revised pppac guidelines
revised pppac guidelines
The Hon’ble FM on 28th June, 2021 while announcing measures for Economic
Relief from COVID-19 Pandemic, observed that the “Current process for approval
of Public Private Partnership (PPP) projects is long and involves multiple levels of
approval. A new policy will be formulated for appraisal and approval of PPP
proposals and monetization of core infrastructure assets, including through InvITs.
The policy will aim to ensure speedy clearance of projects to facilitate private
sector’s efficiencies in financing construction and management of infrastructure.”
The simplification and delegation of the appraisal and approval mechanism for the
PPPAC Guidelines as well as for VGF Scheme and Guidelines is proposed in
pursuance for implementation of the aforesaid announcements.
Provision of quality infrastructure is critical for the economy to attain a higher growth
trajectory on a sustained basis. While stepping up public investments in
infrastructure, the Government has been actively engaged in developing the
appropriate policy framework for private investment in infrastructure projects and
simultaneously keeping adequate checks and balances through transparency,
competition and regulation. Consequently, Public Private Partnerships (PPPs) are
being encouraged for execution and operation of infrastructure projects. In addition
to leveraging public capital to attract private capital and undertaking a larger shelf
of infrastructure projects, PPPs bring in the advantages of private sector expertise
and cost reducing technologies as well as efficiencies in operation and
maintenance.
PPP is an ever-evolving process where relationship between the public and private
sectors alters from time to time. There are a number of legal, social, economic,
political and administrative issues that have a bearing on the success of a PPP in
infrastructure and hence their development requires an enabling eco-system
involving support through proactive planning, policy formulation and regulatory
measures.
PPPAC Guidelines
Guidelines were notified by GoI in 2006 for formulation, appraisal and
recommendation of Central Sector PPP projects in Infrastructure to ensure speedy
appraisal of projects, adopt international best practices and have uniformity in
appraisal mechanism and guidelines. However, in the past 15 years, a lot of activity
and development has been witnessed in the PPP landscape and it appears that
the extant Guidelines require amendment to address these changes. Some of the
issues requiring amendment of the Guidelines have been identified as follows: -
• Multi-Tier Appraisal Requirement: -
At present, the appraisal mechanism prescribed under the Guidelines is m
ulti-tiered with multi-level mutually overlapping system of appraisal based
on Project Cost –
EM Empowered Mechanism
IM Investment Manager
PM Project Manager
“Appointed Date” means the date on which the Concession Agreement comes into full force and
effect in accordance with the terms outlined therein.
“Bid” means the submission made in response to the RFP;
“Bidder” means an entity which has submitted or intends to submit a Bid in response to the RFP;
“Bid Security” means a security furnished by the Bidder to the Contracting Authority to secure the
performance of any obligation under the RFP and includes such arrangements as bank guarantees,
surety bonds, stand-by letters of credit, cheques on which a bank is primarily liable, cash deposits,
promissory notes and bills of exchange;
“Brownfield Asset” means an operational infrastructure project that is generating revenue after
achieving its commercial operation date
“CAPEX” Capital expenditures (CapEx) are funds used by a company to acquire, upgrade, and
maintain infrastructure.
“Concessionaire” means the entity, other than the Contracting Authority, signing the Concession
Agreement.
“Concession Agreement” means the contract entered into between the Contracting Authority and
Selected Bidder for implementing a PPP Project;
“Conditions Precedent” mean the obligations which the Contracting Authority or the Concessionaire
may be required to fulfill prior to financial close/appointed date of the PPP Project, unless waived in
writing by the relevant party in accordance with the terms of the Concession Agreement;
“Contingent Liability” means a liability accruing to a Contracting Authority through the Concession
Agreement or PPP Project on the occurrence or non-occurrence of an uncertain future event.
“Contracting Authority” means the Appropriate Government, or an agency of the Appropriate
Government, or a statutory authority or an entity under control of the Appropriate Government, or a
Central Public Sector Undertaking, which is a signatory to the Concession Agreement.
