or any specific industry
standards applicable to your project.
°Organise your BoQ in a clear and easily understandable format. Include a cover
page with project details and any terms and conditions if required.
Advantages of BOQ
Now that we have explored the definition let’s look at the benefits and importance of a bill of
quantities.
°As mentioned previously, one of the main benefits and purposes of a Bill of
Quantities is to ensure an accurate and fair bidding process. Having this as a
standard document ensures that competing contractors price the project on the same
basis, thus reducing the risk of ambiguity through omissions or misunderstandings.
Plus, it saves the owner and their team hours analyzing bids, as comparisons are
way easier if everyone bids based on the same quantities.
°A BoQ provides a comprehensive overview of works, which makes it the perfect tool
to ensure effective communication, accountability, and transparency between the
owner and the contractor. A clear layout of tasks and costs organized in a defined
timeline reduces the chance of mistakes or misunderstandings, and it saves both
parties time by avoiding unnecessary meetings.
°A well-constructed BoQ provides project owners and contractors with accurate cost
control. A detailed overview of items and their prices can help identify the most costly
items and look for alternatives to ensure the budget is respected. During
construction, the document gives visibility into upcoming expenses to help with
resource management.
°Once the BoQ is priced, it serves as an invaluable source of cost data. Quantity
surveyors or cost professionals can use a priced BoQ to provide professional advice
about the potential costs of future building projects. The cost data from a priced BoQ
can be retrieved and stored to be analyzed in different ways and applied for cost
estimation or benchmarking purposes, among other things.
Importance of BOQ
°It helps all the contractors to compare the items and materials price for better job
opportunities.
°Bill of quantities provides a basic idea about a project by judging its quantities to
tender.
°It provides the best basis for evaluation of the project, its tender comparison, and
contract comparison.
What is interpretation?
It is a specific interpretation of a substantial work that projects or draws on another's
expertise to construct something; it is created through design movements that are based on
task-specific knowledge, combine its parts to create a solid foundation by achieving distinct
characteristics their connection to one another.
Architectural
It offers the potential to make the process of converting paper-based or old-fashioned
CADD drawings that have been preserved into technologically intelligent model-based
CADD representations with much more features easier. Different types of drawings are used
in architecture at different stages of the design process, from unstructured sketches to
schematic designs to more formally established, greater representations that are used to
communicate construction information to contractors.
Structural
Seeing several chosen inline and crossline sections may be the initial phase in the
session in getting a knowledge of the deeper geology in the region. The structural pattern
may also need to be ascertained in other orientations, such as vertical portions following a
dominating dip direction.
● Architectural Drawings
Architectural drawings, which act as a visual aid for construction, show the structure
and design of buildings, including sections, floor plans, elevations, and architectural
details.
● Structural Drawings
Structural drawings depict the structure's framework along with its support systems,
elaborating on elements like foundations, beams, and columns that are important in
securing structural integrity and safety.
● Electrical Drawings
In Electrical drawings, it defines parts including wire, outlets, switches, and lighting
fixtures to enable correct installation and operation. They also show the architecture
and connections of electrical systems within building structures.
● Civil Engineering Drawings
Civil engineering drawings provide the layout and construction requirements for
roads, bridges, dams, and other civil works. They also cover different components of
infrastructure projects, such as site plans, grading, drainage, and utilities.
● Mechanical Drawings
Mechanical drawings provide instructions for installation, maintenance, and functions
by showing the layout and design of mechanical systems and parts, such as
equipment, piping, and HVAC (heating, ventilation, and air conditioning) systems.
When interpreting engineering plans, it's important to understand the essential components
and use certain methods to comprehend and carry them out efficiently. Learning about
symbols, measurements, scales, and annotations on the drawings are essential components
as they provide significant information on the project's design and specifications.
References:
APA format
Westland, Jason. “Project Documentation: 15 Essential Project Documents.”
ProjectManager, 5 Aug. 2022,
https://www.projectmanager.com/blog/great-project-documentation.
“Work Breakdown Structure.” Workbreakdownstructure.Com,
https://www.workbreakdownstructure.com. Accessed 14 June 2024.
“What Is Program Evaluation Review Technique (PERT)? – Shopify Philippines.” Shopify,
https://www.shopify.com/ph/blog/what-is-program-evaluation-review-technique. Accessed 14
June 2024.
Atlassian. “Gantt Charts.” Atlassian,
https://www.atlassian.com/agile/project-management/gantt-chart. Accessed 14 June 2024.
Asana. “Use Critical Path Method (CPM) for Project Management [2024] • Asana.” Asana,
https://asana.com/resources/critical-path-method. Accessed 14 June 2024.
deBara, Deanna. “How to Write an Effective Project Plan in 6 Simple Steps.” Work Life by
Atlassian, 20 July 2023,
https://www.atlassian.com/blog/project-management/write-an-effective-project-plan.
Benator, B. (2003). Project Management & Leadership Skills for Engineering & Construction
Projects. https://doi.org/10.1201/9781482276008