CIVIL HANDOVER CHECKLIST

This document is a checklist for the takeover of a construction site from the client, PWD, Govt. of Assam, after the completion of civil foundation works. It includes records to verify, completion of civil activities, and site access conditions necessary for TATA Steel Nest-In to proceed with further construction. The checklist is divided into sections for civil work, erection work, and site area/access, ensuring all criteria are met before the handover.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views

CIVIL HANDOVER CHECKLIST

This document is a checklist for the takeover of a construction site from the client, PWD, Govt. of Assam, after the completion of civil foundation works. It includes records to verify, completion of civil activities, and site access conditions necessary for TATA Steel Nest-In to proceed with further construction. The checklist is divided into sections for civil work, erection work, and site area/access, ensuring all criteria are met before the handover.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Doc. No.

-
TSL/S&S/NI/EXE/CL-021 TATA Steel Nest-In
Rev. No. Effect from: CHECKLIST Takeover of site from Client after
R1 01-March-24 civil foundation works
Project Name/No.:
Client Name: PWD, Govt. of Assam Location:

Civil Contractor: Date:

C Records YES NO REMARKS


MTCs of Reinforcement Steel, Cement, and other
1 materials.

Concrete Mix Design Report along with Batch


2 Sheet.

28 Days Concrete Cube Compressive Strength


3 Record.

Survey Report of alignment and level of anchor


4 bolts.

5 GTI Report.

Civil Work Erection Work


SL No Activity/Location (Client) (TATA Steel Nest In)

Start Date End Date Start Date End Date


1 Foundation Takeover for Erection
2 Foundation Handover for Brick work
Foundation Takeover for Internal
3
work
4 Takeover after final Civil scope Work
5 Electricity Connection to LT Panel

REMARKS :-

Civil Contractor TATA Steel Nest-In (Client)

Signature &
Date

Name
Designation
Page 3 of 3
Doc. No.-
TSL/S&S/NI/EXE/CL-021 TATA Steel Nest-In
Rev. No. Effect from: CHECKLIST Takeover of site from Client after
R1 01-March-24 civil foundation works
Project Name/No.:
Client Name: PWD, Govt. of Assam Location:

Civil Contractor: Date:

SL No. DESCRIPTION YES NO REMARKS

B WORK COMPLETION from CLIENT

Check whether all the Pre-handover civil activities as per


1 the agreed schedule of works are completed and if any
activity pending or under progress please mention?

Check whether the civil works is done as per approved


2
drawing without any deviation.
Check for any undulation in level in Grade Slab
3 before taking over.

Check for any damages to concrete structure before


4 taking over.

Check for any damage to the anchor bolt or


5 misalignment of anchor bolt before taking over.

Check for the start/completion of any other activities,


such as Masonry Works, which is/are not
6
mentioned/agreed to be started before partial taking
over?
7 Check for Door opening as per the GFC drawing?

8 Check for Window openings as per the GFC drawing?


Check for Rolling Shutter opening as per the GFC
9
drawing?
Check for the removal of all Civil construction materials,
10 P&Ms and Tools and Tackles from the site access area/
which can hamper Nest-

Check for the Electrical Main Line supplied transformer to


11
LT Panel at site?

12 Check for the Windows MS Grill install at site?

Civil Contractor TATA Steel Nest-In (Client)

Signature &
Date

Name
Designation
Page 2 of 3
Doc. No.-
TSL/S&S/NI/EXE/CL-021 TATA Steel Nest-In
Rev. No. Effect from: CHECKLIST Takeover of site from Client after
R1 01-March-24 civil foundation works
Project Name/No.:
Client Name: PWD, Govt. of Assam Location:

Civil Contractor: Date:

SL No. DESCRIPTION YES NO REMARKS

A SITE AREA and ACCESS

1 Check for access to the site for P&Ms and Vehicles?

2 Check for levelness of the site?

Check for any Vegetation, Trees, Over-head Electricity


3 and other utility Lines, Parts of existing nearby structures
falling in line with the Steel Structure?

Check for area for the unloading and storage of Nest-In


4
Materials?

Check for ramp access for the entry to the Floor level of
6
Building?

Check for the accessibility of P&Ms such as Hydra Crane


7
around the Area for material movement?

Check for space for hydra /equipment movement around


8
building

Check for free approach and erection area for


9
assembly/fit up?

10 Check for Construction Electrical power availability?

Civil Contractor TATA Steel Nest-In (Client)

Signature &
Date

Name
Designation