“Contract Management” means activities of the Contracting Authority relating to supervision of a
PPP or Concession Agreement;
“Empowered Mechanism” means an empowered committee with delegated powers as defined
under these Guidelines for Monetization of Central Sector Core Assets
“Harmonized Master List of Infrastructure Sub Sectors” List of Infrastructure sub sectors as
notified by DEA from time to time.
“InvIT” means a trust registered with SEBI under the SEBI (Infrastructure Investment Trust),
Regulations 2014
“Lead Financial Institution” means the financial institution (Fl) that is funding the PPP project, and
in case there is a consortium of FIs, the Fl designated as such by the consortium.
“Lease” means an agreement whereby the lessor confers to the lessee the right to use an asset for
an agreed period of time in exchange for a consideration
“Model Concession Agreement(s)” or “MCA” are documents approved by the Minister-in-Charge
of the concerned Ministry/Department by the Cabinet, after obtaining concurrence of all such
Ministries/Departments, as are required to be consulted in terms of Rule 4 of the Government of India
(Transaction of Business) Rules, 1961;
“Mandatory Component of a project” means that obligation relating to the asset in a concessional
agreement, any default in construction or operation & maintenance of which leads to termination of
the concession agreement.
“OPEX” These are the expenses incurred on a routine basis for normal business operations.
“PPP Projects” mean projects proposed or being implemented on a Public Private Partnership basis;
“Performance Security” means the bank guarantee furnished by the Concessionaire to the
Contracting Authority for the performance of its obligations under the Concession Agreement at the
rate notified by the Department of Expenditure (DoE) from time to time;
“Public Private Partnership” or “PPP” means an arrangement between the Appropriate
Government or a statutory entity or a government-owned entity or Central Public Sector Undertaking
on one side and a private entity on the other, for the provision of public assets and/or public services,
through investments being made and/or management being undertaken by the private entity, for a
specified period of time, where there is well defined allocation of risk between the private entity and
the public entity and the private entity performances conform (or are benchmarked) to specified and
pre-determined performance standards, measurable by the public entity or its representative.
“Private Sector Company” means a company which is not a Government Company” as defined
under section 2(45) of the Companies Act, 2013.
“Project Term or Concession Period” means the duration of the contract or concession agreement
for the PPP project.
“Project Development Expenses” The expenses incurred by the Sponsoring Authority in respect
of development of a Project.
“Replacement Value” Replacement cost/value is the price that an entity would have to pay to
replace an existing asset with a similar asset at current market prices.
“Request for Proposal” or “RFP” means the Tender Document prepared and issued;
“Request for Qualification” or “RFQ” means the Tender Document prepared and issued;
“REIT” means a trust registered with SEBI under the SEBI (Real Estate Investment Trust),
Regulations 2014
“Sponsoring Authority(ies) (SA)” means the entity which owns the project/assets and/or provides
resources and support for the project and includes Central Government Ministries/Departments,
State Governments, Local Government Bodies, Public Sector Undertakings (PSUs), statutory
authorities or other entities under their administrative control.
“Tender Documents” mean, as applicable, the REOI, RFQ, RTP, RFP, draft Concession
Agreement and any addenda or corrigenda issued by the Contracting Authority in respect thereof
as part of the Tender Proceedings;
“Technical Close” The stage of execution of concession agreement, between the private sector
developer and the Sponsoring Authority or its agencies, subsequent to selection of the private sector
developer through a bidding process
“Total Project Cost” All costs and expenses required for construction of a project, which includes
construction cost, compensation cost, incidental expenses, etc.
“Viability Gap Funding or Grant” means a grant one-time or deferred, provided with the objective
of making a project commercially viable.
