Geo Surveying TECHNICAL REQUIREMENT-2025.2.14
Geo Surveying TECHNICAL REQUIREMENT-2025.2.14
2025.02.14
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
Table of Contents
1 SUMMARY .......................................................................................................................................... 2
1.1 GENERAL............................................................................................................................................... 2
1.2 SCOPE AND PURPOSE OF WORKS ............................................................................................... 2
2 TECHNICAL SPECIFICATIONS....................................................................................................... 3
3 SAMPLING ......................................................................................................................................... 5
3.1 SAMPLES ............................................................................................................................................... 5
3.2 PRESERVATION AND STORAGE OF SAMPLES .......................................................................... 5
3.3 SUBMISSION OF SAMPLES .............................................................................................................. 6
4 IN SITU FIELD TEST ......................................................................................................................... 6
4.1 STANDARD PENETRATION TESTS (SPT) ..................................................................................... 6
4.2 RESISTIVITY TEST OF SOIL ............................................................................................................. 7
4.3 DYNAMIC PENETRATION TEST (DPT) ........................................................................................... 9
4.4 CONE PENETRATION TEST (CPT) .................................................................................................. 9
5 LABORATORY TESTING OF SAMPLES ..................................................................................... 10
5.1 TESTS ................................................................................................................................................... 10
5.2 ON SAMPLES..................................................................................................................................... 10
5.3 LABORATORY REPORT ................................................................................................................... 12
6 RECORDS AND REPORTS ............................................................................................................ 12
1
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
1 SUMMARY
1.1 General
Through engineering geological mapping, drilling, pit prospecting, geophysical
testing, indoor and in-situ testing, etc., the stability and suitability of the proposed site,
topography, stratigraphic lithology, geological structure, karst and hydrogeological
conditions, poor Physical geological effects, earthquakes and earthquake effects, etc.
Identify the basic geotechnical conditions and various geotechnical property index
values. In view of the existing engineering geological problems, suggestions for
foundation design, foundation treatment and prevention are proposed.
1.2 Scope and Purpose of Works
The project includes two parts: photovoltaic area and booster station.
2
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
Perform SPT test interval 1.0 m within 10m, and 1.5m below 10m, if SPT is
not applicable, DPT test with interval 2.0 m could adopted. To identify the
subsurface conditions for the foundation and select the appropriate foundation
type.
Each soil layer in each boreholes shall have 1 samples. the quantity may
vary according to the site condition.
2 TECHNICAL SPECIFICATIONS
2.1 REFERENCES
The applicable codes and standards shall be EN standards. The work shall
be generally in accordance with the relevant BS 5930 & BS 1377 and general
practices.Where it is not available, an internationally accepted standard will be
used to the approval of Owner.The ASTM standards or codes including but not
limit to the following codes :
a) ASTM standards
2.1 Boring
Following contents shall be suitable for advancing the boreholes in earth
condition and aquatic condition. The stages or vessel shall be used when
advancing boreholes in aquatic condition.
1) Depth of Boring
The number and location of boreholes shown on the Drawing are provisional.
The Employer may vary the quantities and it shall be understood that the variation
shall not affect the Total Contract Price. The depths of boring and drilling may be
varied as directed by the Engineer depending on the results obtained.
a) PV area
The dune leveling area needs to be surveyed after the plant area is leveled
according to layered rolling. Generally, the normal depth of the borehole is 5m, and
the controlled borehole depth is 10m or 3m enter into bedrock;
b) SS area
The dune leveling area needs to be surveyed after the plant area is leveled
according to layered rolling. Generally, the normal depth of the borehole is 10m,
and the controlled borehole depth is 15m or 3m enter into bedrock ;
3
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
2) Drilling Method
The methods and equipment used shall be such that;
a) The soils encountered and the levels of strata boundaries can be accurately
identified;
c) All in-situ tests referred to in the Specifications can be undertaken and field
installations incorporated at any depth in the borehole.
Drilling shall be carried out in such a manner and using such sizes of bits
including any required modification to the drill bit, such that the maximum amount
of core is recovered. This requires close surveillance of drilling fluid, drilling
pressures, lengths of runs and all other factors relevant to the nature of the
material being drilled.
The core barrel shall be withdrawn and the core removed as often as may be
necessary to secure the maximum possible amount of core.
The Contractor shall in general use no drilling lubricants in the borehole other
than clean water, air or air with an approved drilling foam additive. Additives shall
only be used in the flushing medium upon approval by the Engineer.
2.2 Record of Drilling Equipment
On the daily record sheet the driller shall record the type of core barrel used
and the type of coring bit used. This information shall be recorded for each core
run.
2.3 Drilling Observations and Blasting
It shall be the Contractor's responsibility when boulders or other obstacles are
encountered to advance the boreholes through or past such obstacles or, if
directed by the Engineer, to core the obstacles to determine its size and character.
Blasting shall be used only as approved by the Engineer and only after it has
been shown that the obstruction cannot be removed by conventional methods.
