0% found this document useful (0 votes)
3 views

Network Analysis Detail

Network analysis is a crucial aspect of project management that aids in the formulation and implementation of projects by optimizing time and resource allocation. Techniques such as PERT and CPM are employed to schedule activities, manage costs, and ensure effective coordination among project tasks. While both methods share similarities, they differ in their application, with PERT focusing on uncertain time estimates and CPM emphasizing precise scheduling for repetitive tasks.

Uploaded by

Anirban Biswas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views

Network Analysis Detail

Network analysis is a crucial aspect of project management that aids in the formulation and implementation of projects by optimizing time and resource allocation. Techniques such as PERT and CPM are employed to schedule activities, manage costs, and ensure effective coordination among project tasks. While both methods share similarities, they differ in their application, with PERT focusing on uncertain time estimates and CPM emphasizing precise scheduling for repetitive tasks.

Uploaded by

Anirban Biswas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

NETWORK ANALYSIS

MEANING AND CONCEPT OF NETWORK ANALYSIS

Project formulation and Project implementations are two essential functions of


project management. Project formulation ensures the scientific selection of a
project whereas project implementation ensures an optimal allocation of time
and resources to the project activities. All project design should have contain
five elements it should systematically formulates and describe each of the basic
elements i.e. inputs, activities, outputs, effects, and impact. Project design
should start with defining the desired impact. So we work from the Top down
i.e. what effects are needed to achieve the desired impact? What outputs are
needed to achieve the desired effects? And so on…
Projects should follow this hierarchy. The lowest level in the hierarchy is inputs
like finances’, raw material, human resources and time. All projects perform
various activities like communication, training, organization, construction and
management. These activities convert inputs into outputs and all the activities
are carried out for the output of goods and services.
Importance of Network Analysis/Network technique: A project has
divided into many small activities and these activities can be analyzed with the
help of network technique to achieve the objectives of the project.

 Network analysis helps management to minimize the total cost and total
maintenance time. With the use of network analysis cost of production can be
minimized through reducing the maintenance time.
 Network analysis ensures the effective utilization of limited resources. It also
ensures the optimal use of resources and help to control the idle resources so
that project can be effectively executed within the budgeted costs and
scheduled time.
 Network analysis facilitates co-ordination among the activities as well the
persons responsible for project.
 Time management plays a crucial role in every project. Sometimes available
resources have to be arranged with a view to reduce the total time for the
project rather than reducing the cost of the project. Network analysis helps the
managers to manage activities without any delay.
 Network analysis is great tool which helps in planning, scheduling and
controlling the activities of the project.
 Network analysis also creates inter-relationship as well as inter-dependence of
various activities of project. It helps in integrating the project planning and this
1
NETWORK ANALYSIS

relationship assists in bringing out the technological inter-dependence of the


various activities.
 Network analysis provides the project formulation team an apparent picture of
the work elements and also sequential relationship of the project.

Classification of Network Techniques: There are number of network


techniques which are used by the various people according to their purpose.
The main techniques are given below:

1. CPM: It is popularly known as Critical Path Method. Critical path method is a


project management tool used to formulate a time frame for a project in order
to determine where potential delays are most likely to take place.
2. PERT: The Programme Evaluation and Review Technique is basically a
scheduling technique. It helps project manager in planning, scheduling,
monitoring, evaluating, and controlling large and complex projects. It is a
probabilistic model and introduces uncertainties in project network.
3. GERT: The Graphical Evaluation and Review Technique is a new technique and
superior over the above mentioned techniques. In this analysis only simulation
can be used.
4. LOB: It is known as Line of Balance technique. Line of balance is a graphical
technique to show the progress achieved during the project with the help of key
events.
5. PERT/Cost: It is an extension of the PERT technique to cover the cost of project.
It is not only helpful to plan the completion of project within a specific time but
also within a specific cost.
6. WASP: It is known as Workshop Analysis Scheduling Programme. This method
is propounded by The British Energy Authority.

2
NETWORK ANALYSIS

PROGRAMME EVALUATION AND REVIEW TECHNIQUE (PERT):

Project Programme Evaluation and Review Technique, which is generally


popular as PERT, is a sophisticated and a fairly new tool used by the
management for planning and control in the case of special project. It is
primarily a scheduling technique. It shows any project or job as a set of
processes of operations called activities which must take place in a certain
sequence. It involves diagrammatic presentation of activities and events
involved in a long term project. The diagrammatic presentation is known as
Network Drawing/technique and these techniques are most commonly used in
project management. PERT was developed in 1958 as a result of collaboration
between the operational research division of the United States Navy and a team
of management consultants known as Boose Allen and Hamilton. It was
developed as a management tool to aid for completing Poloris Ballistic Missile
Project which had 250 prime contractors and over 9000 sub-contractors
engaged in research, development, construction, testing and production of
missiles, guidance system and maintenance system. Since then, it has been
adopted by many enterprises in different industries. So PERT schedules the
sequence of activities to be completed in order to accomplish the project within
a short period of time.