I. Guidelines for Formulation, Appraisal and Recommendation of Central Sector Public
Private Partnership Projects in Infrastructure
1. Introduction
1.1 Provision of quality infrastructure is critical for the economy to attain a higher growth trajectory on
a sustained basis. While stepping up public investments in infrastructure, the Government has
been actively engaged in developing the appropriate policy framework for private investment in
infrastructure projects and simultaneously keeping adequate checks and balances through
transparency, competition and regulation. Consequently, Public Private Partnerships (PPPs) are
being encouraged for execution and operation of infrastructure projects. In addition to leveraging
public capital to attract private capital and undertaking a larger shelf of infrastructure projects,
PPPs bring in the advantages of private sector expertise and cost reducing technologies as well
as efficiencies in operation and maintenance.
1.2 PPP is an ever-evolving process where relationship between the public and private sectors alters
from time to time. There are a number of legal, social, economic, political and administrative
issues that have a bearing on the success of a PPP in infrastructure and hence their development
requires an enabling eco-system involving support through proactive planning, policy formulation
and regulatory measures.
1.3 The transactions involved in implementing PPP projects are complex and critical. The high initial
investments, transfer of public assets to the private sector partner for the concession period, the
need to balance the divergent needs of the commercial private interests with the objectives of
inclusive growth underline the criticality of project structuring. In order to make the projects
commercially viable, often, Government viability funding support may also be required. To
achieve economically optimum gains from private participation in infrastructure projects, fair
allocation of risks amongst the private and Government partners and balancing of gains to both
the parties is crucial. Due diligence is also essential given the substantial contingent liability that
could devolve on the State in such projects.
1.4 PPP Infrastructure assets entail a clear need for the government to retain a degree of oversight
and control by way of either contractual mechanisms or regulations. This is because the projects
around these assets typically involve:
• Protection of user interests and the need to secure value for public money
1.5 Recognizing these requirements, guidelines are notified by GoI for formulation, appraisal and
recommendation of Central Sector PPP projects in Infrastructure to ensure speedy appraisal of
projects, adopt international best practices and have uniformity in appraisal mechanism and
guidelines.
1.6 In the light of the above, these Guidelines lay down a system for Formulation, Appraisal and
Recommendation of Central Sector Infrastructure Projects to be undertaken through Public
Private Partnership (PPP).
2. Applicability
2.1 These guidelines will apply to all PPP projects in infrastructure sectors (as per Harmonized Master
list of Infrastructure sub sectors) sponsored by Central Government Ministries/Departments,
Central Public Sector Undertakings (CPSUs), Statutory Authorities or other entities under their
administrative control, unless exempted so by the competent authority.
3. Project Identification
3.1 The sponsoring Ministry will identify the projects to be taken up through PPPs and undertake
preparation of feasibility studies, project agreements, etc. with the assistance of legal, financial
and technical experts as necessary.
3.2 Projects having commercial viability may be preferred to be taken up in PPP mode, rather than
EPC mode. However, even projects which are economically desirable but commercially unviable
may be taken in PPP mode with VGF support.
3.3 Projects fetching benefits for public at large may be the preferred to be undertaken in PPP mode
rather than projects serving only a selected small section of the society.
3.4 Projects meant for serving only a selected small section of the society, may be undertaken in PPP
mode only if it brings good economic rate of return (EIRR) and open up economic development
in that area, which would otherwise not be possible
4. Indicative features of PPP project Structuring
4.3 Target Investor Class - Generally, infrastructure developers, strategic investors with direct
involvement / oversight in operations
4.4 Selection modes - Through an open competitive bidding process and as per prescribed guidelines
of Government
4.5 Contractual aspects - Key performance indicators and clearly defined performance regime with
commensurate incentive or penalty mechanisms, suitable exit provisions, termination and force
majeure provisions
5. Reserve Price
5.1 The Project Sponsoring Ministries/Departments should undertake due diligence about decision
to keep the reserve price keeping in mind having regard to which option will fetch the maximum
value for the government.
5.2 In case, it decides to have the reserve price, the Reserve Price should preferably be determined
after submission of financial bids but before opening of bids.
5.3 The Sponsoring Ministries/Departments should undertake due diligence about decision to make
the reserve price public keeping in mind which option will fetch the maximum value for the
government.