Before blasting, the casing shall be withdrawn a distance sufficient to avoid
damage.
The Contractor shall obtain all necessary permits and shall comply with all
laws, rules, regulations and ordinances governing blasting operations in the locality
of the work.
The Contractor shall exercise all necessary precautions and shall be solely
responsible for all damages caused by the blasting.
4
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
5
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
b) Date of sampling;
6
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
as “Refusal”.
Besides the detailed description for the sampling in the penetration, keep
them to do the laboratory analysis.
Standard Penetration Tests shall be carried out in conjunction with the
sampling by split barrel sampler. When obtaining continuous samples, standard
penetration tests shall also be carried out at 1.0m intervals or as directed by the
Engineer. The equipment and method for carrying out the tests shall be as
described in Test 19 - B.S. 1377 : 1975 except that only self tripping hammer of an
approved type shall be used. The maximum resistance required to be measured is
when an execution of 50 blows causes a penetration of 300mm or less.
The value of N as defined in the BS Standard Method shall be reported
together with number of blow counts for each 75 mm penetration of the sampling
tube in bracket. The blow counts for the first 150 mm penetration (the seating drive)
which do not contribute to the value of N shall be included in the bracket. For
example N=42 (2, 3, 6, 7, 10, 19) .
4.2 Resistivity Test of Soil
The electrical resistivity test points are shown in the figure 1 .
a) There are 4 resistivity test points in the PV plant area and 1 in the step-up
substation.
b) The depth when measuring soil resistivity shall be 0.5 m, 1.0 m, 1.5 m, 2.0 m,
3.0m, 5.0 m, 10.0 m, 25m, 40m, 65m, 100m,150m and 200m. Soil resistivity
stratification value of each layer shall be provided.
c) When measuring soil resistivity, it shall be avoided after rain, and it shall be
measured after three consecutive sunny days.
d) The soil resistivity shall be measured according to specifical requirement of
IEEE Std 81:2012.
e) The measuring method is symmetrical quadrupole electric sounding of direct
current exploration. Simultaneous movement device is adopted (that is,
simultaneous movement of the power supply pole distance and the measuring pole
distance), and the test principle is shown in figure 2. The depth of current electrode
is 0.2m, and the depth of voltage electrode is 0.1m.
7
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
8
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
Thermal Volumetric
Depth Thermal Ground
No Diffusion Heat
(m) Conductivity Temperature
(a.10) Capacity(cf.10)
0.5
1.0
1 1.5
2
2.5
…… …… …… …… …… ……
9
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
10
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
2) Strength Properties
Strength properties shall be determined by compression test, point load test, etc.
3) Weatherability
As an indication of the weatherability of the rock the aggregate durability index
shall be determined.
It is expressed as a percentage and can vary from 0% for a rock which
disintegrates completely, up to 100% for rock in which no disintegration occurs.
4) Other Properties
In addition to establishing the general properties, it may be necessary also to
determine the following characteristics:
•The strength characteristics of the rock in its various degrees of weathering just
as it exists on the site (the relationship of the stress, cohesion, angle of internal
11
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
Site Conditions:
Site geology, General description
Potential geology hazards
Site surface description
Description of aboveground obstructions
Subsurface Conditions:
Stratigraphy distribution
General description of subsurface material properties
Groundwater elevations and expected variations;
Description of underground obstructions encountered or otherwise identified
Corrosion potential for underground utilities
Chemical attack potential for concrete ,steel and underground utilities
12
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
Seismic Analysis:
Seismicity based on seismic risk map
Soil profile type and site coefficients
Site classification
Seismicity parameters based on ASCE 7-05 and local codes
For each borehole, trial pit, as applicable, logs drawn to vertical scale, showing:
For boreholes:
Borehole diameter, stability, casing and drilling fluid used
Type and diameter of bit used
Depth to and elevation of each change in stratum
Geotechnical description of each stratum and geological formation
Legend of stratigraphy, using standard symbols
Label, depth and details of samples
Label, depth details and results of all in situ tests
Groundwater observations
Details of backfilling or instrumentation installation, in particular
13
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
interpretation, all original data must be supplied form in a defined format to the
approval of Contractor.
The Contractor have acknowledged and confirmed the sufficiency of above Final
Report in compliance with the applicable regulations of Local codes. Therefore, the
Contractor shall be liable to submit the Final Report to the authorized Government
Authorities and related consult agent for approval at his own cost as per the Time
Schedule.
7 SITE SERVICE
The Site Service include the following:
7.1 Foundation soil checking
The contractor shall be responsible for the foundation soil checking. And the
Employer will send a notice to the contractor 1 days before the checking time, and
the contractor shall dispatch his technician to the site in time.
7.2 Cooperation with Technical Supervision by local authorities
The Contractor shall cooperate with technical supervision by local authorities
related to his work. The Contractor shall dispatch his technician to the site in time
once requested by the Employer.
14
CONTRACT FOR TECHNICAL REQUIREMENT SOIL INVESTINGATION
15