Basic objective of PERT is to control time. The execution of project becomes


very difficult where long times involved in the planning and scheduling of the
project because it involved lot of complexities and inter related activities. So for
the successful implementation of the project, project manager is to take some
important decisions such as estimation of resource requirement, time for each
activity, and maintaining inter-relationship amongst the activities. Thus each
project involves various decisions about:

1. What is the expected completion time of project?


2. What will be the effect of any delay on the activity/ project?
3. What type of additional resources needed if project has to be completed
before scheduled time?
4. What is the probability of completing the project in time?

PERT is helpful to the project manager for taking decisions about these
questions. It is a technique which helps project manager in planning,
scheduling, monitoring, evaluating and controlling large and difficult projects.
In simple words we can say that projects whose time duration of activities is

3
NETWORK ANALYSIS

not exactly known, PERT is used. It depends upon three time estimates of
activities.

In PERT below three estimates of time are used:

 The most optimistic time (t o): The minimum time that would be required to
perform the activity if everything goes extremely well, the chance of such an
optimum activity actually takes place is one in hundred.
 The most likely time (t m): The length of time that will, in all probability, be
required to perform the job under the given circumstances or normal
circumstances.
 The most pessimistic time (t p): This is the longest or maximum probable
time involved if everything that might logically go wrong does actually go
wrong. It includes time for unusual days or unforeseen circumstances. The
chance of its happening might also be one in hundred or very less.

With the help of these above mentioned time estimates i.e. optimistic time,
most likely time, and pessimistic time, average expected time for each activity
would be determined.

Average expected time of the activity= (to+4tm+tp)/6

Procedure followed in PERT

 First of all, the network of activities is drawn to indicate what activity follows
what.
 Then estimation of time to complete each activity is noted on the network.
 Estimation of minimum time taken to complete the project.
 Identification of critical activities and allocation of resources so that project
can be completed in time.
 Calculation of project variability duration and profitability of the project in
given period.
 In order to complete project in time closer watch on critical and other
activities.

Advantages of PERT

1. It is very helpful in determine the schedule for a project within time limit.
2. It helps the management to optimum allocation of resources for the project.

4
NETWORK ANALYSIS

3. It helps in taking right decision for the projects at a right time.


4. It is very helpful in determine the expected duration of activities.
5. It helps the management in handling the uncertainties involved in the project.
6. It helps the management to reduce the risk element in the project.
7. It suggests area of increasing efficiency, decreasing cost and maximizing
profits.
8. It helps in co-coordinating the various activities involved in a project.
9. It enables the use of statistical analysis.
10. It enables a manager to know in advance, where the trouble may occur, where more
supervision needed, and where resources may be transferred to keep the project on
schedule.

Limitations of PERT
Although PERT have many advantages, but it also suffers from certain
limitations. These are:

1. PERT emphasis only on time. It ignores the cost of a project.


2. It cannot be useful for programmes that are indefinite and vague.
3. Assumption of normal probability distribution is not true.
4. It does not consider the matter of resources required for various types of
activities of a project.
5. It seems to be simple but in reality its application is too complex.
6. It is not practicable for routine planning of recurring events.

Example –

Assembling and Erecting the False work for an Elevated Slab will most likely
require 8 days. If all goes well, without interruption, the duration may be cut to
10 days. However, in the practically worst-case scenario, this activity may take 24
days.

Where
Optimistic time= 8 days,
Most likely time = 10 days, and
Pessimistic time = 24 days
PERT weighted average = (8 workdays + 4 X 10 workdays + 24 workdays)/6 =
12 days. Therefore, you’d use 12 days on the network diagram instead of 10
when using PERT for the above example

5
NETWORK ANALYSIS

6
NETWORK ANALYSIS

7
NETWORK ANALYSIS

CPM (CRITICAL PATH METHOD):


Project Another important method of networking is Critical Path Method.
Critical path method was developed in 1956-1957 at the E.I.Dupent Nemours
and Co., USA in connection with the periodic overhauling and maintenance of a
chemical plant. Critical Path Method basically is a special application of analysis
for planning and scheduling. Critical path method was basically developed with
the objective of reducing duration and cost of the project. Critical path method
is a special application of network analysis. It uses network analysis for
scheduling production, construction projects as well as research and
development activities. It is also useful in situations which require estimates of
time and performance. Critical path method deals with repetitive type projects,
such as overhaul of generating plant, which has to be carried repeatedly after
set time intervals.

The critical path, is the overall time, it will take to complete the project. It is
the longest path in time through the network. In other words, the longest path
in the network is called critical path. Identifying the critical path is of great
importance as it determines the duration of entire project. Critical path method
differentiates between the planning and scheduling of the project.