6.1 Committee for appraisal and recommendation of the projects would be as detailed in Annexure - V
of these Guidelines.
6.2 The Committee would be serviced by the Committee Secretariat in the respective
Ministry/Department.
7.1 Sponsoring Ministries/Departments should ensure that the projects submitted for appraisal of
Committee are based on duly approved MCAs (list is attached at Annexure – IV).
7.2 For projects where MCA is not approved, projects may be based on Draft CAs of NITI Aayog
(erstwhile Planning Commission) (list is attached at Annexure – IV). However, efforts should be
made by the Ministry/Department to convert the existing Draft CAs to MCAs before submitting
the proposal for consideration of the Committee. For projects where neither the MCAs nor any
Draft CAs are available, the Ministry/Department should attempt to prepare and approve MCAs
before submitting the project proposal for consideration of the Committee.
7.3 In case of use of the existing Draft CAs/ MCAs without approved RFQ/RFP, Sponsoring
Ministries/Departments should ensure that the projects submitted for consideration of Committee
are based on model RFQ/RFP prepared by the DoE.
7.4 Formulation and approval of MCAs should be completed within six months of notification of these
Guidelines. The Committee may not consider subsequent project proposals in the absence of
approved MCAs.
8. Inter-ministerial Consultations
8.1 The Administrative Ministry may, if deemed necessary, discuss the details of the project and the
terms of concession agreement in an inter-ministerial consultative committee and comments, if
any, may be incorporated or annexed to the proposal for consideration of the Committee.
8.2 There could be projects, which involve more than one Ministry/ Department. While considering
such projects, Committee may seek participation of such Ministries/Departments.
9.1 Appraisal of the Committee is required only once before floating RFP (Request for Proposals),
i.e., invitation to submit financial bids. The Administrative/Sponsoring Ministry/Department shall
appraise the project from all angles including financial viability of the project before submitting the
same to the Committee.
9.2 The proposal for seeking appraisal of Committee shall be sent (in six copies in both hard and soft
form) to the Committee Secretariat in the format specified at Annexure - I along with copies of
all documents as mentioned in the aforesaid Annexure.
9.3 The Administrative Ministry/Department shall submit clearly spelt out deviations in the concession
agreement vis-à-vis, the MCAs/ Draft CAs and Model RFP.
9.4 Committee Secretariat will circulate the copies of Committee Memo and deviation statement and
other associated documents to all Committee Members for appraisal.
9.5 Ministry of Law and Justice, Department of Legal Affairs will appraise the concession agreement
for a careful legal scrutiny.
9.6 NITI Aayog will provide the independent project appraisal note in the format as given in Annexure
– II.
9.7 All Committee Members will forward their respective project appraisal note to the Sponsoring
Authority directly for their replies, under intimation to Committee Secretariat. The Sponsoring
Authority will forward its replies on the comments of Committee members to all members directly,
under intimation to Committee Secretariat.
9.8 The Committee Secretariat shall convene a Meeting of the Committee for consideration of the
project proposal.
9.9 The Committee Secretariat shall submit Project Appraisal Notes the comments of all Committee
Members, and replies thereon of the Sponsoring Authority to the Committee in its Meeting for its
consideration.
9.10 The Sponsoring Authority shall make a presentation to the Committee on the proposal, Appraisal
Notes of the committee members and replies thereof including deviations from model documents.
10.1 Committee will consider and decide the PPP Project proposal of the Administrative
Ministry/Department.
10.2 Committee will either recommend the proposal (with or without modifications) to the Competent
Authority for Appraisal or request the Sponsoring Authority to make necessary changes for further
consideration of Committee.
11.1 Financial bids may be invited after approval of the Competent Authority has been obtained.
However, pending approval of the Competent Authority, financial bids could be invited after
recommendation of Committee has been conveyed.
12.1 Revalidation of its Recommendation by the Committee is not required if post Committee
recommendation:
• Impact of Changes in the following project particulars is less than 20% of originally
recommended: Project cost, Concession terms like concession period, termination payment,
development rights, penalty clauses, tariffs/ user charges.
