Network Analysis Detail
Network Analysis Detail
Network analysis helps management to minimize the total cost and total
maintenance time. With the use of network analysis cost of production can be
minimized through reducing the maintenance time.
Network analysis ensures the effective utilization of limited resources. It also
ensures the optimal use of resources and help to control the idle resources so
that project can be effectively executed within the budgeted costs and
scheduled time.
Network analysis facilitates co-ordination among the activities as well the
persons responsible for project.
Time management plays a crucial role in every project. Sometimes available
resources have to be arranged with a view to reduce the total time for the
project rather than reducing the cost of the project. Network analysis helps the
managers to manage activities without any delay.
Network analysis is great tool which helps in planning, scheduling and
controlling the activities of the project.
Network analysis also creates inter-relationship as well as inter-dependence of
various activities of project. It helps in integrating the project planning and this
1
NETWORK ANALYSIS
2
NETWORK ANALYSIS
PERT is helpful to the project manager for taking decisions about these
questions. It is a technique which helps project manager in planning,
scheduling, monitoring, evaluating and controlling large and difficult projects.
In simple words we can say that projects whose time duration of activities is
3
NETWORK ANALYSIS
not exactly known, PERT is used. It depends upon three time estimates of
activities.
The most optimistic time (t o): The minimum time that would be required to
perform the activity if everything goes extremely well, the chance of such an
optimum activity actually takes place is one in hundred.
The most likely time (t m): The length of time that will, in all probability, be
required to perform the job under the given circumstances or normal
circumstances.
The most pessimistic time (t p): This is the longest or maximum probable
time involved if everything that might logically go wrong does actually go
wrong. It includes time for unusual days or unforeseen circumstances. The
chance of its happening might also be one in hundred or very less.
With the help of these above mentioned time estimates i.e. optimistic time,
most likely time, and pessimistic time, average expected time for each activity
would be determined.
First of all, the network of activities is drawn to indicate what activity follows
what.
Then estimation of time to complete each activity is noted on the network.
Estimation of minimum time taken to complete the project.
Identification of critical activities and allocation of resources so that project
can be completed in time.
Calculation of project variability duration and profitability of the project in
given period.
In order to complete project in time closer watch on critical and other
activities.
Advantages of PERT
1. It is very helpful in determine the schedule for a project within time limit.
2. It helps the management to optimum allocation of resources for the project.
4
NETWORK ANALYSIS
Limitations of PERT
Although PERT have many advantages, but it also suffers from certain
limitations. These are:
Example –
Assembling and Erecting the False work for an Elevated Slab will most likely
require 8 days. If all goes well, without interruption, the duration may be cut to
10 days. However, in the practically worst-case scenario, this activity may take 24
days.
Where
Optimistic time= 8 days,
Most likely time = 10 days, and
Pessimistic time = 24 days
PERT weighted average = (8 workdays + 4 X 10 workdays + 24 workdays)/6 =
12 days. Therefore, you’d use 12 days on the network diagram instead of 10
when using PERT for the above example
5
NETWORK ANALYSIS
6
NETWORK ANALYSIS
7
NETWORK ANALYSIS
The critical path, is the overall time, it will take to complete the project. It is
the longest path in time through the network. In other words, the longest path
in the network is called critical path. Identifying the critical path is of great
importance as it determines the duration of entire project. Critical path method
differentiates between the planning and scheduling of the project.
Identification of the Critical Path: Project CP is the longest time path through
the network. The path can be identified by determining the following
parameters for each activity:
Earliest start time for activity (ES): It is the earliest possible time at which the
activity should start if only the ongoing activities are first completed.
Earliest finish time (EF): It is the earliest possible time to finish the activity. It
is equal to the earliest start time for activity plus the time required completing
the activity.
Latest possible finish time for activity (LF): It is the latest time at which the
activity can be completing without any postpone or within the time framework.
8
NETWORK ANALYSIS
Latest possible start time for activity (LS): it is the latest start time for an
activity and equal to the latest finish time minus the time required to complete
the activity.
Slack time: Slack time is the difference between earliest start time for activity
and latest start time for activity, or between earliest finish time for activity and
latest finish time for activity.
From the given data, we can draw the following network diagram:
9
NETWORK ANALYSIS
In this diagram, the jobs have been shown in the form of arrows leading from
one circle to another. In simple words the arrow connecting circles 1 and 2
represents job A and so on. All the activities have been reduced to a network
diagram together with the information as regard to time required for the
completion of different jobs. In this diagram, there are two paths- the first
connects circles 1, 2, 4, and 5 and takes 17 days. The second path connects
circles 1, 2, 3, 4, and 5 and takes 22 days. The longest path, called the critical
path takes 22 days and hence the minimum time required to complete the
project will be 22 days.
So in order to complete the project within scheduled time, attention will have
to be given to this path since any delay in time on any job or activity in this path
will delay the completion of the project. In case the completion time is to be
reduced, steps will have to be taken to reduce the time required for various
activities of this path.
Limitations of CPM
10
NETWORK ANALYSIS
It is presumed in CPM that there is a precise known time that each activity in
the project will take. But in reality it is not happen.
Basically it developed as a static planning model and not as a dynamic
controlling device. So it cannot be used as a dynamic controlling device.
8. Similarities between PERT and CPM: PERT and CPM both are the
networking techniques. Both are the important tools of project
implementation. Below are the similarities between PERT and CPM:
Both PERT and CPM have the same procedure and network diagrams are used
in the both the techniques.
Both PERT and CPM are used to determine the earliest/latest start and finish
times for each activity.
Both PERT and CPM techniques help management to plan, schedule and control
the project.
All significant task and activities are defined in the project by both the
techniques.
The networking principles used in both the techniques is more or less the same.
Although both techniques share some common characteristics, yet there are
some differences between them.
11
NETWORK ANALYSIS
12