A Critical path method is a very important project management tool used to


formulate a time frame for a project in order to determine where potential
delays are most likely to occur. The process includes a step by step process that
provides the developer with a visual representation of potential bottleneck,
throughout the course of the project.

Identification of the Critical Path: Project CP is the longest time path through
the network. The path can be identified by determining the following
parameters for each activity:

 Earliest start time for activity (ES): It is the earliest possible time at which the
activity should start if only the ongoing activities are first completed.
 Earliest finish time (EF): It is the earliest possible time to finish the activity. It
is equal to the earliest start time for activity plus the time required completing
the activity.
 Latest possible finish time for activity (LF): It is the latest time at which the
activity can be completing without any postpone or within the time framework.

8
NETWORK ANALYSIS

 Latest possible start time for activity (LS): it is the latest start time for an
activity and equal to the latest finish time minus the time required to complete
the activity.
 Slack time: Slack time is the difference between earliest start time for activity
and latest start time for activity, or between earliest finish time for activity and
latest finish time for activity.

Now we will understand it with the help of following example.


Here the information regards the jobs involved in the project with their time
duration. Now we have to find out the earliest possible time for completing the
project.
Time
Job Activity
Duration
A 1-2 6 days
B 2-4 4 days
C 2-3 5 days
D 3-4 4 days
E 4-5 7 days
Total 26

From the given data, we can draw the following network diagram:

9
NETWORK ANALYSIS

In this diagram, the jobs have been shown in the form of arrows leading from
one circle to another. In simple words the arrow connecting circles 1 and 2
represents job A and so on. All the activities have been reduced to a network
diagram together with the information as regard to time required for the
completion of different jobs. In this diagram, there are two paths- the first
connects circles 1, 2, 4, and 5 and takes 17 days. The second path connects
circles 1, 2, 3, 4, and 5 and takes 22 days. The longest path, called the critical
path takes 22 days and hence the minimum time required to complete the
project will be 22 days.

So in order to complete the project within scheduled time, attention will have
to be given to this path since any delay in time on any job or activity in this path
will delay the completion of the project. In case the completion time is to be
reduced, steps will have to be taken to reduce the time required for various
activities of this path.

Advantages of Critical path method

The following are the advantages of CPM:

 It is very useful for scheduling and controlling of large projects.


 It is simple concept and not mathematically complex.
 It is very helpful in pinpoint activities that needed to be closely watched.
 In CPM, Project documentation and graphics point out who is responsible for
various activities.
 It is applicable to a wide variety of projects.
 It is very useful in monitoring schedules and costs.
 It makes better and detailed planning possible.
 It is helpful at many stages of project management.
 It enables standard method for communicating project plans, schedules, time
and cost performance.
 With the help of CPM most critical activities are identified and thus more
attention can be paid to these activities for the successful completion of project.

Limitations of CPM

 It ignores to incorporate statistical analysis in determining the time estimates.

10
NETWORK ANALYSIS

 It is presumed in CPM that there is a precise known time that each activity in
the project will take. But in reality it is not happen.
 Basically it developed as a static planning model and not as a dynamic
controlling device. So it cannot be used as a dynamic controlling device.

8. Similarities between PERT and CPM: PERT and CPM both are the
networking techniques. Both are the important tools of project
implementation. Below are the similarities between PERT and CPM:

 Both PERT and CPM have the same procedure and network diagrams are used
in the both the techniques.
 Both PERT and CPM are used to determine the earliest/latest start and finish
times for each activity.
 Both PERT and CPM techniques help management to plan, schedule and control
the project.
 All significant task and activities are defined in the project by both the
techniques.
 The networking principles used in both the techniques is more or less the same.

Comparison between PERT and CPM

Although both techniques share some common characteristics, yet there are
some differences between them.

 Origin: the origin of PERT is military organization whereas origin of CPM is


chemical plant (industry).
 Uncertainty: in PERT estimates are uncertain whereas in CPM does not allow
any uncertainty.
 Nature: PERT is used for non-repetitive jobs whereas CPM is used for
repetitive jobs.
 Time/Cost: PERT stresses on time based concept whereas CPM stresses
on cost based concept.
 Model: PERT is a probabilistic model whereas CPM is a deterministic model.
 Time estimates: PERT has three time estimates whereas CPM has only one
single estimate of time.
 Critical activities/Dummy activities: in PERT, Critical activities is not used
whereas in CPM dummy activities is not used.

11
NETWORK ANALYSIS

 Suitability: PERT is suitable where high precision is required in time estimates


such as defence projects whereas CPM is suitable where reasonable precision
is required such as civil construction.
 Event /Activity: PERT is an event oriented whereas CPM is an activity oriented.

12

You might also like