• Change in date/time period for any timebound actions like appointed date, financial close,
construction period, etc.
12.2 Any changes/modification in the project proposal with the overall objective of making project
successful or within the above-mentioned limits or other project particulars not mentioned above,
shall be appraised at the level of Secretary of the Administrative Ministry/Department without any
need of revalidation by the Committee.
13.1 Once the project is recommended by the Committee, the Sponsoring Authority may follow the
procedure for the approval of the project as per the delegation of powers laid down by Department
of Expenditure from time to time.
13.2 The deviations from the MCAs as recommended by the Appraisal Committee shall be approved
at the level of Minister-in–Charge of the Administrative/ /Department, before submitting the
proposal for approval of Competent Authority. However, for project proposals where the Minister-
in-Charge of the Administrative/Sponsoring Ministry/Department is the Competent Authority for
approval of the project, approval for such deviations from MCAs may be taken up simultaneously
with the project proposal.
13.3 At the time of seeking approval from Competent Authority, the Administrative
Ministry/Department would be required to specifically state all changes in project (if any) made
post recommendation of Committee.
14.1 The time frame for the appraisal of projects under the above procedure is at Annexure III.
15.1 Ministry of Defense, Department of Atomic Energy and Department of Space will not be covered
under the purview of these guidelines.
15.2 Ministry/Department with enhanced delegation of Financial Powers by the Cabinet are exempted
from following the threshold financial criteria for recommendation of the project by the Committee
up to the extent of the enhanced delegated financial powers.
3. Detailed Project Report (Details provided in PPPAC/SFC Memo should be in accordance with
the DPR)
5. Deviation Statement from Model RfP, MCA or draft CA on which project documents are based,
etc.
Annexure - II
1. General Analysis
a. Sectoral Analysis – Rationale/Justification for the project, review of demand-supply
gap, availability of options, etc.
b. PPP model analysis – Rationale / justification for selecting this particular model. Could
there be a better model?
c. Socio-Economic cost-benefits analysis.
2. Financial Analysis:
a. Appraisal of financial indicators (with assumptions) such as NPV, IRR, EIRR and viability
of the project.
b. Appraisal of the project costs and revenue assumptions including recovery of fixed and
variable costs
c. Appraisal of assumptions of funding specially from the point of view of possibility of
financial closure
d. Appraisal of Tariffs/ user charges mechanism including reasonability of Tariffs/ user
charges?
e. Appraisal of the grant component
f. Appraisal of bidding parameters.
g. Value for money and public sector comparator analysis
3. Risk Allocation analysis:
a. Roles and responsibilities of public and private partners.
b. Analysis of service level agreements.
4. Project Document Analysis
a. Deviations from MCA /Draft CA and Model RFP
b. Scrutiny of Project Report for any discrepancies
Annexure – III
Timeframe for various steps under the appraisal procedure for PPP projects
Ministry of Shipping
Ministry of Power
1. Model Bidding Document for Construction & Operations of Power stations (DBFOT)
2. Model Bidding Document for Thermal power Stations on (DBFOO)
3. Model Bidding Document for procurement of power for medium term from power generating
stations set up on (FOO)
4. Model Bidding Document for procurement of peaking power for medium term
5. Model Power Supply Agreement for Generation of Electricity (DBFOO)
6. Model Power Agreement for Procurement of Power (DBFOO basis)
7. Model Power Agreement for Procurement of Power (FOO basis)
8. Model Pilot Agreement for Procurement of Power
9. Model Pilot Power Supply Agreement
Draft Concession Agreements developed by erstwhile Planning Commission and now by NITI
Aayog are as below;
Institutional Structure
NO PPPAC/SFC
CHANGES
RECOMMENDS
YES
SPONSORING MINISTRY
YES UNDERTAKES MATERIAL
CHANGE IN PROJECT SCOPE
OR CONFIGURATION OF
APPROVED DOCUMENTS
NO